Home / Browse projects / Pune, Maharashtra / BUSINESS HUB
BUSINESS HUB
RG-MH-58630 · RERA P52100047555 · Last updated on MahaRERA portal: 4 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BUSINESS HUB is a Commercial project by Rajendra Venkat Reddy in Pune, Maharashtra, registered with MahaRERA as P52100047555 on 9 Nov 2022. Possession is promised by 27 Jul 2028. The completion date has moved by 36 months from the original filing. 2 of the 2 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameBUSINESS HUB
- TypeCommercial
- Location
- JUPITAR HOSPIAL
- BANER
- Haveli
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047555
- ReraGenie IDRG-MH-58630
Builder
- NameRajendra Venkat Reddy
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Nov 2022
- Promised completion27 Jul 2028
- Revised completionRevised to 27 Jul 2028 (originally 25 Jul 2025)
- Buildings1 building record
- Documents filed138 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Business HUB | NA | 8 | 3 | 0 | 2 | 2 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Business HUB: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed145
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Rajendra Venkat Reddy | Baner | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Business HUB | NA | Rs 12.43 cr | Rs 10.71 cr |
| - | NA | Rs 2.26 cr | Rs 91.39 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vilas Tarawadi |
| Engineer | DEEPAK KUMAR SINGH DEEPAK KUMAR SINGH |
| Chartered Accountant | CA Shriram G Somwanshi |
| Partner | Role in project |
|---|---|
| Rajendra Venkat Reddy | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterInitially the project was planned and registered based on initial sanction form competent authority. Subsequent to the initial sanction plan and commencement of construction, we have undertaken the additions to the project area. Revised sanction plant attached along with application. Considering the above genuine and unforeseen circumstances arising from the sanctioned addition in the project area, it is not feasible to complete the entire project by the currently registered completion date. However, due to a significant and unforeseen addition in the project's overall area and scope, we requi
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Mar 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Mar 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 27 Jul 2028
Documents filed138
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Signed_Form1_Q1.pdf | 4 Aug 2026 |
| Withdrawal Update Form 2File: Signed_Form2_Q1.pdf | 4 Aug 2026 |
| Withdrawal Update Form 3File: Signed_Form3_Q1.pdf | 4 Aug 2026 |
| Withdrawal Update Form 1File: Signed_Form1_Q3.pdf | 10 Jun 2026 |
| Withdrawal Update Form 1File: Signed_Form1_Q4.pdf | 10 Jun 2026 |
| Withdrawal Update Form 2File: Signed_Form2_Q3.pdf | 10 Jun 2026 |
| Withdrawal Update Form 2File: Signed_Form2_Q4.pdf | 10 Jun 2026 |
| Withdrawal Update Form 3File: Signed_Form3_Q3.pdf | 10 Jun 2026 |
| Withdrawal Update Form 3File: Signed_Form3_Q4.pdf | 10 Jun 2026 |
| Withdrawal Update Form 1File: Form 1_Q2_FY 2025-26.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2_Q2_FY 2025-26.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form 3 Q2.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1_Q2_FY 2025-26.pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: Form 2_Q2_FY 2025-26.pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 18 Feb 2026 |
| Withdrawal Update Form 1File: Annexre-1 Arch cert BH-30-6-25.pdf | 1 Sep 2025 |
| Withdrawal Update Form 2File: ENGG-CERT-BH-30-6-25.pdf | 1 Sep 2025 |
| Withdrawal Update Form 3File: Final Form 3.pdf | 1 Sep 2025 |
| Form 2A (FY 2022-2023)File: FORM 2A-BH-22-23.pdf | 29 Aug 2025 |
| Form 2A (FY 2023-2024)File: FORM -2A-BH-23-24.pdf | 29 Aug 2025 |
| Form 2A (FY 2024-2025)File: FORM2A-BH-24-25.pdf | 29 Aug 2025 |
| Form 5 (FY 2023-2024)File: Business Hub Form 5 FY 2023-24-signed.pdf | 29 Aug 2025 |
| Form 5 (FY 2022-2023)File: Business Hub Form 5 FY 2022-23-signed.pdf | 28 Aug 2025 |
| Form 1File: Form 1 Q3 22-23.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q3 22-23.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q3 FY 2022-23.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q3 FY 2022-23.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form Q3 FY 2022-23.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q4 22-23.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q4 22-23.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q4 FY 2022-23.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sold & Unsold Inventory Q4 FY 22-23.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration Form Q4 FY 2022-23.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q1 23-24.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q1 23-24.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q1 FY 2023-24.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q1 FY 23-24.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form Q1 FY 23-24.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q2 23-24.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q2 23-24.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q2 FY 2023-24.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q2 FY 23-24.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form Q2 FY 23-24.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q3 23-24.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q3 23-24.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q3 FY 2023-24.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q3 FY 23-24.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form Q3 FY 23-24.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q4 23-24.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q4 23-24.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q4 FY 2023-24.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q4 FY 23-24.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q1 24-25.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q1 24-25.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q1 FY 2024-25.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q1 FY 24-25.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q2 24-25.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q2 24-25.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q2 FY 2024-25.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q2 FY 24-25.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Promoter Self Declaration Form.pdf | 9 Jun 2025 |
| Form 1File: Form 1 Q3 24-25.pdf | 9 Jun 2025 |
| Form 2File: Form 2 Q3 24-25.pdf | 9 Jun 2025 |
| Form 3File: Form 3 Q3 FY 2024-25.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold & Unsold Inventory Q3 FY 24-25.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Self-declaration-31-12-24.pdf | 9 Jun 2025 |
| Form 1File: architect Cert- BH-31-3-25.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect Cert- BH-31-3-25.pdf | 7 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 Q4 FY 2024-25.pdf | 7 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg-bh-31-3-25-business HUb.pdf | 7 May 2025 |
| Other - TechnicalFile: Signed RERA CONSENT LETTER - 140.pdf | 27 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5_FY2022-23.pdf | 10 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_FY2023-24.pdf | 10 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 22-23.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 23-24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 23-24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 23-24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 23-24.pdf | 6 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 138 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BUSINESS HUB on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BANER13,700+ in Pune
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: Rajendra Venkat Reddy
Rajendra Venkat Reddy has 1 registration on MahaRERA, including BUSINESS HUB. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if BUSINESS HUB is delayed beyond 27 Jul 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BUSINESS HUB?
The registered promoter entity is Rajendra Venkat Reddy, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BUSINESS HUB?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BUSINESS HUB?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BUSINESS HUB?
The professionals named in the filing: Architect: Vilas Tarawadi; Engineer: DEEPAK KUMAR SINGH DEEPAK KUMAR SINGH; Chartered Accountant: CA Shriram G Somwanshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BUSINESS HUB?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback