Home / Browse projects / Pune, Maharashtra / CASA IMPERIA EWS

Completed No litigation declared Others project

CASA IMPERIA EWS

By Aum Sanskruti Housing

RG-MH-17080 · RERA P52100027706 · Last updated on MahaRERA portal: 8 Oct 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Installation of Lifts, 90%
0 of 28Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

CASA IMPERIA EWS is a Others project by Aum Sanskruti Housing in Pune, Maharashtra, registered with MahaRERA as P52100027706 on 31 Dec 2020. The registration is recorded completed; possession was promised by 20 Mar 2025. The completion date has moved by 30 months from the original filing. 28 of the 28 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameCASA IMPERIA EWS
  • TypeOthers
  • Location
    • WAKADKAR VASTI
    • WAKAD
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027706
  • ReraGenie IDRG-MH-17080

Builder

  • NameAum Sanskruti Housing
  • Entity typePartnership
  • PartnersALPESH JASHUBHAI PATEL, SHARAD NARAYAN MOGALE, KETAN JAYANTILAL VEERA, SRUSHTI RAAKESHH SUREKAA, JETHALAL RATANSHI PATEL, PARESH NANJIBHAI PATEL, RAJESHKUMAR RAGHUBHAI PATEL, GOVERDHANLAL SUKHILAL MAKANI, RAJU SHANKAR VIDHATE, ARVINDKUMAR SHIVJI PATEL, KISHOR SHIVDAS PATEL, CHANDULAL SHIVDASBHAI POKAR and 4 more
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects3 →

Key dates

this monthRegisteredDec 2020First promiseSep 2022Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Dec 2020
  • Promised completion20 Mar 2025
  • Revised completionRevised to 20 Mar 2025 (originally 30 Sep 2022)
  • Buildings1 building record
  • Documents filed114 files

Current status

100%28 of 28 units booked

Figures as on 8 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CASA IMPERIA EWSNA125171128

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

CASA IMPERIA EWS: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 8 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Open Space14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,415 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI22518.0
Proposed, not sanctioned3,398 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAMEER WALIMBE
EngineerKalpesh Zabak
Chartered AccountantAbhishek Godha
Chartered AccountantPriyanka Chordiya
Chartered AccountantSac and co llp
Chartered AccountantForm III Priyanka Chordiya and Associates
PartnerRole in project
Aum Sanskruti Housing-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019821Sep 2022 → Dec 2024

Reason as filed by the promoterProject is already completed but we have not received the completion certificate so we are applying for extension.

EXT52100012586Sep 2022 → Mar 2024

Reason as filed by the promoterDue to funds scarcity and Covid pandemic

EA05082502309Sep 2022 → Mar 2025

Reason as filed by the promoterThis is to state that the project Casa Imperia EWS, bearing MahaRERA Registration No. P52100027706, was completed in all respects before 31.12.2025. Subsequently, the Completion Certificate was issued by the competent authority on 20.03.2025. So we now apply for extension. We have not attached the consent of the allottees, as the entire inventory has been duly handed over to the respective allottees, and possession has been transferred. As the project is already completed and no further development work is pending.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Casa ews Completion final.pdf8 Oct 2025
Occupational CertificateFile: Casa ews Completion final.pdf8 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032025 CASA IMPERIA EWS sign_compressed.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_ Casa Imperia EWS 31032025.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Casa Imperia Ews Sold Unsold Inventory 31032025.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casa Imperia EWS.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CASA Imperia EWS 31122024_compress.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Casa Imperia EWS.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Casa Imperia EWS sign.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30_09_2024 CASA IMPERIA EWS NEW_sign_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2 30_09_2024 EWS.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of units EWS 30_09_2024.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Casa Imperia EWS 31032024_compress.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Aum Sanskruti Housing 10-07-2024.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold EWS 30-06-2024.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CASA IMPERIA EWS 30-06-2024_compressed (1).pdf18 Jul 2024
Declaration in FORM BFile: FORM B DATE OF EXTENSION IS CHANGED.pdf3 Jul 2024
Declaration in FORM BFile: FORM B DATE OF EXTENSION IS CHANGED.pdf29 May 2024
Declaration in FORM BFile: form b casa imperia ews for extension.pdf27 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 casa imperia ews.pdf22 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a casa imperia ews.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: disclosure casa imperia ews 31324.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Casa Imperia EWS 31032024compressed.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sign Form 3 Casa Imperia EWS 31032024 compressed.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a casa imperia ews fy 22 23.pdf7 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM1EWS JULY TO SEPT 23 CASAIMPERIA.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM1 EWS OCT TO DEC23 CASAIMPERIA.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2 31122023 EWS sign_compressed.pdf16 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of units EWS 31122023.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31122023 CASA IMPERIA EWS both sign_compressed.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 CASA IMPERIA EWS_compressed.pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: CASA IMPERIA EWS disclosure sold unsold.pdf1 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 casa imperia ews 30092023 both signed.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_CASA Imperia EWS_FY 22_23.pdf31 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 casa imperia EWS 30032023.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_30062023 EWS.pdf16 Aug 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold 30032023 signed.pdf16 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of units EWS 30062023_sign.pdf16 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CASA IMPERIA EWS_30032023 Both sign_reduce.pdf16 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30062023 CASA IMPERIA EWS_both sign_Reduce.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 casa imperia EWS 31122022.pdf2 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CASA IMPERIA EWS 31-12-2022 both sign_compressed.pdf2 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 3 Engineers Certificate on Quality Assurance fy1920.pdf17 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 3 Engineers Certificate on Quality Assurance fy2021.pdf17 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3 Engineers Certificate on Quality Assurance fy2122.pdf17 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold parking 3009.pdf8 May 2023
Declaration in FORM BFile: 3 Declaration in FORM B.pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf6 May 2023
Disclosure of sold/ booked inventoryFile: 1 Disclosure of sold_ booked inventory.pdf6 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2a fy 19-20.pdf4 May 2023
Declaration in FORM BFile: From B Declaration Casa imperia EWS FINAL.pdf8 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 300922 both signed_compressed.pdf21 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 300922 both signed_compressed.pdf21 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A fy 20 21 both signed_compressed.pdf21 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A fy 21 22 both signed_compressed.pdf21 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: fomr 2a 20-21 casa imperia ews.pdf16 Mar 2023
CERSAI detailsFile: cersai 59-1-b.pdf16 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200263155922_For_Asset_Based_Search_16_03_2023_15_01_49_693.pdf16 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200263155053_For_Asset_Based_Search_16_03_2023_14_57_14_364.pdf16 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of partners merged (1).pdf16 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of partners merged (2)_compressed.pdf16 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of partners merged (3)_compressed.pdf16 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of partners merged (4).pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-1-4_compressed.pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-5-8_compressed.pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-9-12_compressed.pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-13-16_compressed (1).pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-17-20_compressed.pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-21-23.pdf16 Mar 2023
Proforma of Agreement for saleFile: SKM_C454e22120807390-24-26.pdf16 Mar 2023
Other - TechnicalFile: plinth completion letter doc.pdf16 Mar 2023
Declaration in FORM BFile: Form B Declaration Casa imperia EWS.pdf8 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casa Imperisa EWs 31-03-22_compressed.pdf8 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casa Imperisa EWs 30-06-22_compressed.pdf8 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casa Imperisa EWs 30-09-22_compressed.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Casa Imperisa EWS 30-06-22_compressed.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Casa Imperisa EWS 30-09-22_compressed.pdf8 Feb 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
CASA IMPERIA PHASE 3WAKADKAR WASTI WAKAD PIMPRI CHINCHWAD PUNE 5794CompletedOct 2020Jul 2020
CASA IMPERIA PHASE 2WAKADKAR WASTI WAKAD PIMPRI CHINCHWAD PUNE 57141CompletedJun 2015Dec 2014
CASA IMPERIA PHASE 1WAKADKAR WASTI WAKAD PIMPRI CHIMCHWAD PUNE 57161CompletedSep 2014Apr 2014

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CASA IMPERIA EWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAKAD13,700+ in Pune

2 kmCASA IMPERIA EWSCompleted 120Lapsed / revoked 52Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 252 registered projects within 2 km.

Builder: Aum Sanskruti Housing

Aum Sanskruti Housing has 2 registrations on MahaRERA, including CASA IMPERIA EWS and CASA IMPERIA. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if CASA IMPERIA EWS is delayed beyond 20 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CASA IMPERIA EWS?

The registered promoter entity is Aum Sanskruti Housing, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CASA IMPERIA EWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CASA IMPERIA EWS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CASA IMPERIA EWS?

The professionals named in the filing: Architect: SAMEER WALIMBE; Engineer: Kalpesh Zabak; Chartered Accountant: Abhishek Godha; Chartered Accountant: Priyanka Chordiya; Chartered Accountant: Sac and co llp; Chartered Accountant: Form III Priyanka Chordiya and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASA IMPERIA EWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASA IMPERIA EWS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASA IMPERIA EWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.