ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / BOKHARA LAY OUT PHASE 1

Registered No litigation declared Plotted project

BOKHARA LAY OUT PHASE 1

By JOYDIP JIBAN SARKAR

RG-MH-81556 · RERA P50500050050 · Last updated on MahaRERA portal: 20 Jan 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
20 of 53Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

BOKHARA LAY OUT PHASE 1 is a Plotted project by JOYDIP JIBAN SARKAR in Nagpur, Maharashtra, registered with MahaRERA as P50500050050 on 6 Mar 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 33 of the 53 units on this registration are recorded sold or booked. 2 complaints are on record with the regulator.

At a glance

Project

  • NameBOKHARA LAY OUT PHASE 1
  • TypePlotted
  • Location
    • NR GODHANI RLY STATION
    • MOUZA BOKHARA
    • Bokhara
    • Nagpur (Rural)
    • Nagpur
    • 441111
  • Pincode441111
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500050050
  • ReraGenie IDRG-MH-81556

Builder

  • NameJOYDIP JIBAN SARKAR
  • Entity typeIndividual

Key dates

this monthRegisteredMar 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Mar 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • BuildingsNot stated in filing
  • Documents filed125 files

Current status

62%33 of 53 units booked
100.0%Work done, per cost certificate

Figures as on 20 Jan 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes80%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area22,500 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2025

Approvals and building plan

Sanctioning authorityCREDAI NAGPUR

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVAJI NAGAR NAGPUR
Estimated costRs 40.00 lakh
Cost incurredRs 40.00 lakh
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 40.00 lakhRs 40.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIRENDRA KHARE
EngineerKEWAL BANSAL
Chartered AccountantKHANZODE & SHENWAI
Chartered AccountantPRATIK CHHABRIA AND COMPANY
PartnerRole in project
JOYDIP JIBAN SARKAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA18122518740Dec 2025 → Dec 2026

Reason as filed by the promoterDELAY IS DUE TO PENDING COMPLETION OF THE STP WORK. THE SAME SHALL BE COMPLETED AS SOON AS POSSIBLE. PLEASE FIND ATTACHED HEREWITH THE PDF FILE CONTAINING THE JUSTIFICATION

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
SM12500046Mrinal KatkarJOYDIP JIBAN SARKAR03/03/2025
CC12600792KUNAL RAJESH DHOKEJOYDIP JIBAN SARKAR12/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q3.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Q3.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 IDC 24-25.pdf13 Dec 2025
Form 1File: Form 1 architect Certificate.pdf11 Dec 2025
Form 2File: Form 2 Engineer Certificate.pdf11 Dec 2025
Form 3File: Form 3 CA Certificate.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: IDC Disclosure of Sold-unsold.pdf11 Dec 2025
Form 1File: Form 1 Architect Certificate.pdf11 Dec 2025
Form 2File: Form 2 Engineer Certificate.pdf11 Dec 2025
Form 3File: Form 3 CA Certificate.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: IDC Disclosure of Sold-unsold.pdf11 Dec 2025
Form 1File: Architect Certificate 30 SEPT 24.pdf11 Dec 2025
Form 2File: Engineer Certificate 30 SEPT 24.pdf11 Dec 2025
Form 3File: Form 3 FY 24-25 Q2.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory.pdf11 Dec 2025
Form 1File: ARCHITECTS CERTIFICATE.pdf11 Dec 2025
Form 2File: ENGINEER'S CERTIFICATE.pdf11 Dec 2025
Form 3File: RERA FORM 3.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory.pdf11 Dec 2025
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf11 Dec 2025
Form 2File: FORM 2 ENGG CERTIFICATE.pdf11 Dec 2025
Form 3File: Form 3 Q4 FY 2023-24.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Form 3 Q4 FY 2023-24.pdf11 Dec 2025
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf11 Dec 2025
Form 2File: FORM 2 ENGG CERTIFICATE.pdf11 Dec 2025
Form 3File: Form 3 Q4 FY 2023-24.pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: IDC Disclosure of Sold-unsold.pdf11 Dec 2025
Withdrawal Update Form 1File: Architect Certificate.pdf11 Dec 2025
Withdrawal Update Form 1File: Architect Certificate.pdf11 Dec 2025
Withdrawal Update Form 2File: Form 2 Q2 FY 25-26.pdf11 Dec 2025
Withdrawal Update Form 2File: Form 2 Q2 FY 25-26.pdf11 Dec 2025
Withdrawal Update Form 3File: Form 3 Q2 FY 25-26.pdf11 Dec 2025
Withdrawal Update Form 3File: Form 3 Q2 FY 25-26.pdf11 Dec 2025
Form 2A (FY 2023-2024)File: FORM 2A SEPT 24.pdf11 Dec 2025
Form 2A (FY 2022-2023)File: Form 2A -22-23.pdf11 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf11 Dec 2025
Form 5 (FY 2023-2024)File: FORM 5 RERA.pdf11 Dec 2025
Form 5 (FY 2022-2023)File: FORM5 22-23.pdf11 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf27 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 RERA.pdf21 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 RERA.pdf21 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory.pdf9 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SEPT 24.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate position as on 30 SEPT 24.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 24-25 Q2.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 30 SEPT 24.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3.pdf24 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGG CERTIFICATE.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 FY 2023-24.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form Q - Q1 FY 2023-24.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form Q - Q2 FY 2023-24.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form Q - Q3 FY 2023-24.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form Q - Q4 FY 2023-24.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 FY 2023-24.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 FY 2023-24.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 FY 2023-24.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 FY 2023-24.pdf8 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 FY 2023-24.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 FY 2023-24.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 FY 2023-24.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 FY 2023-24.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31-3-2023.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30-6-2023.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30-9-2023.pdf22 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 31-03-2023.pdf22 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30-06-2023.pdf22 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30-09-2023.pdf22 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31-03-2023.pdf22 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30-06-2023.pdf22 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30-09-2023.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: IDC ARCHITECT'S CERTIFICATE Qtr 3 Dec 23.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: IDC ENGINEER,S CERTIFICATE Qtr 3 Dec 23.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Qtr 3 dec 23 idc.pdf8 Feb 2024

How this compares with Nagpur

62%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 12 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BOKHARA LAY OUT PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUZA BOKHARA2,800+ in Nagpur

2 kmBOKHARA LAY OUT PHASE 1Completed 19Lapsed / revoked 6Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 55 registered projects within 2 km.

Builder: JOYDIP JIBAN SARKAR

JOYDIP JIBAN SARKAR has 1 registration on MahaRERA, including BOKHARA LAY OUT PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if BOKHARA LAY OUT PHASE 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BOKHARA LAY OUT PHASE 1?

The registered promoter entity is JOYDIP JIBAN SARKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BOKHARA LAY OUT PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BOKHARA LAY OUT PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BOKHARA LAY OUT PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BOKHARA LAY OUT PHASE 1?

The professionals named in the filing: Architect: VIRENDRA KHARE; Engineer: KEWAL BANSAL; Chartered Accountant: KHANZODE & SHENWAI; Chartered Accountant: PRATIK CHHABRIA AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BOKHARA LAY OUT PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BOKHARA LAY OUT PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BOKHARA LAY OUT PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.