Registration lapsed No litigation declared Residential / Group Housing project

BLUE FORTUNA PHASE II

By ATUL PROJECTS INDIA PRIVATE LIMITED

RG-MH-28275 · RERA P51800026518 · Last updated on MahaRERA portal: 18 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 11 months past the filed date
  • Completion date moved by 26 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2025Possession promised11 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
2 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

BLUE FORTUNA PHASE II is a Residential / Group Housing project by ATUL PROJECTS INDIA PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800026518 on 30 Sep 2020. Possession was promised by 28 Nov 2025 and is now 11 months past that date. The completion date has moved by 26 months from the original filing. 11 of the 13 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameBLUE FORTUNA PHASE II
  • TypeResidential / Group Housing
  • Location
    • MAROL MILITARY ROAD
    • ANDHERI EAST
    • Andheri
    • Mumbai Suburban
    • 400059
  • Pincode400059
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800026518
  • ReraGenie IDRG-MH-28275

Builder

  • NameATUL PROJECTS INDIA PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorNATHALAL BHAGWANJI DELWADIA PATEL
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

11 months past promisethis monthRegisteredSep 2020First promiseSep 2023Revised toNov 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Sep 2020
  • Promised completion28 Nov 2025
  • Revised completionRevised to 28 Nov 2025 (originally 30 Sep 2023)
  • Buildings1 building record
  • Documents filed61 files

Current status

85%11 of 13 units booked

Figures as on 18 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLUE FORTUNANA5513013

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

BLUE FORTUNA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 18 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
MECHANICAL VENTILATIONYes100%
SWIMMING POOLYes100%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered8
Open Space6

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,256 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Feb 2026

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI739.64
Proposed, not sanctioned740 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 GRD FLOOR CENTRE POINT ANDHERI KURLA ROAD MUMBAI 400059

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHM JHAVERI & SONS
EngineerSUFIYAN ARIF KHILJI
EngineerJACON BASTYAW D SOUZA
Chartered AccountantSANKET SHAH
Chartered AccountantKevin Shah & Associates
PartnerRole in project
ATUL PROJECTS INDIA PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017992Sep 2023 → Mar 2024

Reason as filed by the promoterWe have constructed a building but, some technical issues we have not received occupation certificate (OC). Therefore we have applied for extension.

EXT51800025230Sep 2023 → Nov 2025

Reason as filed by the promoterThe application for extension due to litigation pending in High Court and therefore OC not received. We request you to grant extension and we give consent from all 11 members for extension. Please attached documents.

Litigation declared1

CaseCourtStatus
WP/217/2017/2017BOMBAY HIGH COURTFRESH ADMISSION

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Receipt_CC Revalidation.pdf18 Jul 2025
Declaration about Commencement CertificateFile: RE-ENDORSED Further CC_signed.pdf18 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: New Form 5 (Mar 24) - Blue Fortuna P II.pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III - Blue Fortuna II March 2025.pdf7 May 2025
Form 2 Blue Fortuna II29 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form III Blue Fortuna II - Dec24.pdf30 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BF II 2A FY 23-24 New Format.pdf30 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Blue Fortuna PH-2 2023.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Blue Fortuna PH-2 2024.pdf30 Dec 2024
Declaration in FORM BFile: 3Form B.pdf19 Dec 2024
Disclosure of sold/ booked inventoryFile: 5Summery of Sold Unsold units.pdf19 Dec 2024
CERSAI detailsFile: Cersai Declaration.pdf19 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 4Format A.pdf19 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 2Annexure A.pdf19 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 2Annexure AAakash Patel.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Mar24.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Jun24.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Sep24.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III_31-03-2024.pdf11 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD BLUE FORTUNA PHASE 2 (R).pdf16 Jan 2024
Declaration about Commencement CertificateFile: CC Revalidation_AEBP NoteSheet_18534_signed.pdf20 Dec 2023
Declaration about Commencement CertificateFile: Receipt_CC Revalidation.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I (Architect) - Blue Fortuna P II.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III (Sep 23) - Blue Fortuna P II.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2022.pdf29 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2022.pdf29 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2023.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Blue Fortuna Phase II.pdf30 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_Blue Fortuna II (2)_compressed.pdf1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate_Blue Fortuna II (1)_compressed.pdf1 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: APIPL_Blue Fortuna II June22 Form III_compressed.pdf1 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report_200242090695_For_Asset_Based_Search_14_07_2022_13_48_39_844.pdf14 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold Flats.pdf14 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_Blue fortuna II.pdf1 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A sep 21.pdf1 Jun 2022
Disclosure of sold/ booked inventoryFile: Dlsclosure of sold Booked Inventory.pdf1 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3 Blue Fortuna Phase II.pdf31 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Blue Fortuna Phase II.pdf31 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work.pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 sep 21.pdf25 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A sep 21.pdf25 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: APIL ANNUAL REPORT.pdf4 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II_compressed.pdf29 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ATUL PROJECT FORM III_compressed.pdf29 Jun 2021
Declaration about Commencement CertificateFile: Blue Fortuna Phase II.pdf21 Jun 2021
Proforma of Allotment letterFile: Agreement for Sale.pdf25 Sep 2020
Building plan approvalFile: BUILDING PLAN APPROVAL.pdf24 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN APPROVAL.pdf24 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf24 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Sep 2020
Layout approvalFile: LAYOUT PLAN.pdf23 Sep 2020
Copy of the legal title reportFile: Title Certificate.pdf23 Sep 2020
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf23 Sep 2020
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf23 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Sep 2020
Declaration in FORM BFile: Form B.pdf23 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf23 Sep 2020
PAN CardFile: ATUL PROJECTS INDIA PVT LTD.pdf26 Aug 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
BLUE FORTUNAMILLITARY ROAD MAROL ANDHERI EAST MUMBAI 4000591CompletedMar 2020Jul 2018
Blue Orbit 3Near Inorbit Mall goregaon mulund link road malad west mumbai 40006433CompletedFeb 2017Late, Jul 2017
BLUE TULIPBLUE EMPIRE COMPLEX BEHIND EKTA NAGAR MAHAVIR NAGAR KANDIVALI WEST MUMBAI 400067103CompletedJan 2017Late, Jul 2017
BLUE EMPRESSOPP POISAR GYMKHANA DESAI WADI KANDIVALI WEST MUMBAI 40009238CompletedMay 2016Late, Aug 2016
CORPORATE AVENUEOPP SOLITAIRE PARK NEAR MARADOR HOTEL CHAKALA ANDHERI EAST MUMBAI 40009321CompletedMay 2015Late, Jul 2015

How this compares with Mumbai Suburban

85%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 26 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BLUE FORTUNA PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI EAST6,700+ in Mumbai Suburban

2 kmBLUE FORTUNA PHASE IICompleted 106Lapsed / revoked 41Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 250 registered projects within 2 km.

Builder: ATUL PROJECTS INDIA PRIVATE LIMITED

ATUL PROJECTS INDIA PRIVATE LIMITED has 3 registrations on MahaRERA, including BLUE FORTUNA and SAMARTH BLUE MOUNTAINS. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that BLUE FORTUNA PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BLUE FORTUNA PHASE II is delayed beyond 28 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BLUE FORTUNA PHASE II?

The registered promoter entity is ATUL PROJECTS INDIA PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BLUE FORTUNA PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BLUE FORTUNA PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BLUE FORTUNA PHASE II?

The professionals named in the filing: Architect: HM JHAVERI & SONS; Engineer: SUFIYAN ARIF KHILJI; Engineer: JACON BASTYAW D SOUZA; Chartered Accountant: SANKET SHAH; Chartered Accountant: Kevin Shah & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BLUE FORTUNA PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BLUE FORTUNA PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BLUE FORTUNA PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.