Completed No litigation declared Residential / Group Housing project

Carmichael Residences

By R A Realty Ventures LLP

RG-MH-20908 · RERA P51900001442 · Last updated on MahaRERA portal: 19 Feb 2020

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Sep 2019Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 98%
1Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

Carmichael Residences is a Residential / Group Housing project by R A Realty Ventures LLP in Malabar Cumballa Hill, 400026, registered with MahaRERA as P51900001442 on 28 Jul 2017. The registration is recorded completed; possession was promised by 30 Sep 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCarmichael Residences
  • TypeResidential / Group Housing
  • Location
    • Carmichael Road
    • Malabar Cumballa Hill
    • 400026
  • Pincode400026
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900001442
  • ReraGenie IDRG-MH-20908

Builder

  • NameR A Realty Ventures LLP
  • Entity typePartnership
  • PartnerRajendrakumar Kothari

Key dates

this monthRegisteredJul 2017First promiseSep 2018Revised toSep 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Jul 2017
  • Promised completion30 Sep 2019
  • Revised completionRevised to 30 Sep 2019 (originally 30 Sep 2018)
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Carmichael ResidencesNA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 98%.

Carmichael Residences: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 19 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes35%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed86

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots86
Closed/Covered86

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,017 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9022.13
Proposed, not sanctioned9,022 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANEKJI WADIA BLDG, GROUND FLOOR, NANIK MOTWANI MARG, FORT MUMBAI MAHARASHTRA 400001

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIrani Architects
PartnerRole in project
R A Realty Ventures LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900000646Sep 2018 → Sep 2019

Reason as filed by the promoterDetailed application for extention is uploded hereunder along with documents supporting the grounds and reasons thereof. the three main reasons for which extension of Registration is sought: A. Issues with adjoining society namely, Anand Kamal Co-operative Housing Society Ltd (“Society”), in relation to relocation of pipelines supplying drinking water, pump room and sewerage lines of the Society. These pipelines and pump room were, at the relevant time, located on our project where the proposed Storm water drainage pipeline and Sewer pipeline connections of Promoter’s project were to be constr

Litigation declared2

CaseCourtStatus
PIL/48/2016/2016High Court of BombayDISPOSED OF
009044/ 2019/2019Supreme Court of IndiaDISPOSED OF

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12504032Rajendrakumar KothariVandana Jatia Family Trust15/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Feb 2020

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 4)File: Form 4 - Architect`s Certificate 15 02 2020.pdf19 Feb 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Carmichael OC.pdf4 Feb 2020
Certificates of Architect (Form 4)File: download (1).pdf4 Feb 2020
Proforma of Allotment letterFile: Carmichael_Deed of Conveyance_final for upload_30092019.pdf30 Sep 2019
Details of encumbrancesFile: Updated Encumbrance - RA Realty.pdf29 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert Carmichael residences-compressed June 19.pdf19 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Carmicheal road 30 June 2019.pdf18 Jul 2019
Certificates of CA (Form 3)File: Form 3 CA Certificate - Carmichael Residences.pdf3 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Carmichael Engineer March 19.pdf2 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Carmicheal road March 2019.pdf24 Apr 2019
Certificates of CA (Form 3)File: Form 3 CA Certificate - Carmichael Residences.PDF16 Feb 2019
Form 2AFile: Carmichael quality-compressed.pdf25 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect`s Certificate Carmichael 31 December 2018.pdf24 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Carmichel Dec 31.pdf24 Jan 2019
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Sep'2018.PDF23 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect`s Certificate Carmichael road 30 September 2018.pdf25 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate CMR 30th sept.pdf25 Oct 2018
Certificates of CA (Form 5)File: Form 5 - Annual Report on Statement of Accounts.PDF12 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Cert Carmichael 15 Sept 2018.pdf20 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Cert Carmichael 15 Sept 2018.pdf20 Sep 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Carmichael Road.PDF9 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Carmicheal road June 18.pdf19 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Carmichael June'18.pdf19 Jul 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Carmichael Road.PDF25 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate _ Carmicheal road March 2018.pdf3 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Carmichael.pdf3 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Carmichael_FCC.pdf3 Mar 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Dec'17 - Compressed.PDF7 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CMR Architects Certificate - Dec 17.pdf30 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Carmicahel 31st dec Engineer Certificate.pdf30 Jan 2018
Certificates of Architect (Form 4)File: Architect's Certificate _ Carmichael Residences Sep 17.pdf24 Oct 2017
Layout approvalFile: Approved Layout Plan CMR.pdf25 Jul 2017
Building plan approvalFile: Amended Approval Letter CMR.pdf25 Jul 2017
Building plan approvalFile: I O D CMR Compressed.pdf25 Jul 2017
PAN CardFile: Pan Card - RA Realty.pdf25 Jul 2017
Copy of the legal title reportFile: T Report Carmichael part I.pdf25 Jul 2017
Copy of the legal title reportFile: T Report Carmichael part II.pdf25 Jul 2017
Copy of the legal title reportFile: T Report Carmichael part III.pdf25 Jul 2017
Copy of the legal title reportFile: T Report Carmichael part IV.pdf25 Jul 2017
Copy of the legal title reportFile: Supplemental Title Certificate.pdf25 Jul 2017
Details of encumbrancesFile: List of Encumbrances - R A Reality Ventures LLP.PDF25 Jul 2017
Copy of Layout Approval (in case of layout)File: Approved Layout Plan CMR.pdf25 Jul 2017
Building Plan Approval (IOD)File: I O D CMR Compressed.pdf25 Jul 2017
Building Plan Approval (IOD)File: Amended Approval Letter CMR.pdf25 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration - RA.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate CMR.pdf25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate CMR.pdf25 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf25 Jul 2017
Proforma of Allotment letterFile: Carmichael Residences-AFS-25072017.pdf25 Jul 2017

Keep Carmichael Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malabar Cumballa Hill

2 kmCarmichael ResidencesCompleted 5Lapsed / revoked 2Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: R A Realty Ventures LLP

R A Realty Ventures LLP has 1 registration on MahaRERA, including Carmichael Residences. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if Carmichael Residences is delayed beyond 30 Sep 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Carmichael Residences?

The registered promoter entity is R A Realty Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Carmichael Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Carmichael Residences?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Carmichael Residences?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Carmichael Residences?

The professionals named in the filing: Architect: Irani Architects. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Carmichael Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Carmichael Residences. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Carmichael Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.