ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BLOOMVILLE

Registration lapsed No litigation declared Residential / Group Housing project

BLOOMVILLE

By REDSHIFT BUILDCON

RG-MH-04852 · RERA P52100020688 · Last updated on MahaRERA portal: 22 Aug 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
21 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
1Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

BLOOMVILLE is a Residential / Group Housing project by REDSHIFT BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100020688 on 3 May 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBLOOMVILLE
  • TypeResidential / Group Housing
  • Location
    • HINJAWADI MURANJE
    • HINJAWADI
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100020688
  • ReraGenie IDRG-MH-04852

Builder

  • NameREDSHIFT BUILDCON
  • Entity typePartnership
  • PartnersSUNIKET BAJIRAO RAYKAR, VIKAS SHIVAJIRAO GAIKWAD, SHRIRAM DHANRAJ HANDIBAGH, ARUN BABAN MARATHE, DASHRATH RAJARAM INGALE, RAHUL HANUMANT RAYKAR
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredMay 2019PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 May 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA170000
BNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities19

As on 22 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Water PumpYes0%
Swimming PoolYes0%
Paving of areas appurtenant to Building or WingYes0%
Compound WallYes100%

Parking filed139

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots139
Closed/Covered86
Open Space53
BuildingClosed/CoveredOpen SpaceTotal
A463076
B402363

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,320 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
REDSHIFT BUIDCONPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY, PUNE
Permissible FSI16449.2
Proposed, not sanctioned16,449 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAYUR COLONEY PUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Vishwas Kulkarni KULKARNI
EngineerMr. Dnyaneshwar Biradar
EngineerAIJAJ SIKANDAR NADAF
Chartered AccountantCA Amol Datar
PartnerRole in project
REDSHIFT BUILDCON-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602003Bloomville A and B Wing S.G.S. Maryadit Thro authorized representative Vikram DawkharREDSHIFT BUILDCON04/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Aug 2023

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: REDSHIFE - Part Completion Certificate - A Bldg 03-10-2022.pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate (A and B Wing) 12-07-2023.pdf12 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 (A and B wing) 12-07-2023.pdf12 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate Form 2A (A and B wing) 2021-2022.pdf12 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD (A and B WING) 12-07-2023.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 ( A and B WING) 12-07-2023.pdf12 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form -1.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf28 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A.pdf28 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf28 Feb 2023
Certificates of CA (Form 3)File: Form-3.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5.pdf28 Feb 2023
Details of encumbrancesFile: Encumbrance - Self declaration.pdf14 Dec 2021
Certificates of CA (Form 3)File: FORM 3 RERA 300621.pdf2 Sep 2021
Certificates of CA (Form 3)File: Form 3 300621 certified_compressed.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 31032020 certified.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 310321 certified.pdf13 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate compressed.pdf11 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGR Certificate_compressed.pdf11 Aug 2021
Building plan approvalFile: Revised sanction plans compressed.pdf18 Mar 2021
Layout approvalFile: Layout Plan.pdf18 Mar 2021
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf18 Mar 2021
Building Plan Approval (IOD)File: Revised sanction plans compressed.pdf18 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf18 Mar 2021
Proforma of Allotment letterFile: RERA Draft-REDSHIFT BUILDON Flat -As per RERA Act -Agreement for Sale - -Hinjawadi.pdf1 Aug 2020
Building plan approvalFile: Sanctioned plan.PDF19 Apr 2019
Layout approvalFile: layout.PDF19 Apr 2019
Details of encumbrancesFile: Encumbrance Certificate.pdf19 Apr 2019
Copy of Layout Approval (in case of layout)File: layout.PDF19 Apr 2019
Building Plan Approval (IOD)File: Sanctioned plan.PDF19 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf19 Apr 2019
Proforma of Allotment letterFile: Allotment letter - Bloom Ville.pdf19 Apr 2019
Copy of the legal title reportFile: Search pdf.pdf13 Apr 2019
Declaration in FORM BFile: Affidavit.pdf13 Apr 2019
Certificates of CA (Form 3)File: Form 3.pdf13 Apr 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BLOOMVILLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HINJAWADI13,700+ in Pune

Builder: REDSHIFT BUILDCON

REDSHIFT BUILDCON has 2 registrations on MahaRERA, including BLOOMVILLE and BLOOMVILLE BUILDING C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that BLOOMVILLE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BLOOMVILLE is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BLOOMVILLE?

The registered promoter entity is REDSHIFT BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BLOOMVILLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BLOOMVILLE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BLOOMVILLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BLOOMVILLE?

The professionals named in the filing: Architect: Ar. Vishwas Kulkarni KULKARNI; Engineer: Mr. Dnyaneshwar Biradar; Engineer: AIJAJ SIKANDAR NADAF; Chartered Accountant: CA Amol Datar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BLOOMVILLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BLOOMVILLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BLOOMVILLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.