Home / Browse projects / Thane, Maharashtra / Bharat Ecovistas Phase III
Bharat Ecovistas Phase III
By BHARAT REALTY VENTURE PRIVATE LIMITED
RG-MH-84692 · RERA P51700015290 · Last updated on MahaRERA portal: 17 Mar 2025
Source: official MahaRERA filing
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 22 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Bharat Ecovistas Phase III is a Residential / Group Housing project by BHARAT REALTY VENTURE PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700015290 on 15 Feb 2018. The registration is recorded completed; possession was promised by 10 Oct 2023. The completion date has moved by 22 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameBharat Ecovistas Phase III
- TypeResidential / Group Housing
- Location
- Old Mumbai Pune Highway
- Shilphata Junction
- Thane
- Thane (M Corp.)
- Thane
- 400616
- Pincode400616
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700015290
- ReraGenie IDRG-MH-84692
Builder
- NameBHARAT REALTY VENTURE PRIVATE LIMITED
- Entity typeCompany
- CINU45200MH1998PTC116452
- GSTIN27AABCB3630P1ZJ
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorAtul Ambalal Barot
- Other registrations10 more →
- Completed7 of 11
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects11 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Feb 2018
- Promised completion10 Oct 2023
- Revised completionRevised to 10 Oct 2023 (originally 31 Dec 2021)
- Buildings2 building records
- Documents filed144 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ecovistas Building E2 Mayfield | NA | 27 | 0 | 0 | 0 | 0 |
| Ecovistas Building F1 Glenfield | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 17 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
Ecovistas Building E2 Mayfield82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Ecovistas Building F1 Glenfield82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities17
As on 17 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Clubhouse | Yes | 100% |
Parking filed218
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Ecovistas Building E2 Mayfield | 127 | 2 | 129 |
| Ecovistas Building F1 Glenfield | 79 | 10 | 89 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Joshi Deshaware and Associates |
| Architect | Vasant Pissay |
| Partner | Role in project |
|---|---|
| BHARAT REALTY VENTURE PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSub: Corrections in FORM B DECLARATION- Project Registration Certificate No. P51700015290 dated 15.02.2018, Bharat Ecovistas Phase III- reg With reference to the captioned subject matter, we have registered with your Hon’ble Authority a Project pertaining to ALL THAT pieces or parcels of non-agricultural land or ground, hereditaments and premises admeasuring about 25200 Sq.Mtrs or thereabouts comprised under Survey No.67/C/4 previously forming part of (Undivided) Survey No. 67, Hissa No.2A and Survey No.67, Hissa No.3A situate in the Village of Shil, Taluka and District Thane, Registration Dis
Reason as filed by the promoterSubject : Extension u/s 7 (3 ) - Reason for extension only for the project closure This is to inform the authority that the project had received the occupancy certificate in two parts dated 13.07.2023 and 10.10.2023. Since only for the purpose of project closure we are taking the extension till 10.10.2023, kindly consider the same and allow us to get the project closed. The project is already handed over to the society members.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000354303 | Chetan Kumar | Atul Ambalal Barot | 28/05/2023 |
| CC12501246 | BHARAT REALTY VENTURE PRIVATE LIMITED | SAHAWAZ RAHAT KHAN and FARANA KHAN | 14/04/2025 |
| CC12503761 | BHARAT REALTY VENTURE PRIVATE LIMITED | Shahadat Ali Mohd Siddiq Shaikh | 28/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jan 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jan 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jan 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Oct 2023
Documents filed144
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: ECOVISTA PHASE 3 SOLD UNSOLD.pdf | 17 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ecovistas Phase III Sep 2023.pdf | 13 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf | 5 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 5 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA.pdf | 5 Mar 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 E2 F1.pdf | 21 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: mayfield form 4.pdf | 22 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: mayfield form 4.pdf | 22 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 E2.pdf | 28 Oct 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate Mayfield.pdf | 26 Dec 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf | 12 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Ecovistas Phase III Sold Inventory Sep 2023.pdf | 30 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas E2 Architects Certificate Sep 2023.pdf | 17 Oct 2023 |
| Certificates of CA (Form 3)File: CA FORM 3 Ecovistas III Sep 2023.pdf | 17 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate for E2 Mayfield .pdf | 11 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Ecovistas Phase III Sold Inventory June 2023.pdf | 11 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance Ecovistsa III.pdf | 8 Aug 2023 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance Ecovistsa III.pdf | 8 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure Intrest.pdf | 8 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Ecovistas 30th June 2023.pdf | 5 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate Ecovistas 30th June 2023.pdf | 5 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 A Achrekar FY 2022-23 19072023.pdf | 19 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas F-1 Architects Certificate - 30-06-2023.pdf | 17 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas E-2 Architects Certificate - 30-06-2023.pdf | 17 Jul 2023 |
| Certificates of CA (Form 3)File: Form3 CA Certificate for ECOVISTAS RERA AS ON 30062023 (1)_compressed (3).pdf | 17 Jul 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bharat Eco Vista F1 OC certificate 13-07-2023.pdf | 14 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineers Certificates - Ecovistas.pdf | 13 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Ecovistasb Phase III Sold Flat March 2023.pdf | 25 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas Phase III March 2023.pdf | 7 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineers Certificates - Ecovistas III 31St March 2023.pdf | 7 Apr 2023 |
| Certificates of CA (Form 3)File: Ecovistas Phase III CA form 3.pdf | 7 Apr 2023 |
| Certificates of CA (Form 5)File: FORM 5 Ecovistas Phase III.pdf | 7 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certifciate From 5 Ecovistas III June 2022.pdf | 24 Mar 2023 |
| Details of encumbrancesFile: Indenture of Mortgage dated 02nd March 2023 Bajaj finance 10 CR index 2 rera.pdf | 8 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Ecovistas III Sold Flats Dec 2022.pdf | 25 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineers Certificates - Ecovistas (Phase III).pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: Eco vistas 31st Dec 2022.pdf | 12 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas Phase III 31 Dec 2022 F1.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas Phase III 31 dec 2022.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ecovistas Phase III Sep 2022.pdf | 2 Jan 2023 |
| Certificates of CA (Form 3)File: RERA ECOVISTA PHASE III Sep 2022.pdf | 2 Jan 2023 |
| OtherFile: Transfer Deed of Amenity Plot Handedover.pdf | 20 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Phase III Sold June 2022.pdf | 10 Aug 2022 |
| OtherFile: 1LETTER INFORMING HANDOVER OF 15 OF THE PROJECT LAND TO TMC.pdf | 8 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate III Glenfield E2 June 2022.pdf | 26 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate III Mayfield E2 june 2022.pdf | 26 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovistas.pdf | 26 Jul 2022 |
| Certificates of CA (Form 3)File: CA Form 3 June 2022 Ecovistas Phase III.pdf | 26 Jul 2022 |
| Certificates of CA (Form 3)File: CA certificate june 2022 Phase III.pdf | 26 Jul 2022 |
| Details of encumbrancesFile: Mortgage Deed Dated 27th May 2022 15 CR with Bajaj Finance - INDEX 2.pdf | 1 Jun 2022 |
| PAN CardFile: New pancard.pdf | 19 May 2022 |
| OtherFile: Deed Of Right Of Way.pdf | 7 May 2022 |
| Disclosure of sold/ booked inventoryFile: Ecovistas Phase III March 2022.pdf | 19 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovistas - Phase III.pdf | 16 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Glenfield F1 march 2022.pdf | 14 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mayfield E2 March 2022.pdf | 14 Apr 2022 |
| Certificates of CA (Form 3)File: ECO VISTAS RERA.pdf | 14 Apr 2022 |
| Declaration about Commencement CertificateFile: Delcaration for CC Ecovistas III.pdf | 28 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovistas form 2.pdf | 18 Jan 2022 |
| Certificates of CA (Form 3)File: RERA Certificate Ecovistas III Dec 21.pdf | 17 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200227264412_For_Asset_Based_Search_04_01_2022_11_02_05_240.pdf | 4 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200227266307_For_Asset_Based_Search_04_01_2022_11_15_30_269.pdf | 4 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200227266570_For_Asset_Based_Search_04_01_2022_11_17_30_617.pdf | 4 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200227268082_For_Asset_Based_Search_04_01_2022_11_28_27_849.pdf | 4 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovista E2 F1 Sep 2021.pdf | 18 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Ecovistas Phase III Sep 2021.pdf | 18 Oct 2021 |
| Certificates of CA (Form 3)File: RERA Certificate Ecovistas III Sept 21.pdf | 18 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Ecovistas E2 Sep 2021.pdf | 4 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Ecovistas F1 Sep 2021.pdf | 4 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold flat Ecovistas III june 2021.pdf | 11 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovistas Phase III.pdf | 10 Aug 2021 |
| Certificates of CA (Form 3)File: RERA Certificate Ecovistas III Jun 21.pdf | 10 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Ecovistas phase III.pdf | 17 Jul 2021 |
| Details of encumbrancesFile: Scan Copy of Registered Indenture of Mortgage dated 28th June 2021 with Bajaj for RERA.pdf | 12 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate - Ecovistas - E2 - 30 th JUne 2021.pdf | 12 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate - Ecovistas - F1 -30th June 2021.pdf | 12 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecovistas Phase III Eng Certificate March 2021.pdf | 12 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A Ecovistas Pase III June 2021.pdf | 12 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Sold inventary Ecovistas Phase III 30th June 2021.pdf | 12 Jul 2021 |
| Certificates of CA (Form 3)File: RERA Certificate Ecovistas III Mar 21.pdf | 12 Jul 2021 |
Promoter's earlier projects11
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| JUHU vISTAS | Plot No. 50 survey no. 287 CTS no. 484 of Village Vile Parle West | 9 | Completed | Mar 2024 | Late, May 2024 |
| JUHU ACROPOLIS | Gulmohar Cross Road JUPD Scheme JUHU | 75 | Completed | Mar 2024 | Sep 2022 |
| Redevelopment of Existing building no 5 known as Mahavir Nagar Tristar CHSL | Mahavir Nagar Kandivali Wesy | 58 | Completed | Dec 2022 | Sep 2021 |
| Bharat Ecovistas Phase II | Shilphata Junction Thane | 256 | Completed | Dec 2022 | Sep 2020 |
| Redevelopment of Malad Swing | Marve Road Malad West | 73 | Completed | Dec 2021 | Jan 2018 |
| Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase III | D.N. Nagar Andheri West | 93 | Completed | Dec 2021 | Mar 2020 |
| Ecovistas Building D1 Fairfield Phase I | Shilphata Junction Thane | 122 | Completed | Dec 2016 | Late, Apr 2017 |
| Ecovistas Building C2 Moorfield Phase I | Shilphata Junction Thane | 134 | Completed | Dec 2016 | Late, Apr 2017 |
| Redevelopment of God Kamgar Building C3 Wing A Skyvistas Skyz Phase II | D N Nagar Andheri West | 92 | Completed | Sep 2016 | Sep 2016 |
| Redevelopment of Park Darshan CHSL Parkvistas | Lallu Bhai Park Andheri West Mumbai Maharashtra 400058 | 64 | Completed | Dec 2015 | Late, Aug 2016 |
| Redevelopment of Godi Kamgar Building C2 Phase II | D N Nagar Andheri West | 89 | Completed | Apr 2014 | Apr 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 10 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 144 filed documents as one ZIP, foldered, with a manifest
Keep Bharat Ecovistas Phase III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shilphata Junction, Thane7,600+ in Thane
Filed coordinates, straight-line distance. 67 registered projects within 2 km.
Bharat Ecovistas Phase II
BHARAT REALTY VENTURE PRIVATE LIMITED
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
Plot No -1A,Sector -19, Vashi Truck Terminal
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
Constrcution of 2557 EWS tenements at S.No.157
ARUN SHANKARRAO BORGAVE
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
See every Thane project, with the district possession charts
Builder: BHARAT REALTY VENTURE PRIVATE LIMITED
BHARAT REALTY VENTURE PRIVATE LIMITED has 11 registrations on MahaRERA, including Redevelopment of Malad Swing CHSL and Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase III. Its filings disclose 11 earlier MahaRERA projects: declares 7 of 11 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Bharat Ecovistas Phase III is delayed beyond 10 Oct 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Bharat Ecovistas Phase III?
The registered promoter entity is BHARAT REALTY VENTURE PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1998PTC116452 and GSTIN 27AABCB3630P1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Bharat Ecovistas Phase III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Bharat Ecovistas Phase III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Bharat Ecovistas Phase III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Bharat Ecovistas Phase III?
The professionals named in the filing: Architect: Joshi Deshaware and Associates; Architect: Vasant Pissay. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bharat Ecovistas Phase III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback