ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / SILVER SHINE

Registration approved No litigation declared Residential/Group Housing project

SILVER SHINE

By SILVER SHINE BUILDERS AND DEVELOPERS

RG-KA-43836 · RERA PRM/KA/RERA/1249/447/PR/090925/008074 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2029Possession promisedno revision filed
2 of 13Construction stages donefurthest along: Upto Plinth Level, 70%
0 of 25Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 81 documents Report an error

SILVER SHINE is a Residential/Group Housing project by SILVER SHINE BUILDERS AND DEVELOPERS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/090925/008074 on 9 Sep 2025. Possession is promised by 30 Jun 2029. 25 of the 25 units on this registration are recorded sold or booked, and 2 of 13 construction stages are filed complete.

At a glance

Project

  • NameSILVER SHINE
  • TypeResidential/Group Housing
  • Location
    • Belagavi
    • 590019
  • Pincode590019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/090925/008074
  • ReraGenie IDRG-KA-43836

Builder

  • NameSILVER SHINE BUILDERS AND DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN07AEXFS8079J1ZA
  • Authorized SignatorySUHIB Asif I ANKALGI

Key dates

this monthRegisteredSep 2025PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Sep 2025
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed81 files

Current status

100%25 of 25 units booked
22.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SILVER SHINE---25025

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 13 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 70%.

Building: 27% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level70%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)Not applicable
RCC or MS Framed structure30%
Masonry Construction5%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area475 sq m
Named landowners1
LandownerVillageDistrict
SILVER SHINE BUILDERS AND DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.70 cr
Cost incurredRs 1.30 cr
Spent of the estimate22.81%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.45 crRs 1.30 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 20.00 lakh-
Payment of taxesRs 3.00 lakh-
Architech, Engineer, Designers and other consultant feesRs 2.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerFAKRUDDIN MEERASAB SUTGATTI
Chartered AccountantSANKANNAVAR MOOLYA & CO

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed81

As listed on the registration, under the names the promoter filed them with; the newest 80 of 81 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/090925/008074 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Silver_Shine_Declaration.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: architect.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: engineer.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: DeclarationNonAvailability.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: DeclarationNonAvailability.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SILVER SHINE Q4 2.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Declaration_Non-Availability.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: SILVER SHINE Q4 (2).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Declaration_Non-Availability.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SILVER SHINE Q3- 2025-26.pdf22 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: SILVER SHINE Q3- 2025-26.pdf22 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: SILVER SHINE Q3- 2025-26.pdf22 Jan 2026
Certificate of registration of partnership firmFile: Shine Registration certificate.pdf2 Sep 2025
Conversion order issued by the deputy commissionerFile: NA ORDER.pdf2 Sep 2025
Financials 2023-24File: Financials 2023-24.pdf14 Aug 2025
Declaration for non availability of Financials in 2022-23 and 2024-25File: Non Availability of Financial Documents .pdf14 Aug 2025
What are all sources of fund to complete the project with supporting documentsFile: Sources of funds.pdf14 Aug 2025
Upload CA certificate in prescribed format form-01File: CA Certificate with UDIN.pdf14 Aug 2025
Upload Bank account name should be as per bank account direction circularFile: Escrow Account Details.pdf14 Aug 2025
Partners details are not matched with partnership deed- Both Deed AttachedFile: Partnership Deed.pdf14 Aug 2025
certificate of registration of partnership firmFile: Shine Registration certificate.pdf14 Aug 2025
conversion order issued by the deputy commissionerFile: NA ORDER COPY.pdf14 Aug 2025
latest katha extractFile: Khata.pdf14 Aug 2025
Approved Original Single Plot layout planFile: Single Layout Plan.pdf14 Aug 2025
Approved Original Single Plot layout plan order.File: Non Applicability of Single Plan Layout.pdf14 Aug 2025
Building License from Local Authority Original Copy.File: SILVER SHINE COMMENCEMENT CERTIFICATE.pdf14 Aug 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Sketch Silvershine.pdf14 Aug 2025
Letter with details of the project , with clear demarcation.File: Letter Related with Longitute and Latitude.pdf14 Aug 2025
Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: SILVER SHINE APPROVED DWG.pdf14 Aug 2025
Upload commencement certificate.File: SILVER SHINE COMMENCEMENT CERTIFICATE.pdf14 Aug 2025
Demarcation of proposed land in Approved Master plan Certified by the competent authority.File: CDP Plan.jpeg14 Aug 2025
Declaration for Non Availability of village mapFile: Non Applibility of Village Map.pdf14 Aug 2025
Declaration - Approval/NOC under section 14 of the KTCP Act from competent Authority.File: Non Applicability of Non Applicability KTCP.pdf14 Aug 2025
Declaration for not excuting sales and delay in registrationFile: Declaration for Not executing any sales along with reason for delay in Registration.pdf14 Aug 2025
Upload the Engineer certificate pertaining to new project.File: F M SUTAGATTI (Engineer Certificate).pdf14 Aug 2025
Upload structural stability certificate duly signed by the Structural engineerFile: Stability - Silver-Shine-B-wing.pdf14 Aug 2025
Upload project specification with signature.File: Project Specification for Silvershine.pdf14 Aug 2025
Upload the brief project estimation details with Engineer signature.File: Project Cost Estimation.pdf14 Aug 2025
Upload ESCOM NOC with fee paid receipts.File: HESCOM NOC (1).pdf14 Aug 2025
Upload water supply NOC with fee paid receipts.File: Non Applicability Water Supply.pdf14 Aug 2025
Kindly upload the STP design drawing certified by the Engineer as per the guidelines.File: Non Applicability of STP.pdf14 Aug 2025
Bank AffidavitFile: rera bank affidavit_compressed.pdf14 Aug 2025
Clarification on Validity of Sanction PlanFile: Clarification regarding clarity on Sanction Plan Validity.pdf14 Aug 2025
Agreement for Sale DraftFile: ATS SILVER SHINE.pdf14 Aug 2025
Allotment Letter SilvershineFile: ALLOTMENT LETTER SILVERSHINE.pdf14 Aug 2025
Land cost calculation sheet as per the guidance value(Self-attested copy).File: Guidance Value with Registrar Details.jpeg14 Aug 2025
Summary of all the queries and repliesFile: Silvershine Query Summary.pdf14 Aug 2025
RTC, survey 4857/65/10-
Mutation, survey 4857/65/10-
Encumbrance Certificate, survey 4857/65/10-
Sale/Title/Gift Deed, survey 4857/65/10-
Khatha, survey 4857/65/10-
Registration CertificateFile: Shine Partnership deed COMPANY (1).pdf-
GST CertificateFile: GST Certificate- Silver shine Builders and Developers.pdf-
Partnership DeedFile: partnership deed of company.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Certificate with UDIN.pdf-
Certificate issued by Engineer Form 3File: F M SUTAGATTI (Engineer Certificate).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: AFFIDAVIT CUM DECLARATION (NON LITIGATION).pdf-
Balance Sheet 2023 - 2024File: Balance Sheet.pdf-
Audited Profit and Loss Statement 2023 - 2024File: P&L.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: IT ACKNOWLEDGEMENT.pdf-
SHINE PERMISSION-
SILVER SHINE APPROVED DWG (1)-
SILVER SHINE APPROVED DWG-
Reconsitition Deed-
FORM - B-
section 3 affidavit-

How this compares with Belagavi

100%of this project is bookeddistrict median 39%
24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep SILVER SHINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmSILVER SHINEOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: SILVER SHINE BUILDERS AND DEVELOPERS

SILVER SHINE BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including SILVER SHINE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if SILVER SHINE is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SILVER SHINE?

The registered promoter entity is SILVER SHINE BUILDERS AND DEVELOPERS, a partnership firm as per the filing. Its GSTIN 07AEXFS8079J1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SILVER SHINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SILVER SHINE?

The professionals named in the filing: Engineer: FAKRUDDIN MEERASAB SUTGATTI; Chartered Accountant: SANKANNAVAR MOOLYA & CO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SILVER SHINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SILVER SHINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SILVER SHINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.