Registered No litigation declared Others project

Brij

By Vedbhumi Builders & Developers Pvt. Ltd.

RG-MH-02233 · RERA P50500013364 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 104 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 104 months from the original
1 of 11Construction stages donefurthest along: Basement (if any), 90%
1 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

Brij is a Others project by Vedbhumi Builders & Developers Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500013364 on 26 Sep 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 104 months from the original filing. 23 of the 24 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameBrij
  • TypeOthers
  • Location
    • Nagpur
    • Nagur
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • 440008
  • Pincode440008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500013364
  • ReraGenie IDRG-MH-02233

Builder

  • NameVedbhumi Builders & Developers Pvt. Ltd.
  • Entity typeCompany
  • Managing DirectorYogesh Maganbhai Chawda
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseApr 2019Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2019)
  • Buildings1 building record
  • Documents filed120 files

Current status

96%23 of 24 units booked
40.7%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BrijNA7716824

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.

Brij: 49% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor80%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area834 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNagpur Improvement Trust
Permissible FSI833.87
Proposed, not sanctioned834 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGandhi Grain Market, Old Bagadganj Layout, CA Road, Nagpur
Estimated costRs 29.94 cr
Cost incurredRs 12.20 cr
Work done40.74%
BuildingWingEstimatedIncurred
BrijNARs 14.97 crRs 6.10 cr
-NARs 14.97 crRs 6.10 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSMT SUCHITA MALEWAR
Architectvaibhav khadse
EngineerP S PATANKAR
EngineerVaibhav Khadse
Chartered AccountantCA Rishi Lashkare
Chartered AccountantRavindra Lashkare
PartnerRole in project
Vedbhumi Builders & Developers Pvt. Ltd.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500002137Apr 2019 → Apr 2020

Reason as filed by the promoterRECESSION IN REAL ESTATE & FUNDS PROBLEM:- The company has invested its entire capital and quasi capital alongwith the delayed release of bank project loan.The very bad situation of real estate sector has been the main reason for delay in completion of construction of project as such we pray for extension of time period for completion of construction and thereby giving possession to the esteemed customers for a further period of one year.

EXT50500010927Apr 2019 → Dec 2024

Reason as filed by the promoterDue to current ongoing pandemic we could not arrange the requisite

EA24062621495Apr 2019 → Dec 2027

Reason as filed by the promoterWe, M/s. Ved Bhumi Builders and Developers Pvt. Ltd., promoter of the said project, we are writing to formally request an extension for the completion date of our plotted development project located at Plot No. 7, City Survey No. 34, Mouza - Wathoda, Tah. - Nagpur, District - Nagpur; total admeasuring 834.20 Sq. Mtrs. The current registration for the aforementioned project is valid until 30-06-2025. We are seeking an extension of 1.5 years, proposing a revised completion date of 31-12-2027. - Reasons for Delay Despite our best efforts to adhere to the original timeline, the development of the

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - Architects Certificate - Ved Bhumi - Sep 2025..pdf30 Jul 2026
Withdrawal Update Form 1File: FORM 1 - Architects Certificate - ved bhumi - Dec 2025..pdf30 Jul 2026
Withdrawal Update Form 1File: FORM 1- Arch Certificate - Ved Bhumi - March 2026..pdf30 Jul 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved Bhumi - SEP 2025.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved bhumi - Dec 2025.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM 2 - Engineer Certificate - Ved Bhumi - March 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - VEd Bhumi - Sep 2025.pdf30 Jul 2026
Withdrawal Update Form 3File: FORM 3 - CA Certificate - Ved bhumi - dec 2025.pdf30 Jul 2026
Withdrawal Update Form 3File: FORM 3 - CA Certificate - Ved Bhumi - March 2026.pdf30 Jul 2026
Form 5 (FY 2021-2022)File: Form 5 - (2021-2022).pdf8 Jul 2026
Form 5 (FY 2020-2021)File: Form 5 - (2020-2021).pdf8 Jul 2026
Form 5 (FY 2019-2020)File: Form 5 - (2019-2020).pdf8 Jul 2026
Form 2A (FY 2017-2018)File: Form 2A - (2017-18).pdf30 May 2026
Form 2A (FY 2018-2019)File: Form 2A - (2018-19).pdf30 May 2026
Form 2A (FY 2019-2020)File: Form 2A - (2019-20).pdf30 May 2026
Form 2A (FY 2020-2021)File: Form 2A - (2020-21).pdf30 May 2026
Form 2A (FY 2021-2022)File: Form 2A - (2021-22).pdf30 May 2026
Form 2A (FY 2022-2023)File: Form 2A - (2022-23).pdf30 May 2026
Form 2A (FY 2023-2024)File: Form 2A - (2023-24).pdf30 May 2026
Form 2A (FY 2024-2025)File: Form 2A - (2024-25).pdf30 May 2026
Form 2A (FY 2025-2026)File: Form 2A - (2025-26).pdf30 May 2026
Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - March 2024.pdf29 May 2026
Form 1File: FORM 1 - Architects Certificate - BRIJ - March 2024.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - March 2024.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - March 2024.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - June 2024.pdf29 May 2026
Form 1File: FORM 1 - Architects Certificate - BRIJ - June 2024.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - June 2024.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - June 2024.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - Sept 2024.pdf29 May 2026
Form 1File: FORM 1 - Architects Certificate - BRIJ - Sept 2024.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - Sept 2024.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - Sept 2024.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - Dec 2024.pdf29 May 2026
Form 1File: FORM 1 - Arch Certificate - BRIJ - Dec 2024.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - Dec 2024.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - Dec 2024.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - March 2025.pdf29 May 2026
Form 1File: FORM 1 - Architects Certificate - BRIJ - March 2025.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - March 2025.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - March 2025.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - BRIJ - June 2025.pdf29 May 2026
Form 1File: FORM 1 - Architects Certificate - BRIJ - JUNE 2025.pdf29 May 2026
Form 2File: FORM 2 - Engineer Certificate - BRIJ - JUNE 2025.pdf29 May 2026
Form 3File: FORM 3 - C A Certificate - BRIJ - JUNE 2025.pdf29 May 2026
Form 1File: BRIJ - Form 1 - Arch Certificate Dec 2023.pdf26 May 2026
Form 2File: BRIJ - Form 2 - Engineer Certificate Dec 2023.pdf26 May 2026
Form 3File: BRIJ - Form 3 - CA Certificate Dec 2023.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inevntory - Dec 2023.pdf26 May 2026
Form 1File: BRIJ - Form 1 - Arch Certificate Sept 2023.pdf26 May 2026
Form 2File: BRIJ - Form 2 - Engineer Certificate Sept 2023.pdf26 May 2026
Form 3File: BRIJ - Form 3 - CA Certificate Sept 2023.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inevntory - Sept 2023.pdf26 May 2026
Form 1File: Form 1 - March 2023.pdf26 May 2026
Form 2File: Form 2 - March 2023.pdf26 May 2026
Form 3File: Form 3 - March 2023.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - march 2023.pdf26 May 2026
Form 1File: Form 1 - June 2023.pdf26 May 2026
Form 2File: Form 2 - June 2023.pdf26 May 2026
Form 3File: Form 3 - June 2023.pdf26 May 2026
Disclosure of Sold and Booked InventoryFile: BRIJ - Disclosure of Sold Inventory - june 2023.pdf26 May 2026
Form 5 (FY 2022-2023)File: Form 5 - (2022-23).pdf26 May 2026
Form 5 (FY 2023-2024)File: Form 5 - (2023-24).pdf26 May 2026
Form 5 (FY 2024-2025)File: Form 5 - (2024-25).pdf26 May 2026
Form 5 (FY 2025-2026)File: Form 5 - (2025-26).pdf26 May 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf26 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 - Brij.pdf26 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23 - Brij.pdf26 Feb 2024
Details of encumbrances concerned to FinanceFile: BRIJ - ENCUMBRANCE CERTI - LEGAL.pdf1 Jan 2024
Details of encumbrances concerned to LegalFile: BRIJ - ENCUMBRANCE CERTI - LEGAL.pdf1 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf1 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf1 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf1 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BRIJ - ARCHITECT CERTIFICATE.pdf1 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf1 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf1 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BRIJ - ENGINEER CERTIFICATE.pdf1 Jan 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Bhumi ArcadeNagpur21CompletedJul 2014Late, Jul 2017

How this compares with Nagpur

96%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 104 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Brij on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nagur2,800+ in Nagpur

2 kmBrijCompleted 1Lapsed / revoked 3Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: Vedbhumi Builders & Developers Pvt. Ltd.

Vedbhumi Builders & Developers Pvt. Ltd. has 2 registrations on MahaRERA, including Brij and Barsana. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Brij is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Brij?

The registered promoter entity is Vedbhumi Builders & Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Brij?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Brij?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Brij?

The professionals named in the filing: Architect: SMT SUCHITA MALEWAR; Architect: vaibhav khadse; Engineer: P S PATANKAR; Engineer: Vaibhav Khadse; Chartered Accountant: CA Rishi Lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brij?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brij. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brij to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.