ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / BUILDING A1-SHREE KRUPA HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

BUILDING A1-SHREE KRUPA HEIGHTS

By SHREE KRUPA BUILDERS AND DEVELOPERS

RG-MH-28363 · RERA P51700025692 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
12 of 39Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 132 documents Report an error

BUILDING A1-SHREE KRUPA HEIGHTS is a Residential / Group Housing project by SHREE KRUPA BUILDERS AND DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700025692 on 3 Jul 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 48 months from the original filing. 27 of the 39 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameBUILDING A1-SHREE KRUPA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • TISGAON ROAD
    • TISGAON
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700025692
  • ReraGenie IDRG-MH-28363

Builder

  • NameSHREE KRUPA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersSUNIL VASANT GAIKWAD, SURYAKANT VASANT GAIKWAD
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredJul 2020First promiseJun 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Jul 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed132 files

Current status

69%27 of 39 units booked
100.0%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING A1NA7739039

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

BUILDING A1: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Open Space15

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,141 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Oct 2025
LandownerVillageDistrict
SAVITRIBAI VASANT GAIKWADTisgaonThane

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI1300.0
Proposed, not sanctioned1,300 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYAN EAST
Estimated costRs 6.15 cr
Cost incurredRs 6.15 cr
Work done100.0%
BuildingWingEstimatedIncurred
BUILDING A1NARs 5.01 crRs 5.01 cr
-NARs 1.13 crRs 1.13 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVARGHESE JOHN
EngineerMANOHAR PATIL
Chartered AccountantABHAY UPADHYAY
Chartered AccountantVINESH AHUJA
Chartered AccountantDEEPAK DADLANI
PartnerRole in project
SHREE KRUPA BUILDERS AND DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012716Jun 2022 → Dec 2023

Reason as filed by the promoterIn view of the Covid-19 pandemic, situations have become very uncertain leading number of stalled projects losing customer confidence. This situation made homebuyers to adopted wait and watch awaiting further correction in prices. The Real Estate is currently in crisis, reduced demand, liquidity crunch, lending, and non-banking credit flow dried-up dramatically, Besides the low local demand the capital inflow into Housing Sector from Investors no longer forthcoming as this class turned cautious. This concern is no different than the other stake holders and pandemic has affected our project too

EXT51700019023Jun 2022 → Jun 2024

Reason as filed by the promoterAs per consent attached.

EA03122518506Jun 2022 → Jun 2026

Reason as filed by the promoterProject shall be completed and OC shall be processed within the requested extension period.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jun 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jun 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed132

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Shree krupa.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2 Shree Krupa.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 signed.pdf24 Jul 2026
Form 2A (FY 2025-2026)File: 2A 25-26.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1 Q3.pdf8 May 2026
Withdrawal Update Form 1File: Form 1 Q4.pdf8 May 2026
Withdrawal Update Form 2File: Form 2 Q3.pdf8 May 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 Q3 Final.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 q4 final.pdf8 May 2026
Form 1File: Form 1 Mar 25.pdf24 Apr 2026
Form 2File: Form 2 Mar 25.pdf24 Apr 2026
Form 3File: Form 3 Mar 25 signed.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold signed 1.pdf24 Apr 2026
Form 1File: Form 1 Dec 24.pdf24 Apr 2026
Form 2File: Form 2 Dec 24.pdf24 Apr 2026
Form 3File: Form 3 Dec 24.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: sold unsold dec 24.pdf24 Apr 2026
Form 1File: Form 1 Sep 24.pdf24 Apr 2026
Form 2File: Form 2 Sep 24.pdf24 Apr 2026
Form 3File: Form 3 signed.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold sep 24.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 jun 25.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 sep 25.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Jun 25.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Sep 25.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 Jun 25.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 sep 25.pdf24 Apr 2026
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf3 Dec 2025
Form 2File: Form 2 Dec 23.pdf3 Dec 2025
Form 3File: Form 3 Dec 23.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 23 signed.pdf3 Dec 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf3 Dec 2025
Form 2File: Form 2 Dec 23.pdf3 Dec 2025
Form 3File: Form 3 Dec 23.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 23 signed.pdf3 Dec 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf3 Dec 2025
Form 2File: Form 2 Dec 23.pdf3 Dec 2025
Form 3File: Form 3 Dec 23.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 23 signed.pdf3 Dec 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf3 Dec 2025
Form 2File: Form 2 Dec 23.pdf3 Dec 2025
Form 3File: Form 3 Dec 23.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 23 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf3 Dec 2025
Form 2File: Form 2 Dec 23.pdf3 Dec 2025
Form 3File: Form 3 Dec 23.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 23 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025
Form 1File: Form 1 signed.pdf3 Dec 2025
Form 2File: Form 2 signed.pdf3 Dec 2025
Form 3File: Form 3 signed.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 22 signed.pdf3 Dec 2025

How this compares with Thane

69%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 48 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BUILDING A1-SHREE KRUPA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TISGAON7,600+ in Thane

2 kmBUILDING A1-SHREE KRUPA Completed 63Lapsed / revoked 44Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 212 registered projects within 2 km.

Builder: SHREE KRUPA BUILDERS AND DEVELOPERS

SHREE KRUPA BUILDERS AND DEVELOPERS has 3 registrations on MahaRERA, including BUILDING A1-SHREE KRUPA HEIGHTS and SHREE SAHAWAS CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that BUILDING A1-SHREE KRUPA HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BUILDING A1-SHREE KRUPA HEIGHTS is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BUILDING A1-SHREE KRUPA HEIGHTS?

The registered promoter entity is SHREE KRUPA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BUILDING A1-SHREE KRUPA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BUILDING A1-SHREE KRUPA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BUILDING A1-SHREE KRUPA HEIGHTS?

The professionals named in the filing: Architect: VARGHESE JOHN; Engineer: MANOHAR PATIL; Chartered Accountant: ABHAY UPADHYAY; Chartered Accountant: VINESH AHUJA; Chartered Accountant: DEEPAK DADLANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BUILDING A1-SHREE KRUPA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BUILDING A1-SHREE KRUPA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BUILDING A1-SHREE KRUPA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.