Home / Browse projects / Mumbai Suburban, Maharashtra / Mantra Marquis Tower 5
Mantra Marquis Tower 5
By ACME REALTIES PRIVATE LIMITED
RG-MH-10479 · RERA P51800001690 · Last updated on MahaRERA portal: 11 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 24 complaints at MahaRERA
- Completion date moved by 54 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mantra Marquis Tower 5 is a Residential / Group Housing project by ACME REALTIES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001690 on 29 Jul 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 54 months from the original filing. 120 of the 152 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 24 complaints are on record with the regulator.
At a glance
Project
- NameMantra Marquis Tower 5
- TypeResidential / Group Housing
- Location
- Sarvodaya Nagar
- Jogeshwari (E)
- Majas
- Andheri
- Mumbai Suburban
- 400060
- Pincode400060
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800001690
- ReraGenie IDRG-MH-10479
Builder
- NameACME REALTIES PRIVATE LIMITED
- Entity typeCompany
- CINU45202MH2008PTC180445
- GSTIN27AAICA6893N2ZT
- DirectorsSARANSH SUKANTA DEY, ASHISH SATISH GUPTA, ROHIT GHANSHYAM GUPTA
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Jul 2017
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed229 files
Current status
Figures as on 11 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Boulevard Tower 5 | NA | 33 | 26 | 152 | 0 | 152 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 60%.
Boulevard Tower 5: 74% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 20% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 60% |
Parking filed240
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Boulevard Tower 5 | NA | Rs 28.00 cr | Rs 4.50 cr |
| - | NA | Rs 7.00 cr | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | H.M JHAVERI & SONS |
| Architect | Ellora Projects Consultants Pvt. Ltd. |
| Architect | SONAL AREKAR |
| Engineer | JW CONSULTANTS LLP |
| Engineer | Ravi Rawal |
| Chartered Accountant | R Devendra Kumar and Associates |
| Chartered Accountant | Patel and Sharma Chartered Accountants |
| Chartered Accountant | Manoj Shah |
| Partner | Role in project |
|---|---|
| ACME REALTIES PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. Force Majeure - COVID-19 Pandemic. 2. Ongoing Litigations and Complaints. 3. Various Challenges to the Project.
Reason as filed by the promoterThe Promoter company underwent Corporate Insolvency Resolution Process (CIRP) under the Insolvency and Bankruptcy Code, 2016. Pursuant to the approved Resolution Plan, Mantra Properties and Developers Private Limited along with Mr. Rohit Gupta were appointed as the Successful Resolution Applicants (SRA). As per the approved Resolution Plan and NCLT Order, the delivery schedule for the units to homebuyers is stipulated within 18 months from the Effective Date (Effective Date: 30/12/2025).
Litigation declared10
| Case | Court | Status |
|---|---|---|
| Writ Petition No 605 of 2017/2017 | High Court Bombay | Pending |
| Writ Petition No 1338 of 2017/2016 | High Court Bombay | Pending |
| LC Suit No 1367 of 2014/2014 | City Civil Court Dindoshi | Pending |
| City Civil LC Suit No 2585 of 2012/2012 | Civil Court Dindoshi | Pending |
| Dispute Application No 37 of 2013/2013 | Cooperative Court Old Custom House | Pending |
| Dispute Application No 78 of 2011/2011 | Cooperative Court Old Custom House | Pending |
| Civil Writ Petition No 2703 of 2013 in Dispute 78/11/2013 | High Court Bombay | Disposed |
| Civil Writ Petition No 10399 of 2013 in Dispute-78/11/2013 | High Court Bombay | Pending |
| PIL 47/2012/2012 | High Court Bombay | Disposed |
| CP-IB-324-MB/C-III/2023/2023 | NATIONAL COMPANY LAW TRIBUNAL | Pending |
Complaints filed with MahaRERA24
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196123 | Anshu Mohta | Acme Realties Private Limited | 04/03/2021 |
| CC006000000195224 | PREM SHANKAR | Acme Realties Private Limited | 12/12/2020 |
| CC006000000198314 | Abhishek Ranganathan | Acme Realities Private Limited | 13/11/2021 |
| CC006000000198343 | SANJEEV KUMAR | ACME REALTIES PVT LTD | 15/10/2021 |
| CC006000000292631 | Madhukar Vishwanath Hadkar | ACME REALTIES PRIVATE LIMITED | 10/09/2022 |
| CC006000000282174 | Sanjay Suryadeo Upadhyay | Acme Realties Private Limited | 05/08/2022 |
| CC006000000282201 | Vivek Kumar Singh | Acme Realties Private Limited | 05/08/2022 |
| CC006000000292433 | Roshan Jaya Shetty | Acme Realties Pvt Ltd | 23/08/2022 |
| CC006000000292431 | GANGADHAR CHATURBHUJ BHARARIA | Acme Realties Private Limited | 02/09/2022 |
| CC006000000292773 | Joy Mendonca | Acme Realties Pvt. Ltd | 21/09/2022 |
| CC006000000302894 | Abhijoy Phalguni de Choudhury | ACME HOUSING | 30/09/2022 |
| CC006000000302899 | Manoj kumar | ACME HOUSING | 03/10/2022 |
| CC006000000302914 | Milin Shah | ACME HOUSING | 03/10/2022 |
| CC006000000303158 | VIJAY RAMMURAT SINGH | J P INFRA MUMBAI PRIVATE LIMITED | 27/02/2023 |
| CC006000000303295 | Nilufer Merwan Shekhawat | ACME Realties Private Limited | 10/11/2022 |
| CC006000000333803 | Ajit Kumar Grover | ACME HOUSING | 27/12/2022 |
| CC006000000333847 | Sandhya Amit Tiwari | ACME Realties Pvt. Ltd. | 31/12/2022 |
| CC006000000364581 | Ekta Sawant | ACME HOUSING | 02/03/2023 |
| CC006000000396025 | Anoop Chokhani | Keemaya Developers Private Limited | 02/06/2023 |
| CC006000000408298 | Akshata Ashok Parab | Acme Realties Pvt. Ltd. | 07/12/2023 |
| CC006000000408551 | Mahesh Prabhu Mistry | Acme Realities Private Limited | 19/12/2023 |
| CC006000000429390 | Ravi Khurana | Acme Realties Private Limited | 28/02/2024 |
| CC006000000429262 | Pradeep Kumar | Acme Realities Private Limited | 15/02/2024 |
| CC006000000429396 | Varun Uchil | ACME Realties | 23/02/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed229
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 229 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Tower 5_compressed.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Acme Tower 5.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: CA Certificate Acme T5_Final_compressed.pdf | 11 Aug 2026 |
| Form 5 (FY 2025-2026)File: Declaration in Lieu of Form 5 and 2A.pdf | 5 Aug 2026 |
| Layout approvalFile: 01 Layout Highlighted Final.pdf | 28 Jul 2026 |
| Building plan approvalFile: 02 Second Basement Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 03 First Basement Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 04 Lower Ground Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 05 Ground Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 06 First Podium Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 07 Second Podium Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 08 Elevator Level Podium Floor Plan.pdf | 28 Jul 2026 |
| Building plan approvalFile: 09 Tower S5- Floor Plan 1.pdf | 28 Jul 2026 |
| Building plan approvalFile: 10 Tower S5- Floor Plan 2.pdf | 28 Jul 2026 |
| Building plan approvalFile: 11 Tower S5- Floor Plan 3.pdf | 28 Jul 2026 |
| Building plan approvalFile: 12 Sections_.pdf | 28 Jul 2026 |
| Building plan approvalFile: 13 Sections.pdf | 28 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Tower 5_compressed.pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Acme Tower 5.pdf | 27 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate Acme T5_Final_compressed.pdf | 27 Jul 2026 |
| Form 2A (FY 2026-2027)File: Form 2a Tower 5.pdf | 27 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2a Tower 5.pdf | 27 Jul 2026 |
| Form 2A (FY 2017-2018)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2018-2019)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2019-2020)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2020-2021)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2021-2022)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2022-2023)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2023-2024)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 2A (FY 2024-2025)File: Declaration in Lieu of Form 05 and 2A.pdf | 22 Apr 2026 |
| Form 5 (FY 2024-2025)File: Declaration in Lieu of Form 05 and 2A.pdf | 14 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Tower 5 Signed.pdf | 13 Apr 2026 |
| Withdrawal Update Form 2File: Engg Certificate Acme T5_Scanned.pdf | 13 Apr 2026 |
| Withdrawal Update Form 3File: Form 03.pdf | 13 Apr 2026 |
| Form 1File: Declaration.pdf | 9 Apr 2026 |
| Form 2File: Declaration.pdf | 9 Apr 2026 |
| Form 3File: Declaration.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration.pdf | 9 Apr 2026 |
| Form 1File: Declaration.pdf | 9 Apr 2026 |
| Form 2File: Declaration.pdf | 9 Apr 2026 |
| Form 3File: Declaration.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration.pdf | 9 Apr 2026 |
| Form 1File: Declaration.pdf | 9 Apr 2026 |
| Form 2File: Declaration.pdf | 9 Apr 2026 |
| Form 3File: Declaration.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration.pdf | 9 Apr 2026 |
| Form 1File: Declaration.pdf | 9 Apr 2026 |
| Form 2File: Declaration.pdf | 9 Apr 2026 |
| Form 3File: Declaration.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration.pdf | 9 Apr 2026 |
| Form 1File: Declaration.pdf | 9 Apr 2026 |
| Form 2File: Declaration.pdf | 9 Apr 2026 |
| Form 3File: Declaration.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: FORM-1 BOULEVARD S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: FORM-1 BOULEVARD S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: FORM-1 BOULEVARD S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Tower 5 Signed.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTF S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTF S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTF S-5.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: Engg Certificate Acme T5_Scanned.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Declaration.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Declaration.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Declaration.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Form 03.pdf | 9 Apr 2026 |
| Form 1File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 2File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 3File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 1File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 2File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 3File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 2File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 1File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 3File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 1File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
| Form 2File: Declaration In Lieu of Previous Compliances_1.pdf | 11 Feb 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 229 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mantra Marquis Tower 5 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Jogeshwari (E)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 171 registered projects within 2 km.
RATAN HERITAGE
NEXUS BUILDERS & DEVELOPERS
JP Parkway
Srushti Raj Developers LLP
Gyan Gold Crest
Gyan S. P. Developers LLP
PREM BUILDERS
PREM BUILDERS
Edenrose
Hillview Venture
AIM Garden
AIM Developers
See every Mumbai Suburban project, with the district possession charts
Builder: ACME REALTIES PRIVATE LIMITED
ACME REALTIES PRIVATE LIMITED has 2 registrations on MahaRERA, including Mantra Marquis Tower 4 and Mantra Marquis Tower 5. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Mantra Marquis Tower 5 is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mantra Marquis Tower 5?
The registered promoter entity is ACME REALTIES PRIVATE LIMITED, a company as per the filing. Its CIN U45202MH2008PTC180445 and GSTIN 27AAICA6893N2ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mantra Marquis Tower 5?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mantra Marquis Tower 5?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mantra Marquis Tower 5?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mantra Marquis Tower 5?
The professionals named in the filing: Architect: H.M JHAVERI & SONS; Architect: Ellora Projects Consultants Pvt. Ltd.; Architect: SONAL AREKAR; Engineer: JW CONSULTANTS LLP; Engineer: Ravi Rawal; Chartered Accountant: R Devendra Kumar and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mantra Marquis Tower 5?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback