Home / Browse projects / Mumbai Suburban, Maharashtra / BLOSSOM RESIDENCY
BLOSSOM RESIDENCY
By HF REALTY
RG-MH-29532 · RERA P51800028538 · Last updated on MahaRERA portal: 8 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BLOSSOM RESIDENCY is a Residential / Group Housing project by HF REALTY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028538 on 10 Mar 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 18 of the 45 units on this registration are recorded sold or booked, and 19 of 22 construction stages are filed complete.
At a glance
Project
- NameBLOSSOM RESIDENCY
- TypeResidential / Group Housing
- Location
- ANDHERI
- VILE PARLE (E)
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800028538
- ReraGenie IDRG-MH-29532
Builder
- NameHF REALTY
- Entity typePartnership
- PartnersASIF ABDUL HABIB CHUNAWALA, ASHFAQUE AHABIB CHUNAWALA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Mar 2021
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
- Buildings2 building records
- Documents filed76 files
Current status
Figures as on 8 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 15 | 15 | 8 | 0 | 8 |
| B WING | NA | 15 | 15 | 37 | 0 | 37 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 8 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 98%.
A WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Progress on shared amenities15
As on 8 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 98% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| A WING | 8 | 8 |
| B WING | 8 | 8 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MR. KASAM ISMAIL PAYAK | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 7.95 cr | Rs 6.19 cr |
| B WING | NA | Rs 7.95 cr | Rs 6.19 cr |
| - | NA | Rs 13.95 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arun Kumar Dube |
| Engineer | Niyaz Ahmed Hanware (Hanware Consultants) |
| Engineer | SWAPNIL OKATE |
| Chartered Accountant | Tushar D. Shah |
| Chartered Accountant | BHUMIKA C. AGARWAL & ASSOCIATES |
| Partner | Role in project |
|---|---|
| HF REALTY | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWith reference to the above case, we wish to inform you that the partial Occupancy Certificate (OCC) for the building has already been issued on 08.05.2024. However, the OCC for 2 sale flats located on the 12th floor in Wing ‘A’ is still pending due to the non-compliance of certain IQA conditions, specifically the completion of the SWD line and road works. The delay is further attributed to the partial encroachment of slum structures on the 9.15-meter-wide D.P. road adjacent to our plot, which is not a part of our property. These encroachments are to be removed by the Municipal Corporation of
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Mar 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Mar 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Mar 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1_DEC 25_ BLOSSOM RESIDENCY.pdf | 8 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2_DEC 25_ BLOSSOM RESIDENCY.pdf | 8 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_DEC 25_ BLOSSOM RESIDENCY.pdf | 8 Apr 2026 |
| Form 1File: FORM 1_JUNE 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 2File: FORM 2_ JUNE 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 3File: FORM 3_ JUNE 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD USNOLD_JUNE 24_ BLOSSOM RESIDENCYNEW.pdf | 27 Jan 2026 |
| Form 1File: FORM 1_ SEP 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 2File: FORM 2_ SEP 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 3File: FORM 3_ SEP 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_SEP 24_BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 1File: FORM 1_ DEC 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 2File: FORM 2_ DEC 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 3File: FORM 3_ DEC 24_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_DEC 24_BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 1File: FORM 1_MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 2File: FORM 2_ MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 3File: FORM 3_ MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1_ JUNE 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1_SEP 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2_ JUNE 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2_SEP 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3_ JUNE 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3_ SEP 25_ BLOSSOM RESIDENCY_organized.pdf | 27 Jan 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A_ MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ BLOSSOM RESIDENCY.pdf | 27 Jan 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf | 21 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSO,D.pdf | 21 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 21 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 21 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 22 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 22 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-BLOSSOM RESIDENCY_SEP 23.pdf | 5 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-BLOSSOM RESIDENCY_SEP 23.pdf | 5 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-BLOSSOM RESIDENCY_22 23.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-BLOSSOM RESIDENCY_SEP 23.pdf | 5 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-BLOSSOM RESIDENCY_SEP 23.pdf | 5 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-BLOSSOM RESIDENCY_22 23.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 11 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 11 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSLOD A WING.pdf | 11 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSLOD B WING.pdf | 11 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 11 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf | 11 Feb 2023 |
| Declaration about Commencement CertificateFile: DEC OF CC BLOSSOM RESIDENCY.pdf | 3 Apr 2022 |
| Declaration about Commencement CertificateFile: DEC OF CC SRA CHL.pdf | 3 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate-compressed.pdf | 3 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 3 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 22.pdf | 3 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A (2).pdf | 3 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A (2).pdf | 3 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSLOD A WING.pdf | 3 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSLOD B WING.pdf | 3 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA CERTIFICATE.pdf | 3 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5.pdf | 3 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5.pdf | 3 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.pdf | 3 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5.pdf | 3 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf | 3 Apr 2022 |
| Layout approvalFile: LP.pdf | 2 Mar 2021 |
| Building plan approvalFile: FP.pdf | 2 Mar 2021 |
| PAN CardFile: H F REALTY PAN CARD.pdf | 2 Mar 2021 |
| Copy of the legal title reportFile: TITLE _ SERACH REPORT_compressed.pdf | 2 Mar 2021 |
| Details of encumbrancesFile: detail of encumbrance hf realty.pdf | 2 Mar 2021 |
| Copy of Layout Approval (in case of layout)File: LP.pdf | 2 Mar 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: FP.pdf | 2 Mar 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: cc hf realty.pdf | 2 Mar 2021 |
| Declaration in FORM BFile: form b _hf realty_compressed.pdf | 2 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: HF REALTY DOC CA CERTIFICATE.pdf | 2 Mar 2021 |
| Proforma of Allotment letterFile: Agreement For Sale .pdf | 2 Mar 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BLOSSOM RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILE PARLE (E)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 351 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: HF REALTY
HF REALTY has 1 registration on MahaRERA, including BLOSSOM RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that BLOSSOM RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if BLOSSOM RESIDENCY is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BLOSSOM RESIDENCY?
The registered promoter entity is HF REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BLOSSOM RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BLOSSOM RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BLOSSOM RESIDENCY?
The professionals named in the filing: Architect: Arun Kumar Dube; Engineer: Niyaz Ahmed Hanware (Hanware Consultants); Engineer: SWAPNIL OKATE; Chartered Accountant: Tushar D. Shah; Chartered Accountant: BHUMIKA C. AGARWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BLOSSOM RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback