Brij
By Vedbhumi Builders & Developers Pvt. Ltd.
RG-MH-02233 · RERA P50500013364 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 104 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Brij is a Others project by Vedbhumi Builders & Developers Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500013364 on 26 Sep 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 104 months from the original filing. 23 of the 24 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameBrij
- TypeOthers
- Location
- Nagpur
- Nagur
- Nagpur (M Corp.)
- Nagpur (Urban)
- 440008
- Pincode440008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500013364
- ReraGenie IDRG-MH-02233
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on26 Sep 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2019)
- Buildings1 building record
- Documents filed120 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Brij | NA | 7 | 7 | 16 | 8 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
Brij: 49% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Brij | NA | Rs 14.97 cr | Rs 6.10 cr |
| - | NA | Rs 14.97 cr | Rs 6.10 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SMT SUCHITA MALEWAR |
| Architect | vaibhav khadse |
| Engineer | P S PATANKAR |
| Engineer | Vaibhav Khadse |
| Chartered Accountant | CA Rishi Lashkare |
| Chartered Accountant | Ravindra Lashkare |
| Partner | Role in project |
|---|---|
| Vedbhumi Builders & Developers Pvt. Ltd. | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRECESSION IN REAL ESTATE & FUNDS PROBLEM:- The company has invested its entire capital and quasi capital alongwith the delayed release of bank project loan.The very bad situation of real estate sector has been the main reason for delay in completion of construction of project as such we pray for extension of time period for completion of construction and thereby giving possession to the esteemed customers for a further period of one year.
Reason as filed by the promoterDue to current ongoing pandemic we could not arrange the requisite
Reason as filed by the promoterWe, M/s. Ved Bhumi Builders and Developers Pvt. Ltd., promoter of the said project, we are writing to formally request an extension for the completion date of our plotted development project located at Plot No. 7, City Survey No. 34, Mouza - Wathoda, Tah. - Nagpur, District - Nagpur; total admeasuring 834.20 Sq. Mtrs. The current registration for the aforementioned project is valid until 30-06-2025. We are seeking an extension of 1.5 years, proposing a revised completion date of 31-12-2027. - Reasons for Delay Despite our best efforts to adhere to the original timeline, the development of the
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed120
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 - Architects Certificate - Ved Bhumi - Sep 2025..pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 - Architects Certificate - ved bhumi - Dec 2025..pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1- Arch Certificate - Ved Bhumi - March 2026..pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved Bhumi - SEP 2025.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved bhumi - Dec 2025.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved Bhumi - March 2026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate - VEd Bhumi - Sep 2025.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 - CA Certificate - Ved bhumi - dec 2025.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 - CA Certificate - Ved Bhumi - March 2026.pdf | 30 Jul 2026 |
| Form 5 (FY 2021-2022)File: Form 5 - (2021-2022).pdf | 8 Jul 2026 |
| Form 5 (FY 2020-2021)File: Form 5 - (2020-2021).pdf | 8 Jul 2026 |
| Form 5 (FY 2019-2020)File: Form 5 - (2019-2020).pdf | 8 Jul 2026 |
| Form 2A (FY 2017-2018)File: Form 2A - (2017-18).pdf | 30 May 2026 |
| Form 2A (FY 2018-2019)File: Form 2A - (2018-19).pdf | 30 May 2026 |
| Form 2A (FY 2019-2020)File: Form 2A - (2019-20).pdf | 30 May 2026 |
| Form 2A (FY 2020-2021)File: Form 2A - (2020-21).pdf | 30 May 2026 |
| Form 2A (FY 2021-2022)File: Form 2A - (2021-22).pdf | 30 May 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - (2022-23).pdf | 30 May 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - (2023-24).pdf | 30 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - (2024-25).pdf | 30 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - (2025-26).pdf | 30 May 2026 |
| Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - March 2024.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Architects Certificate - BRIJ - March 2024.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - March 2024.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - March 2024.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - June 2024.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Architects Certificate - BRIJ - June 2024.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - June 2024.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - June 2024.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - Sept 2024.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Architects Certificate - BRIJ - Sept 2024.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - Sept 2024.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - Sept 2024.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - Dec 2024.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Arch Certificate - BRIJ - Dec 2024.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - Dec 2024.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - Dec 2024.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - March 2025.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Architects Certificate - BRIJ - March 2025.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - March 2025.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - March 2025.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - June 2025.pdf | 29 May 2026 |
| Form 1File: FORM 1 - Architects Certificate - BRIJ - JUNE 2025.pdf | 29 May 2026 |
| Form 2File: FORM 2 - Engineer Certificate - BRIJ - JUNE 2025.pdf | 29 May 2026 |
| Form 3File: FORM 3 - C A Certificate - BRIJ - JUNE 2025.pdf | 29 May 2026 |
| Form 1File: BRIJ - Form 1 - Arch Certificate Dec 2023.pdf | 26 May 2026 |
| Form 2File: BRIJ - Form 2 - Engineer Certificate Dec 2023.pdf | 26 May 2026 |
| Form 3File: BRIJ - Form 3 - CA Certificate Dec 2023.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inevntory - Dec 2023.pdf | 26 May 2026 |
| Form 1File: BRIJ - Form 1 - Arch Certificate Sept 2023.pdf | 26 May 2026 |
| Form 2File: BRIJ - Form 2 - Engineer Certificate Sept 2023.pdf | 26 May 2026 |
| Form 3File: BRIJ - Form 3 - CA Certificate Sept 2023.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inevntory - Sept 2023.pdf | 26 May 2026 |
| Form 1File: Form 1 - March 2023.pdf | 26 May 2026 |
| Form 2File: Form 2 - March 2023.pdf | 26 May 2026 |
| Form 3File: Form 3 - March 2023.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - march 2023.pdf | 26 May 2026 |
| Form 1File: Form 1 - June 2023.pdf | 26 May 2026 |
| Form 2File: Form 2 - June 2023.pdf | 26 May 2026 |
| Form 3File: Form 3 - June 2023.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - june 2023.pdf | 26 May 2026 |
| Form 5 (FY 2022-2023)File: Form 5 - (2022-23).pdf | 26 May 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - (2023-24).pdf | 26 May 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - (2024-25).pdf | 26 May 2026 |
| Form 5 (FY 2025-2026)File: Form 5 - (2025-26).pdf | 26 May 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 26 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 26 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 26 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 26 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 - Brij.pdf | 26 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23 - Brij.pdf | 26 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: BRIJ - ENCUMBRANCE CERTI - LEGAL.pdf | 1 Jan 2024 |
| Details of encumbrances concerned to LegalFile: BRIJ - ENCUMBRANCE CERTI - LEGAL.pdf | 1 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf | 1 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf | 1 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Bhumi Arcade | Nagpur | 21 | Completed | Jul 2014 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 120 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Brij on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nagur2,800+ in Nagpur
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
KUKREJA PARIS CITY-WING C & D
KUKREJA INFRASTRUCTURES
kASTURI HEIGHT
SKY DEVELOPERS AND PROMOTERS INDIA PVT. LT
EASTORIA GRACE
EASTORIA BUILDERS AND DEVLOPERS LLP
SDPL Om
SANDEEP DWELLERS PVT. LTD.
UDYOG VIHAR
ALLIANCE REALITIES
KUKREJA INFINITY EAST
KUKREJA INFRASTRUCTURES
See every Nagpur project, with the district possession charts
Builder: Vedbhumi Builders & Developers Pvt. Ltd.
Vedbhumi Builders & Developers Pvt. Ltd. has 2 registrations on MahaRERA, including Brij and Barsana. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if Brij is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Brij?
The registered promoter entity is Vedbhumi Builders & Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Brij?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Brij?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Brij?
The professionals named in the filing: Architect: SMT SUCHITA MALEWAR; Architect: vaibhav khadse; Engineer: P S PATANKAR; Engineer: Vaibhav Khadse; Chartered Accountant: CA Rishi Lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Brij?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback