BHAVANI RESIDENCY
RG-KA-46004 · RERA PRM/KA/RERA/1273/318/PR/210810/004257 · Last updated on RERA Karnataka portal: 30 Jul 2021
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
BHAVANI RESIDENCY is a Residential/Group Housing project by MS BHAVANI DEVELOPERS in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/210810/004257 on 10 Aug 2021. Possession is promised by 30 Sep 2024. 0 of the 24 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.
At a glance
Project
- NameBHAVANI RESIDENCY
- TypeResidential/Group Housing
- Location
- Udupi
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1273/318/PR/210810/004257
- ReraGenie IDRG-KA-46004
Builder
- NameMS BHAVANI DEVELOPERS
- Entity typePartnership Firm
- Authorized SignatoryNARAYAN ACHAR
- OthersPUNEETH KUMAR, VIJAY RAMANAN, BHAVANI, NARAYAN ACHAR, APARNA BHAT
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Aug 2021
- Promised completion30 Sep 2024
- Revised completionNone
- Buildings1 building record
- Documents filed61 files
Current status
Figures as on 30 Jul 2021, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BHAVANI RESIDENCY | - | - | - | 24 | 0 | 24 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 30 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 30 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MS BHAVANI DEVELOPERS | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGISHCHANDRA DHARA |
| Engineer | M GOPAL BHAT |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed61
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/210810/004257 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Bank account name should be as per bank account direction circularFile: BANK PASS BOOK.pdf | 30 Jul 2021 |
| bank pass bookFile: BANK PASS BOOK.pdf | 19 Jul 2021 |
| approved building Elevation, Cross Section and Site planFile: SECTION AND ELEVATION.pdf | 19 Jul 2021 |
| approved building Elevation, Cross Section and Site planFile: SANCTION PLAN 1.pdf | 19 Jul 2021 |
| Previous Project DetailsFile: PREVIOUS DETAILS.pdf | 19 Jul 2021 |
| CertificateFile: FIRM REGISTRATION CERTIFICATE.pdf | - |
| ApprovalCertificate | - |
| SANCTION PLAN 1 | - |
| SINGLE LAYOUT (2)-compressed | - |
| SALEDEED-compressed | - |
| SANCTION PLAN 1 | - |
| PARTNERSHIP DEED | - |
| BROCHER | - |
| SPECIFICATION | - |
| EC 2005 TO 2021 | - |
| AFFIDAVITH | - |
| AFFIDAVITH | - |
| E KHATHA | - |
| PARTNERSHIP DEED | - |
| Unnamed document | - |
| CONVERTION COPY | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| HELTH DEPT NOC | - |
| MESCOM NOC | - |
| water supply NOC | - |
| KSPCB | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| SINGLE LAYOUT (2)-compressed | - |
| SANCTION PLAN 1 | - |
| CONVERTION COPY | - |
| Unnamed document | - |
| Income Tax Return Acknowledgement 2019 - 2020File: CA CERTIFICATE.jpg | - |
| FORM B | - |
| Prospectus/BrochureFile: Brochure_BHAVANI RESIDENCY.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1273_318_PR_210810_004257.xlsx | - |
| Loan raised documentFile: DESIGNATED AC.pdf | - |
| Stability CertificateFile: STABILITY CERTIFICATE- BHAVANI RESIDENCY.pdf | - |
| Occupancy CertificateFile: occupancy certificate-bhavani.pdf | - |
| Consent for operation issued by KSPCBFile: POLLUTION BOARD.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT PERMISSION FROM ELECTRICAL DEPT.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: ELECTRICITY DEPT.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form-5_Architect Certificate.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4_Chartered Accountant Certificate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: COMPLETION- AFFIDAVIT.pdf | - |
| ENGINEER CERTIFICATEFile: Form-6_Engineer Certificate.pdf | - |
| BANK SECURITYFile: BADAGUBETTU SOCIETY.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep BHAVANI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: MS BHAVANI DEVELOPERS
MS BHAVANI DEVELOPERS has 1 registration on RERA Karnataka, including BHAVANI RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if BHAVANI RESIDENCY is delayed beyond 30 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of BHAVANI RESIDENCY?
The registered promoter entity is MS BHAVANI DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in BHAVANI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at BHAVANI RESIDENCY?
The professionals named in the filing: Architect: YOGISHCHANDRA DHARA; Engineer: M GOPAL BHAT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BHAVANI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.