Home / Browse projects / Mumbai Suburban, Maharashtra / Boirvali Samarpan CHS Ltd
Boirvali Samarpan CHS Ltd
By Konark Structural Engineers Private Limited
RG-MH-69665 · RERA P51800045358 · Last updated on MahaRERA portal: 17 Jun 2024
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Boirvali Samarpan CHS Ltd is a Residential / Group Housing project by Konark Structural Engineers Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800045358 on 12 May 2022. The registration is recorded completed; possession was promised by 30 Jun 2023.
At a glance
Project
- NameBoirvali Samarpan CHS Ltd
- TypeResidential / Group Housing
- Location
- Rokadia cross lane
- Boriwali West
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- RERA no.P51800045358
- ReraGenie IDRG-MH-69665
Builder
- NameKonark Structural Engineers Private Limited
- Entity typeCompany
- CINU45200MH1998PTC117205
- GSTIN27AAACK9113B1ZY
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsArvind Shah, Sangeeta Arvind Shah
- Other registrations9 more →
- Completed3 of 10
- Declared earlier projects8 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 May 2022
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings1 building record
- Documents filed65 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Borivali Samarpan CHS Ltd | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Borivali Samarpan CHS Ltd: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Borivali Samarpan CHS Ltd | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ashim Khatri |
| Engineer | Aditya |
| Chartered Accountant | Navin Podar |
| Partner | Role in project |
|---|---|
| Konark Structural Engineers Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to non availability of Manpower and material, We were unable to complete the project as per the promised date. Therefore we would request to get the extension 29/06/2024. We will try to complete the project before the timeline.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Jun 2024
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf | 17 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 1.pdf | 17 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 2.pdf | 17 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sagar supeda 1.pdf | 17 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sagar supeda 2.pdf | 17 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sagar supeda 3.pdf | 17 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SAMARPAN FORM 2A FINAL.pdf | 17 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 1.pdf | 17 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 2.pdf | 17 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 3.pdf | 17 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Samarpan final inventory.pdf | 17 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FROM 5 2022-23 samarpan.pdf | 17 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate - Samarpan.pdf | 17 Jun 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: SAMARPAN FORM 4.pdf | 17 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance.pdf | 28 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (1).pdf | 28 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F.pdf | 23 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc 1.pdf | 21 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc 2.pdf | 21 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc 3.pdf | 21 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc 4.pdf | 21 Aug 2023 |
| Declaration in FORM BFile: Form B.pdf | 18 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Site Supervisor's Certificate.pdf | 18 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Disclodure of Sold and Unsold inventory 1.pdf | 18 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Disclodure of Sold and Unsold inventory 2.pdf | 18 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Disclodure of Sold and Unsold inventory 3.pdf | 18 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Disclodure of Sold and Unsold inventory 4.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 1_compressed.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 2_compressed.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 3_compressed.pdf | 18 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 4_compressed (1).pdf | 18 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: sangeeta.pdf | 18 Aug 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Letter (5).pdf | 18 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: ilovepdf_merged (64).pdf | 17 Aug 2023 |
| Details of encumbrances concerned to LegalFile: ilovepdf_merged (64).pdf | 17 Aug 2023 |
| Declaration about Commencement CertificateFile: Form D.pdf | 17 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 1.pdf | 17 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 2.pdf | 17 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 3.pdf | 17 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate 4.pdf | 17 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 17 Aug 2023 |
| Layout approvalFile: 1_11zon.pdf | 8 May 2022 |
| Layout approvalFile: 2_11zon.pdf | 8 May 2022 |
| Layout approvalFile: 3_11pdf.pdf | 8 May 2022 |
| Building plan approvalFile: 1_11zon.pdf | 8 May 2022 |
| Building plan approvalFile: 2_11zon.pdf | 8 May 2022 |
| Building plan approvalFile: 3_11pdf.pdf | 8 May 2022 |
| Copy of the legal title reportFile: New Title Report_11zon.pdf | 8 May 2022 |
| Copy of Layout Approval (in case of layout)File: 1_11zon.pdf | 8 May 2022 |
| Copy of Layout Approval (in case of layout)File: 2_11zon.pdf | 8 May 2022 |
| Copy of Layout Approval (in case of layout)File: 3_11pdf.pdf | 8 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_11zon.pdf | 8 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_11zon.pdf | 8 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3_11pdf.pdf | 8 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAMARPAN_11zon.pdf | 8 May 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER DRAFT.pdf | 8 May 2022 |
| Proforma of Allotment letterFile: 1 Proforma of the allotment letter and agreement for sale.pdf | 8 May 2022 |
| Building plan approvalFile: 2289001_IOD_signed Amended.pdf | 18 Apr 2022 |
| PAN CardFile: 1) PAN CARD.pdf | 18 Apr 2022 |
| Details of encumbrancesFile: SAMARPAN NON ENCUMBRANCE CERTIFICATE.pdf | 18 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2289001_IOD_signed Amended.pdf | 18 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 2311867_FirstCC_signed.pdf | 18 Apr 2022 |
| Declaration about Commencement CertificateFile: samarpan declaration.pdf | 18 Apr 2022 |
| Declaration in FORM BFile: FormB_Konark_Samarpan.pdf | 18 Apr 2022 |
| CERSAI detailsFile: BORIVALI SAMARPAN CHS LTD CERSAI.pdf | 18 Apr 2022 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| MODERN ROOP-KAMAL CO-OPERATIVE HOUSING SOCIETY LTDPR1180002501123 | KANDIVALI WEST, Mumbai Suburban | 66 | Oct 2025 | Certificate Signed | Dec 2029 | Not due yet |
| Girnar Apartment Co-Operative Housing Society LimitedPM1180002500885 | BORIVALI WEST, Mumbai Suburban | 106 | Sep 2025 | Ongoing | Dec 2029 | Not due yet |
| BHAVIK DARSHAN CHS LTD AND GAJMUKH CHS LTDP51800051166 | BORIVALI, Mumbai Suburban | 120 | Jun 2023 | Ongoing | Dec 2027 | Not due yet |
| STATE SECTOR BANK EMPLOYEES CHS LTD KAILAS BUILDINGP51800051152 | BORIVALI WEST, Mumbai Suburban | 63 | Jun 2023 | Ongoing | Mar 2026Registered original: Mar 2025 | Not delivered |
| Shanti Kishan CHS LTDP51800045230 | Dahisar East, Mumbai Suburban | 1 | May 2022 | Completed | Jun 2025Registered original: Dec 2024 | Mar 2025 |
| MUNICIPAL EMPLOYEES AKANKSHA CHSLP51800035158 | SVP Road, Mumbai Suburban | - | May 2022 | Completed | Jun 2023 | Late, Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
Keep Boirvali Samarpan CHS Ltd on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Boriwali West6,700+ in Mumbai Suburban
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: Konark Structural Engineers Private Limited
Konark Structural Engineers Private Limited has 10 registrations on MahaRERA, including MUNICIPAL EMPLOYEES AKANKSHA CHSL and Shanti Kishan CHS LTD. Its filings disclose 8 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Boirvali Samarpan CHS Ltd is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Boirvali Samarpan CHS Ltd?
The registered promoter entity is Konark Structural Engineers Private Limited, a company as per the filing. Its CIN U45200MH1998PTC117205 and GSTIN 27AAACK9113B1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Boirvali Samarpan CHS Ltd?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Boirvali Samarpan CHS Ltd?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Boirvali Samarpan CHS Ltd?
The professionals named in the filing: Architect: Ashim Khatri; Engineer: Aditya; Chartered Accountant: Navin Podar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Boirvali Samarpan CHS Ltd?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback