Home / Browse projects / Pune, Maharashtra / Bhargav Bellina

Registration lapsed No litigation declared Others project

Bhargav Bellina

By Bhargav Buildcon

RG-MH-04759 · RERA P52100020200 · Last updated on MahaRERA portal: 26 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 70%
23 of 56Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

Bhargav Bellina is a Others project by Bhargav Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100020200 on 29 Mar 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 18 months from the original filing. 33 of the 56 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameBhargav Bellina
  • TypeOthers
  • Location
    • Near Pune Banglore Highway
    • Warje Pune
    • Warje
    • Haveli
    • Pune
    • 411058
  • Pincode411058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020200
  • ReraGenie IDRG-MH-04759

Builder

  • NameBhargav Buildcon
  • Entity typePartnership
  • PartnersLalitkumar Bhausaheb Kudale, Mahesh Shripati Kokate, Sandeep Sonaba Jagade, Shreeniwas Sopan Londhe, Yuvraj Bhausaheb Kudale, Rahul Tryambak Date
  • Declared earlier projects5 →

Key dates

16 months past promisethis monthRegisteredMar 2019First promiseDec 2023Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Mar 2019
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed72 files

Current status

59%33 of 56 units booked

Figures as on 26 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bhargav BellinaNA1512401656

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 70%.

Bhargav Bellina: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 26 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Closed/Covered37
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
USK VenturesPune (M Corp.)Pune

Approvals and building plan

Sanctioning authoritypune muncipal corporation
Permissible FSI3279.31
Proposed, not sanctioned1,173 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJ M Road Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVilas J Yele
EngineerSneha Jadhav
Chartered AccountantSPCM & Associates
PartnerRole in project
Bhargav Buildcon-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018111Dec 2023 → Dec 2024

Reason as filed by the promoterThat due to the Covid-19 pandemic, reverse migration of labourers to their native places, and scarcity in supply chain of construction material as well as 30% enhanced construction cost thereof, the construction activity has been severely impacted. Thus, till date the Developer has completed the 80% of the work till date and is unable to complete the 100% project on or before 30/12/2023 therefore hereby requesting for extension of the same and assured to complete the project on or before 29/12/2024.

EXT52100025796Dec 2023 → Jun 2025

Reason as filed by the promoterThis Self-explanatory note has been prepared on the basis of requirement under [See rule 7(3)] of Maharashtra Real Estate Rules 2017 for Extension of registration of the Real estate project. Reasons for delay in completion of the Project A) Cash Crunch B) Shortage of Material 98% Work of project is completed

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000228369Dilshad Faruk ShaikhBhargav Buildcon22/02/2023
CC12400934Mukund p PataskarBhargav Buildcon29/11/2024
CC12400988Shreya Deepak KulkarniBhargav Buildcon03/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina Form 1 Architect Certificate mar 24.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina Form 1 Architect Certificate june 24.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina Form 1 Architect Certificate Dec 24.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina Form 1 Architect Certificate mar 25.pdf26 May 2025
Certificates of CA (Form 3)File: Form 3 2023 - 2024.pdf26 May 2025
Certificates of CA (Form 3)File: 2 Form 3 30062024_11zon.pdf26 May 2025
Certificates of CA (Form 3)File: 3 Form 3 30092024_11zon.pdf26 May 2025
Certificates of CA (Form 3)File: 4 Form 3 31122024_11zon.pdf26 May 2025
Certificates of CA (Form 3)File: Form 3 31032025_11zon.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 Engineer Certificate 31122023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 31032025.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 Engineer Certificate 31122023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Form 2 Engineer Certificate 30092023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Engineer Certificate 30062023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form 2 Engineer Certificate 31032023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Form 2 Engineer Certificate 30092023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Engineer Certificate 30062023.pdf26 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form 2 Engineer Certificate 31032023.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv Dec 23_organized.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv Mar 24.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv june 24.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv oct 24.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv dec 24.pdf26 May 2025
Disclosure of sold/ booked inventoryFile: Bellina sold inv march 25.pdf26 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Belina 2A 23-24.pdf26 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023 - 2024.pdf26 May 2025
Declaration about Commencement CertificateFile: Bellina-Form-D.pdf10 Jan 2024
Declaration in FORM BFile: Notarized Affidavit-Bellina-RERA Form-B.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina-Architect-Cert-300623.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina-Architect-Cert-300923.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bellina-Architect-Cert-311223.pdf10 Jan 2024
Form 2AFile: BLFORM231March2022.pdf10 Jan 2024
Form 2AFile: BLFORM2June2022.pdf10 Jan 2024
Form 2AFile: BLFORM2Sept2022.pdf10 Jan 2024
Form 2AFile: BLFORM2Dec2022.pdf10 Jan 2024
Form 2AFile: BLFORM231March2023.pdf10 Jan 2024
Form 2AFile: BLFORM2June2023.pdf10 Jan 2024
Form 2AFile: BLFORM2Sep2023.pdf10 Jan 2024
Form 2AFile: BLFORM2Dec2023.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: BLFORM2A31321.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: BLFORM 2A31322.pdf10 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BLFORM2A31323.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: Bellina-Sold-Unsold-Inventary.pdf10 Jan 2024
Certificates of CA (Form 3)File: FORM323.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM522.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM523.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1ARCH3132023.pdf29 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2E3132022.pdf29 Apr 2023
Other - FinanceFile: Mortgage- Warje.pdf29 Apr 2023
Certificates of CA (Form 3)File: SCANNED FORM 03 (31-03-2020)_compressed.pdf15 Sep 2021
Certificates of CA (Form 3)File: SCANNED FORM 03- 2021-Bhargav Bellina-Buildcon-Warje_compressed.pdf15 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: 202-CC-Revised_ Buildcon_compressed.pdf28 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bhargav Bellina Warje RERA Archi From-1.pdf12 Oct 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Bhargav Bellina Warje RERA Archi From-1.pdf12 Oct 2019
Declaration in FORM BFile: Bhargav Bellina-Form-B- Warje.pdf2 Oct 2019
Form 2AFile: Bhargav Bellina-Form-2A- Engineer Certificate Warje_compressed.pdf2 Oct 2019
Form 2AFile: Bhargav Bellina Warje Form 2 A_compressed.pdf27 Jun 2019
Building plan approvalFile: Warje layout.pdf27 Mar 2019
Layout approvalFile: Warje layout.pdf27 Mar 2019
PAN CardFile: Bhargav Buildcon Pan Card.pdf27 Mar 2019
Copy of the legal title reportFile: Compressed Title.pdf27 Mar 2019
Details of encumbrancesFile: Warje no encumbrances.pdf27 Mar 2019
Copy of Layout Approval (in case of layout)File: Warje layout.pdf27 Mar 2019
Building Plan Approval (IOD)File: Warje layout.pdf27 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: WARAJE New Revised CC 2018-compressed.pdf27 Mar 2019
Declaration in FORM BFile: Warje affidavit form B-compressed.pdf27 Mar 2019
Certificates of CA (Form 3)File: Warje Bhargav Buildcon CA CERTIFICATE (3).pdf27 Mar 2019
Proforma of Allotment letterFile: RERA Allotment of Flat.pdf27 Mar 2019
OtherFile: Warje 712.pdf27 Mar 2019
OtherFile: Warje NA Order.pdf27 Mar 2019
OtherFile: Warje Index.pdf27 Mar 2019

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VivianaPanchavati Nashik92CompletedSep 2017Jul 2017
Rarajya SankulPanchavati Nashik70CompletedMar 2017Late, Jul 2017
Abelone BAmbegaon BK64CompletedMar 2016Jan 2016
Anuj ApartmentWadgaon BK6CompletedJun 2014May 2014
Bhargav HouseHingane Kh6CompletedMar 2014Mar 2014

How this compares with Pune

59%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhargav Bellina on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Warje Pune13,700+ in Pune

2 kmBhargav BellinaCompleted 40Lapsed / revoked 25Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: Bhargav Buildcon

Bhargav Buildcon has 1 registration on MahaRERA, including Bhargav Bellina. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Bhargav Bellina shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Bhargav Bellina is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhargav Bellina?

The registered promoter entity is Bhargav Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhargav Bellina?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Bhargav Bellina?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Bhargav Bellina?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhargav Bellina?

The professionals named in the filing: Architect: Vilas J Yele; Engineer: Sneha Jadhav; Chartered Accountant: SPCM & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhargav Bellina?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhargav Bellina. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhargav Bellina to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.