Home / Browse projects / Pune, Maharashtra / BUILDING NO. A1 -NAVYANGAN PHASE - II

Registration lapsed No litigation declared Residential / Group Housing project

BUILDING NO. A1 -NAVYANGAN PHASE - II

By AVIOR MERLIN VENTURE LLP

RG-MH-15833 · RERA P52100024143 · Last updated on MahaRERA portal: 10 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 16%
110 of 110Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

BUILDING NO. A1 -NAVYANGAN PHASE - II is a Residential / Group Housing project by AVIOR MERLIN VENTURE LLP in Pune, Maharashtra, registered with MahaRERA as P52100024143 on 21 Jan 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 0 of the 110 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameBUILDING NO. A1 -NAVYANGAN PHASE - II
  • TypeResidential / Group Housing
  • Location
    • -
    • PAUD ROAD
    • Kasar Amboli
    • Mulshi
    • Pune
    • 412108
  • Pincode412108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024143
  • ReraGenie IDRG-MH-15833

Builder

  • NameAVIOR MERLIN VENTURE LLP
  • Entity typePartnership
  • PartnersAVIOR ENTERPRISES LLP THROUGH SUNIL SOMANI, SUNIL CHAMPALAL SOMANI, SHAM BHAGWANDAS LADDHA, RADHA KISAN LADDHA, SAKET SUSHIL MOHTA, KAMLESH BALDEV JHAWAR
  • Other registrations4 more →
  • No longer live5 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

10 months past promisethis monthRegisteredJan 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed99 files

Current status

0%0 of 110 units booked
0.0%Work done, per cost certificate

Figures as on 10 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING - A1NA15141100110

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 16%.

BUILDING - A1: 38% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure16%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area647 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
SAHADEV MARUTI DHUMALKasar AmboliPune
DATTATRYA BAJIRAO SUTARKasar AmboliPune
ARUNCHANDRAKANT BHILAREKasar AmboliPune
NATHU KERU BHILAREKasar AmboliPune
RAMAKANT RAMCHANDRA DHIDEKasar AmboliPune
BABAN PANDHARINATH BHILAREKasar AmboliPune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI6262.55
Proposed, not sanctioned6,263 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVAJI NAGAR, PUNE
Estimated costRs 17.15 cr
Work done0.0%
BuildingWingEstimatedIncurred
BUILDING - A1NARs 14.55 cr-
-NARs 2.61 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCH SANDEEP HARDIKAR AND ASSOCIATES
EngineerParimal Dongre
EngineerVINOD KATHARE
EngineerChandrakant Deshpande
EngineerKedari kakatkar
Chartered AccountantRMS & Associates
Chartered AccountantSpak & Co
Chartered AccountantUmesh Jhawar & Associates
PartnerRole in project
AVIOR MERLIN VENTURE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 A 1.pdf10 Nov 2025
Withdrawal Update Form 2File: Form2 A1.pdf10 Nov 2025
Withdrawal Update Form 3File: Form 3 A1.pdf10 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A - Nav - A1 - Mar 25.pdf16 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A1 - Mar 25.pdf22 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A1 - Mar 25_compressed.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1 - Mar 25.pdf22 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure A1 - Mar 25_compressed.pdf22 May 2025
Form 1File: FORM 1 A1 - Mar 25.pdf19 May 2025
Form 2File: FORM 2 A1 - Mar 25.pdf19 May 2025
Form 3File: FORM 3 A1 - Mar 25_compressed.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: Disclosure A1 - Mar 25_compressed.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A1 - Dec 24.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A1 - Dec 24.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1 - Dec 24.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure A1 - Dec 24.pdf1 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - AMV A1 - 2023-2024.pdf30 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A1 - Sept 24.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A1 - Sept 24.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1 - Sept 24.pdf21 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure A1 - Sept 24.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A1 - Jun 24.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1 - Jun 24.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure A1 - Jun 24.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A1 - Jun 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A1 - Jun 24.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A1 - Jun 24.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A1 - Jun 24.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure A1 - Jun 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nav A-1- Mar 24.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nav A1 - Mar 24.pdf15 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Navyangan-Ph-2 -A1 - Mar 24.pdf15 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-Mar -24.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-Mar-24_compressed.pdf15 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Dec- 23.pdf15 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nav A-1 - Dec 23.pdf1 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nav A1 - Dec 23_compressed.pdf1 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-Dec -23.pdf1 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-Dec-23_compressed.pdf1 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nav A-1 - Sept 23.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nav A1 - Sept 23.pdf22 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Sept- 23.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-Sept -23_compressed.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-Sept-23_compressed.pdf22 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - AMV A1 - 2022-2023.pdf28 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nav A-1 - Mar 23.pdf24 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nav A-1 - Jun 23.pdf24 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nav A1 - Mar 23.pdf22 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nav A1 - Jun 23.pdf22 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Mar- 23.pdf22 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-Mar-23.pdf22 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-Jun -23.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-Mar-23_compressed.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-JUN-23.pdf22 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Jun- 22.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Sept- 22.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Nav-A1- Dec- 22.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Nav A1 - Jun-22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Nav A1 - SEP-22.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Nav A1 - DEC-22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Engineer Certificate AMV-A1-JUNE 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Engineer Certificate AMV-A1-Sept 22.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Engineer Certificate AMV-A1-DEC 22.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-JUN-22.PDF11 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-SEPT-22.PDF11 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure -AMV-A1-DEC-22.PDF11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-JUN-22.pdf11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-SEPT-22.pdf11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-AMV-A1-DEC-22.pdf11 Jul 2023
Declaration about Commencement CertificateFile: Bldg - A1 - Declaration about CC.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Navyangan A1 - DEC 2021.pdf15 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Navyangan A1 - MAR 2022.pdf15 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure - AMV - A1 - Mar -22.pdf15 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 - AMV - A1 - Mar - 22.pdf15 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From - 5 - AMV - A-1 - 2021-2022.pdf15 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form - 2A - A1 - Jun - Sept -21.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A Certificate - A1 - SEP 2021.pdf4 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A Certificate - D1 - SEP 2021.pdf16 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A Certificate - A1 - SEP 2021.pdf16 Oct 2021
Disclosure of sold/ booked inventoryFile: Building - A1-Navyangan - Phase 2.pdf16 Jun 2021

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Prakriti -D- NavyanganKASAR AMBOLI MULSHI136CompletedMar 2019Late, May 2019
Prakriti -C- NavyanganKASAR AMBOLI MULSHI95CompletedOct 2017Late, Nov 2017
Nikunj NavyanganKASAR AMBOLI MULSHI244CompletedOct 2017Late, Nov 2017

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BUILDING NO. A1 -NAVYANGAN PHASE - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PAUD ROAD13,700+ in Pune

2 kmBUILDING NO. A1 -NAVYANGCompleted 21Lapsed / revoked 17Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: AVIOR MERLIN VENTURE LLP

AVIOR MERLIN VENTURE LLP has 5 registrations on MahaRERA, including AMENITY SPACE 1 - NAVYANGAN PHASE - II and BUILDING - D- WING -D-1- NAVYANGAN PHASE - II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BUILDING NO. A1 -NAVYANGAN PHASE - II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BUILDING NO. A1 -NAVYANGAN PHASE - II is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BUILDING NO. A1 -NAVYANGAN PHASE - II?

The registered promoter entity is AVIOR MERLIN VENTURE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BUILDING NO. A1 -NAVYANGAN PHASE - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BUILDING NO. A1 -NAVYANGAN PHASE - II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BUILDING NO. A1 -NAVYANGAN PHASE - II?

The professionals named in the filing: Architect: ARCH SANDEEP HARDIKAR AND ASSOCIATES; Engineer: Parimal Dongre; Engineer: VINOD KATHARE; Engineer: Chandrakant Deshpande; Engineer: Kedari kakatkar; Chartered Accountant: RMS & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BUILDING NO. A1 -NAVYANGAN PHASE - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BUILDING NO. A1 -NAVYANGAN PHASE - II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BUILDING NO. A1 -NAVYANGAN PHASE - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.