ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / BILVA

Registration approved No litigation declared Residential/Group Housing project

BILVA

By SHRI PARVATI CONSTRUCTION CO

RG-KA-31928 · RERA PRM/KA/RERA/1249/447/PR/191126/009111 · Last updated on RERA Karnataka portal: 25 Sep 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared

Nothing adverse is on this record. The buyer report still lays out every unit as filed and places this filing against the promoter's other registrations and every project registered within 2 km.

See what the report covers Free either way: .
Oct 2029Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 116 documents Report an error

BILVA is a Residential/Group Housing project by SHRI PARVATI CONSTRUCTION CO in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/191126/009111 on 19 Nov 2026. Possession is promised by 22 Oct 2029.

At a glance

Project

  • NameBILVA
  • TypeResidential/Group Housing
  • Location
    • Belagavi
    • 590019
  • Pincode590019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/191126/009111
  • ReraGenie IDRG-KA-31928

Builder

  • NameSHRI PARVATI CONSTRUCTION CO
  • Entity typeProprietorship
  • GSTIN29ATHPH3173P2Z2
  • Authorized SignatoryMR. VRISHABENDRA P HIREMATH
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2026PromisedOct 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Nov 2026
  • Promised completion22 Oct 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed116 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BILVA---27027

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 25 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 25 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,258 sq m
Named landowners1
LandownerVillageDistrict
SHRI PARVATI CONSTRUCTION CO PROP VRISHABENDRA P HIREMATH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.36 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 12.73 cr-
On-site expenditure-Consultants FeesRs 50.90 lakh-
On-site expenditure-Site OverheadRs 12.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. PARTH SANGOLLI
EngineerEr. PANCHAXSHRI S HIREMATH
Chartered AccountantCA Vilas. S. Halbhavi

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed116

As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/191126/009111 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer Licence Renewed Copy with Self AttestationFile: Engineer Licence Copy Renewed.pdf25 Sep 2026
Form-3 Engineer CertificateFile: Form-3 Engineer.pdf25 Sep 2026
Structural Engineer Licence Copy with Self AttestationFile: Structural Engineer Licence Ack Copy.pdf25 Sep 2026
Affidavit of Renwed Structural Engineer Licence CopyFile: Affidavit Cum Declaration of Structural Engineer Licence.pdf25 Sep 2026
Project Estimation duly Signed by EngineerFile: Brief Estimation Cost.pdf25 Sep 2026
ADLR Certified survey sketch Certifying the Boundary of the Proposed Land-Original survey sketchFile: ADLR SURVEY SKETCH CTS NO 2478.pdf28 Jul 2026
Location and demarcation planFile: Location Demarcation Bilva.png28 Jul 2026
Demarcation of proposed land in original Village map certified by the concern authorityFile: CDP Demarcation Bilva.pdf28 Jul 2026
Reason for delay in registration in this authority so provide details of which does not involve markFile: Self Declration of Start Date.pdf28 Jul 2026
Engineer certificate licenceFile: Engineer Licence Copy.pdf28 Jul 2026
Engineer certificate form-3File: Form-3 Engineer.pdf28 Jul 2026
brief project estimation duly signed by the valid licence holder engineerFile: Brief Estimation Cost.pdf28 Jul 2026
profit and loss account and balance sheet for 2021-22File: P&L Statement 2021-22.pdf28 Jul 2026
Computation Income 2021-22File: Computation Income 2021-22.pdf28 Jul 2026
profit and loss account and balance sheet for 2022-23File: P&L Statement 2022-23.pdf28 Jul 2026
Computation Income 2022-23File: Computation Income 2022-23.pdf28 Jul 2026
Computation Income for 2023-24File: Computation Income 2023-24.pdf28 Jul 2026
ITR 2023-24File: ITR 2023-24.pdf28 Jul 2026
structural engineer licenceFile: Structural Engineer Licence Copy.pdf28 Jul 2026
Proprietorship registration certificateFile: Udyam Registration Certificate.pdf14 Nov 2025
profit and loss account and balance sheet for 2021-22, CA certification with schedules and CA UDINFile: ITR 2021-22.pdf14 Nov 2025
profit and loss account and balance sheet for 2021-22, CA certification with schedules and CA UDINFile: P&L Statement 2021-22.pdf14 Nov 2025
profit and loss account and balance sheet for 2021-22 CA certification with schedules and CA UDINFile: Computation Income 2021-22.pdf14 Nov 2025
profit and loss account and balance sheet for 2022-23 CA certification with schedules and CA UDINFile: ITR 2022-23.pdf14 Nov 2025
profit and loss account and balance sheet for 2022-23 CA certification with schedules and CA UDINFile: P&L Statement 2022-23.pdf14 Nov 2025
profit and loss account and balance sheet for 2022-23 CA certification with schedules and CA UDINFile: Computation Income 2022-23.pdf14 Nov 2025
profit and loss account and balance sheet for 2023-24 CA certification with schedules and CA UDINFile: ITR 2023-24.pdf14 Nov 2025
profit and loss account and balance sheet for 2023-24 CA certification with schedules and CA UDINFile: Computation Income 2023-24.pdf14 Nov 2025
sources of funds to complete the projectFile: Source of Funds Declaration for Bilva.pdf14 Nov 2025
authenticated copy of current year RTCFile: Form-2 E-Swattu.pdf14 Nov 2025
defect free EC from 1-4-2010 to till date continuous, single documentFile: Nil Encumbrance.pdf14 Nov 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed Land-Original survey sketchFile: ADLR SURVEY SKETCH CTS NO 2478.pdf14 Nov 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed Land-Original survey sketchFile: ADLR Sketch Plan.pdf14 Nov 2025
Approved Original Single Plot layout planFile: Not Appliocable for Single Plot Layout & Order for CTS No-2478.pdf14 Nov 2025
Approved Original Single Plot layout plan work orderFile: Single Plot Layout Plan with Demarcation.pdf14 Nov 2025
Building License from Local Authority Original CopyFile: Commencement Certificate.pdf14 Nov 2025
Existing layout plan, sectional and specificationFile: Single Plot Layout Plan with Demarcation.pdf14 Nov 2025
Location and demarcation planFile: Location Demarcation Bilva.png14 Nov 2025
Area development plan approved by the concern authorityFile: Floor Wise Area Calculation Sheet.pdf14 Nov 2025
Approved building plan - Original CopyFile: Approved Plan.pdf14 Nov 2025
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Approved Drawings.pdf14 Nov 2025
commencement certificateFile: Commencement Certificate.pdf14 Nov 2025
Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: CDP Demarcation Bilva.pdf14 Nov 2025
Demarcation of proposed land in original Village map certified by the concern authorityFile: Village Map for CTS 2478.pdf14 Nov 2025
KSPCB NOCFile: KSPCB NOC.pdf14 Nov 2025
Change of land use detailsFile: DC Conversion Copy.pdf14 Nov 2025
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Declaration of All Sanctioned Drawings.pdf14 Nov 2025
Approval/NOC under section 14 of the KTCP ActFile: Change of Land Use as per KTCP Act.pdf14 Nov 2025
Engineer certificate licence validity has expired, hence upload the renewed one with self-attestatioFile: Engineer Licence Copy.pdf14 Nov 2025
Stability Certificate with Structural Engineer SignFile: Stability Certificate Bilva.pdf14 Nov 2025
project section 3(1) notarised affidavitFile: Non-Violation Affidavit.pdf14 Nov 2025
land cost calculation sheetFile: Land Value Calculaion Sheer CTS No 2478.pdf14 Nov 2025
STP design drawing duly mentioning the project name and address along with engineer signatureFile: STP DRAWING.pdf14 Nov 2025
brief project estimation duly signed by the valid license holder engineer whose license is uploadedFile: Brief Estimation Cost.pdf14 Nov 2025
Approval/NOC under section 14 of the KTCP ActFile: Guidelines of KTCP Act.pdf14 Nov 2025
Registration CertificateFile: GST Certificate.pdf-
GST CertificateFile: GST Certificate.pdf-
Certificate issued by CA Form 1File: Form-1 CA Bilva.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation.pdf-
Balance Sheet 2023 - 2024File: Computation Income 2023-24.pdf-
Balance Sheet 2022 - 2023File: Computation Income 2022-23.pdf-
Balance Sheet 2021 - 2022File: Computation Income 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P&L Statement 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L Statement 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR 2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-22.pdf-
Approval Certificate-
Approved Plan-
Sectional Drawing-
Stability Certificate Bilva-
Project Specification of Bilva-
Agreement of Sale Proforma-
ALLOTMENT LETTER-
Form-B Declaration Affidavit-

How this compares with Belagavi

23%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep BILVA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmBILVAOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: SHRI PARVATI CONSTRUCTION CO

SHRI PARVATI CONSTRUCTION CO has 3 registrations on RERA Karnataka, including RUDRAKSHA and BILVA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if BILVA is delayed beyond 22 Oct 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BILVA?

The registered promoter entity is SHRI PARVATI CONSTRUCTION CO, a proprietorship as per the filing. Its GSTIN 29ATHPH3173P2Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BILVA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BILVA?

The professionals named in the filing: Architect: Ar. PARTH SANGOLLI; Engineer: Er. PANCHAXSHRI S HIREMATH; Chartered Accountant: CA Vilas. S. Halbhavi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BILVA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BILVA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BILVA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.