ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / BORIVALI YASH PRABHA CHS LTD

Completed No litigation declared Residential / Group Housing project

BORIVALI YASH PRABHA CHS LTD

By UNIQUE SHANTI DEVELOPERS LLP

RG-MH-09907 · RERA P51700003496 · Last updated on MahaRERA portal: 24 Jan 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

BORIVALI YASH PRABHA CHS LTD is a Residential / Group Housing project by UNIQUE SHANTI DEVELOPERS LLP in Thane, Maharashtra, registered with MahaRERA as P51700003496 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameBORIVALI YASH PRABHA CHS LTD
  • TypeResidential / Group Housing
  • Location
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003496
  • ReraGenie IDRG-MH-09907

Builder

  • NameUNIQUE SHANTI DEVELOPERS LLP
  • Entity typePartnership
  • PartnersMADHU DOSHI, AMI DOSHI, VIDHI DOSHI, KHUSHBU SHAH, HEMAL DOSHI, KUNAL DOSHI
  • Other registrations9 more →
  • Completed7 of 10
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 30 Dec 2020)
  • Buildings1 building record
  • Documents filed55 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BORIVALI YASH PRABHA CHS LTDNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

BORIVALI YASH PRABHA CHS LTD: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed115

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots115
Closed/Covered1
Open Space114

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,708 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
BORIVALI YASH PRABHA CHS LTD.BorivaliMumbai Suburban

Approvals and building plan

Permissible FSI7261.88
Proposed, not sanctioned1,829 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA-WING, SHANTI SHOPPING CENTRE, MIRA ROAD EAST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH SHAH
EngineerHIREN TANNA
PartnerRole in project
UNIQUE SHANTI DEVELOPERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700008764Dec 2020 → Jun 2021

Reason as filed by the promoterDue to the Lockdown, movement of people was restricted as per Guideline issued by Ministry of Hoe Affairs. Essential public and private transport was suspended, workers and Laborers were also not available.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jun 2021

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: USDLLP Form 5 YP 2021.pdf24 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OCC dated 22-06-2021.pdf30 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Architect Certificate for full occ.pdf30 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 YP.pdf29 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC YP.pdf3 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC Further Upto 14th Floors.pdf28 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: USDLLP Form No-5 YP.pdf9 Mar 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: USDLLP - Part OCC Certificate Commercial.pdf1 Oct 2019
Certificates of CA (Form 5)File: FORM NO- 5 YP.pdf13 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Yash Prabha - Revised CC.pdf30 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Yash Prabha - Architect Certificate.pdf30 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Yash Prabha - Engineer Certificate.pdf30 Mar 2018
Certificates of CA (Form 3)File: Yash Prabha - CA Certificate.pdf30 Mar 2018
Building plan approvalFile: IOD Approved Plans-1.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-2.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-3.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-4.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-5.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-6.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-7.pdf31 Jul 2017
Building plan approvalFile: IOD Approved Plans-8.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-1.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-2.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-3.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-4.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-6.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-5.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-7.pdf31 Jul 2017
Layout approvalFile: IOD Approved Plans-8.pdf31 Jul 2017
PAN CardFile: YP - PAN Card.pdf31 Jul 2017
Copy of the legal title reportFile: YP - Title Report.pdf31 Jul 2017
Details of encumbrancesFile: YP - Encumberances Certificate.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-2.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-3.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-4.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-5.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-6.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-7.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Approved Plans-8.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-1.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-2.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-3.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-4.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-5.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-6.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-7.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD Approved Plans-8.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: YP - Commencement Certificate.pdf31 Jul 2017
Declaration in FORM BFile: YP - Form 'B'-Affidavit cum Declaration.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: YP - Architect Certificate Yash Prabha.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Address5 - Engineer Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: Address5 - CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: YP - Agreement for sale.pdf31 Jul 2017
Proforma of Allotment letterFile: YP - Allotment Letter.pdf31 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SKYLINESKYLINE MIRA ROAD EAST THANE 401 107165CompletedFeb 2015Late, Apr 2015

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BORIVALI YASH PRABHA CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane

2 kmBORIVALI YASH PRABHA CHSCompleted 105Lapsed / revoked 80Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: UNIQUE SHANTI DEVELOPERS LLP

UNIQUE SHANTI DEVELOPERS LLP has 10 registrations on MahaRERA, including UNIQUE AURUM-II and BORIVALI YASH PRABHA CHS LTD. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if BORIVALI YASH PRABHA CHS LTD is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BORIVALI YASH PRABHA CHS LTD?

The registered promoter entity is UNIQUE SHANTI DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BORIVALI YASH PRABHA CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BORIVALI YASH PRABHA CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BORIVALI YASH PRABHA CHS LTD?

The professionals named in the filing: Architect: MANISH SHAH; Engineer: HIREN TANNA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BORIVALI YASH PRABHA CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BORIVALI YASH PRABHA CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BORIVALI YASH PRABHA CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.