BHARAT REALTY VENTURE PRIVATE LIMITED: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

BHARAT REALTY VENTURE PRIVATE LIMITED has 11 registrations in this build, including Redevelopment of Malad Swing CHSL and Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase III. Its filings disclose 11 earlier MahaRERA projects: 7 of 11 past projects completed on time. Litigation is declared on 2 of its registrations.

11Registrations in this build
11Past projects disclosed
on timeMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Redevelopment of Malad Swing CHSLMumbai Suburban, Maharashtra--Completed
Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase IIIMumbai Suburban, Maharashtra--Completed
Bharat Ecovistas Phase IIThane, Maharashtra--Completed
Redevelopment of Ganpati Niwas CHSLMumbai Suburban, Maharashtra9100%Registration lapsed
Redevelopment of Existing Building No. 5 known as Mahavir Nagar Tri-star CHSLMumbai Suburban, Maharashtra--Completed
Bharat Ecovistas Phase IIIThane, Maharashtra--Completed
JUHU ACROPOLISMumbai Suburban, Maharashtra--Completed
JUHU VISTASMumbai Suburban, Maharashtra--Completed
Proposed Residential cum Commercial Redevelopment of Apna Ghar Unit No. 9 CHSLMumbai Suburban, Maharashtra28347%Registered
Proposed Redevelopment of Existing Building Known as Queens Croft CHSLMumbai Suburban, Maharashtra5535%Registered
BHARAT AURAVISTASMumbai Suburban, Maharashtra18346%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Redevelopment of Godi Kamgar Building C2 Phase II
17 Apr 201417 Apr 2014On time
Redevelopment of Park Darshan CHSL Parkvistas
31 Dec 201520 Aug 2016+8 months
Redevelopment of God Kamgar Building C3 Wing A Skyvistas Skyz Phase II
7 Sep 20167 Sep 2016On time
Ecovistas Building C2 Moorfield Phase I
31 Dec 20163 Apr 2017+3 months
Ecovistas Building D1 Fairfield Phase I
31 Dec 20163 Apr 2017+3 months
Redevelopment of Malad Swing
31 Dec 202130 Jan 2018On time
Redevelopment of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase III
31 Dec 20219 Mar 2020On time
Bharat Ecovistas Phase II
31 Dec 202222 Sep 2020On time
Redevelopment of Existing building no 5 known as Mahavir Nagar Tristar CHSL
31 Dec 202215 Sep 2021On time
JUHU ACROPOLIS
30 Mar 202416 Sep 2022On time
JUHU vISTAS
30 Mar 20246 May 2024+1 months

Frequently asked questions

How do I verify BHARAT REALTY VENTURE PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with BHARAT REALTY VENTURE PRIVATE LIMITED?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make BHARAT REALTY VENTURE PRIVATE LIMITED unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.