Home / Browse projects / Pune, Maharashtra / BROADWAY INTEGRATED PARK LLP - TOWER 1

De-registered No litigation declared Commercial project

BROADWAY INTEGRATED PARK LLP - TOWER 1

By BROADWAY INTEGRATED PARK LLP

RG-MH-43749 · RERA P52100048283 · Last updated on MahaRERA portal: 19 Oct 2024

Source: official MahaRERA filing

Red flags

  • De-registered

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 90%
0Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

BROADWAY INTEGRATED PARK LLP - TOWER 1 is a Commercial project by BROADWAY INTEGRATED PARK LLP in Pune, Maharashtra, registered with MahaRERA as P52100048283 on 22 Dec 2022. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameBROADWAY INTEGRATED PARK LLP - TOWER 1
  • TypeCommercial
  • Location
    • TATHWADE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • RERA no.P52100048283
  • ReraGenie IDRG-MH-43749

Builder

  • NameBROADWAY INTEGRATED PARK LLP
  • Entity typeOthers
  • GSTIN27AAQFB2188L1ZV
  • Named personsSAMEER SHANTILAL MUTTHA, SHANTILAL GULABCHAND MUTTHA

Key dates

this monthRegisteredDec 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on22 Dec 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed134 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1NA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 90%.

TOWER 1: 8% average across the applicable activities

ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,188 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Sep 2024

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI53469.0
Proposed, not sanctioned53,469 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPimpri Chinchwad, Pune

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShitesh Agrawal Agrawal
ArchitectAR. Sourabh Laghate
EngineerHariharan Iyer Iyer
Chartered AccountantCA Paresh Sabadra Prakash SABADRA
Chartered AccountantPRAKASH SABADRA
Chartered AccountantSuchita Pawar
PartnerRole in project
BROADWAY INTEGRATED PARK LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Final.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate final.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Final.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate final.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Final.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate final.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Broadway-RA_23-24_Old signed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Broadway-RA_23-24_Old signed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Broadway-RA_23-24_Old signed.pdf7 Oct 2024
Form 5 (FY 2022-2023)File: Form 5_RERA audit_FY-22-23.pdf25 Sep 2024
Form 5 (FY 2023-2024)File: Form 5_Broadway_23 24_Signed.pdf19 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_ Signed.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Signed.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Broadway Signed.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Signed copy.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf20 Apr 2024
Other - TechnicalFile: Form 2A.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate -March-24 Sign Copy.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- March-24 Sign Copy.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- March-24 Sign Copy.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate- March-24 Sign Copy.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 23_Signed.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate -BIPL tower Signed.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Broadway Integrated Park LLP - Tower 1.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Broadway_Dec 23_Signed.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Tower 1-30 09 23 SSM SIGN.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - BIPP_Sept 23.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Sept 23.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Broadway_Sept 23_SSM Signed.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_RERA audit_FY-22-23.pdf13 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate-30 06 23 SSM SIGN.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-30 06 23 SSM SIGN.pdf18 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 30 06 23 SIGN.pdf18 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-Tower 1-30 06 23 SSM SIGN.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Scan Copy-31 03 23 SSM Sign.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate SSM Sign_compressed.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold - Booked.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_31 03 23 SSM Sign.pdf20 Apr 2023
Other - TechnicalFile: Quality certificate 17-4-2023 SSM Sign.pdf20 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank account Declaration indusind.pdf24 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Broadway CA Cert_Signed.pdf19 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SGM-Disclosure of Interest in Other Real Estate Organizations-Broadway Integrated Park LLP19 Jan 2023
CERSAI detailsFile: CERSAI.pdf13 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf10 Dec 2022
Layout approvalFile: Plan 1 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 2 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 3 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 4 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 5 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 6 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 7 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 8 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 9 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 10 of 33 (2).pdf22 Nov 2022
Building plan approvalFile: Plan 11 of 33 (2).pdf22 Nov 2022
Building plan approvalFile: Plan 12 of 33 (2).pdf22 Nov 2022
Building plan approvalFile: Plan 13 of 33 (2).pdf22 Nov 2022
Building plan approvalFile: Plan 14 of 33 (2).pdf22 Nov 2022
Building plan approvalFile: Plan 15 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 16 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 17 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 18 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 19 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 20 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 21 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 22 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 23 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 24 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 25 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 26 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 27 of 33.PDF22 Nov 2022
Building plan approvalFile: Plan 28 of 33.PDF22 Nov 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BROADWAY INTEGRATED PARK LLP - TOWER 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TATHWADE13,700+ in Pune

Builder: BROADWAY INTEGRATED PARK LLP

BROADWAY INTEGRATED PARK LLP has 1 registration on MahaRERA, including BROADWAY INTEGRATED PARK LLP - TOWER 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BROADWAY INTEGRATED PARK LLP - TOWER 1 shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BROADWAY INTEGRATED PARK LLP - TOWER 1 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BROADWAY INTEGRATED PARK LLP - TOWER 1?

The registered promoter entity is BROADWAY INTEGRATED PARK LLP, an others as per the filing. Its GSTIN 27AAQFB2188L1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BROADWAY INTEGRATED PARK LLP - TOWER 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BROADWAY INTEGRATED PARK LLP - TOWER 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BROADWAY INTEGRATED PARK LLP - TOWER 1?

The professionals named in the filing: Architect: Shitesh Agrawal Agrawal; Architect: AR. Sourabh Laghate; Engineer: Hariharan Iyer Iyer; Chartered Accountant: CA Paresh Sabadra Prakash SABADRA; Chartered Accountant: PRAKASH SABADRA; Chartered Accountant: Suchita Pawar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BROADWAY INTEGRATED PARK LLP - TOWER 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BROADWAY INTEGRATED PARK LLP - TOWER 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BROADWAY INTEGRATED PARK LLP - TOWER 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.