ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BHAKTI AANGAN

Registered No litigation declared Residential / Group Housing project

BHAKTI AANGAN

By NIRMITI DEVELOPERS

RG-MH-62860 · RERA P52100020919 · Last updated on MahaRERA portal: 14 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 85 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 85 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 20%
32 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 161 documents Report an error

BHAKTI AANGAN is a Residential / Group Housing project by NIRMITI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100020919 on 23 May 2019. Possession is promised by 31 Dec 2028. The completion date has moved by 85 months from the original filing. 0 of the 32 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameBHAKTI AANGAN
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO 224/B KADOLKAR COLONY
    • VADGAON MAVAL
    • Wadagaon (CT)
    • Mawal
    • Pune
    • 412106
  • Pincode412106
  • RERA no.P52100020919
  • ReraGenie IDRG-MH-62860

Builder

  • NameNIRMITI DEVELOPERS
  • Entity typePartnership
  • PartnersSAMBHAJI DAMODAR TONAGE, RAJAN SHIVRAM PATIL, PARATAPRAO KALYANRAO PATIL
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

this monthRegisteredMay 2019First promiseNov 2021Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 May 2019
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 28 Nov 2021)
  • Buildings2 building records
  • Documents filed161 files

Current status

0%0 of 32 units booked
52.0%Work done, per cost certificate

Figures as on 14 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA5416016
B WINGNA5416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 20%.

A WING38%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING38%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered10
Open Space30
BuildingClosed/CoveredOpen SpaceTotal
A WING52025
B WING51015

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area948 sq m
Land owned byNot the promoter
Named landowners3
LandownerVillageDistrict
VIJAYA DEVIDAS SHIDOREWadagaon (CT)Pune
SEEMA VIJAY UBHE AND VISHAL EKNATH BORHADEWadagaon (CT)Pune
SANTOSH NARAYAN ZAREKARWadagaon (CT)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI1086.28
Proposed, not sanctioned1,086 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No- 6, 7, 8 A, Ground Floor, Saras Plaza Apartments, Samsan Nagar Chs Limited, Success Chambers
Estimated costRs 2.60 cr
Cost incurredRs 1.35 cr
Work done52.05%
BuildingWingEstimatedIncurred
A WINGNARs 1.23 crRs 67.66 lakh
B WINGNARs 1.23 crRs 67.66 lakh
-NARs 15.00 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM J ASSOCIATES
EngineerRAVINDRA A KARNAVAT AND ASSOCIATES
EngineerSachin G Sonawane
Chartered AccountantM S KUMBHAR AND ASSOCIATES
Chartered AccountantN. L. Bhakare and Associates
Chartered AccountantRanjeetkaur Harvindersingh Pothiwal
PartnerRole in project
NIRMITI DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012642Nov 2021 → Dec 2025

Reason as filed by the promoterWe have Not taken any booking from Customer hence consent for extension from Customer dont applicable to us and we here by applied for extension for the project

EA13032620202Nov 2021 → Dec 2028

Reason as filed by the promoterThe project has faced multiple disruptions during its execution period, including the impact of COVID-19 waves, large-scale migration of labour, and reduced market confidence in the Vadgaon area which significantly affected customer bookings and project progress. Due to these circumstances, the pace of construction and sales was adversely impacted. However, the market sentiment in the area has now started improving and there is a renewed interest from prospective buyers. In order to take advantage of this positive momentum and ensure completion of the project in a compliant and systematic mann

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed161

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 161 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate - Mar 26.pdf14 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate - Mar 26.pdf14 Apr 2026
Withdrawal Update Form 3File: CA Certificate_Mar 26.pdf14 Apr 2026
Form 5 (FY 2022-2023)File: Form-5 FY-22-23.pdf27 Mar 2026
Form 5 (FY 2023-2024)File: Form-5 FY-23-24.pdf27 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A 25.pdf25 Mar 2026
Form 5 (FY 2024-2025)File: Form-5 FY-24-25.pdf25 Mar 2026
Form 1File: 1 Arch Cert Jun-22.pdf12 Mar 2026
Form 2File: 1 Engg Cert Jun-22.pdf12 Mar 2026
Form 3File: CA CERT 22-23 1.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 22-23 1.pdf12 Mar 2026
Form 1File: 2 Arch Cert Sep-22.pdf12 Mar 2026
Form 2File: 2 Engg Cert Sep-22.pdf12 Mar 2026
Form 3File: CA CERT 22-23 2.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 22-23 2.pdf12 Mar 2026
Form 1File: 3 Arch Cert Dec-22.pdf12 Mar 2026
Form 2File: 3 Engg Cert Dec-22.pdf12 Mar 2026
Form 3File: CA CERT 22-23 3.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 22-23 3.pdf12 Mar 2026
Form 1File: 4 Arch Cert Mar-23.pdf12 Mar 2026
Form 2File: 4 Engg Cert Mar-23.pdf12 Mar 2026
Form 3File: CA CERT 22-23 4.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 22-23 4.pdf12 Mar 2026
Form 1File: 1 Arch Cert Jun-23.pdf12 Mar 2026
Form 2File: 1 Engg Cert Jun-23.pdf12 Mar 2026
Form 3File: CA CERT 23-24 1.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 23-24 1.pdf12 Mar 2026
Form 1File: 2 Arch Cert Sep-23.pdf12 Mar 2026
Form 2File: 2 Engg Cert Sep-23.pdf12 Mar 2026
Form 3File: CA CERT 23-24 2.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 23-24 2.pdf12 Mar 2026
Form 1File: 3 Arch Cert Dec-23.pdf12 Mar 2026
Form 2File: 3 Engg Cert Dec-23.pdf12 Mar 2026
Form 3File: CA CERT 23-24 3.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 23-24 3.pdf12 Mar 2026
Form 1File: 4 Arch Cert Mar-24.pdf12 Mar 2026
Form 2File: 4 Engg Cert Mar-24.pdf12 Mar 2026
Form 3File: CA CERT 23-24 4.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 23-24 4.pdf12 Mar 2026
Form 1File: 1 Arch Cert Jun-24.pdf12 Mar 2026
Form 2File: 1 Engg Cert Jun-24.pdf12 Mar 2026
Form 3File: CA CERT 24-25 1.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 24-25 1.pdf12 Mar 2026
Form 1File: 2 Arch Cert Sep-24.pdf12 Mar 2026
Form 2File: 2 Engg Cert Sep-24.pdf12 Mar 2026
Form 3File: CA CERT 24-25 2.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 24-25 2.pdf12 Mar 2026
Form 1File: 3 Arch Cert Dec-24.pdf12 Mar 2026
Form 2File: 3 Engg Cert Dec-24.pdf12 Mar 2026
Form 3File: CA CERT 24-25 3.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 24-25 3.pdf12 Mar 2026
Form 1File: 4 ARch Cert Mar-25.pdf12 Mar 2026
Form 2File: 4 Engg Cert Mar-25.pdf12 Mar 2026
Form 3File: CA CERT 24-25 4.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 24-25 4.pdf12 Mar 2026
Withdrawal Update Form 1File: 1 Arch Cert Jun-24.pdf12 Mar 2026
Withdrawal Update Form 1File: 2 Arch Cert Sep-24.pdf12 Mar 2026
Withdrawal Update Form 1File: 3 Arch Cert Dec-25.pdf12 Mar 2026
Withdrawal Update Form 2File: Engg Form 2 31032022.pdf12 Mar 2026
Withdrawal Update Form 2File: Engg Form 2 31032022.pdf12 Mar 2026
Withdrawal Update Form 2File: Engg Form 2 31032022.pdf12 Mar 2026
Withdrawal Update Form 3File: CA CERT 24-25 1.pdf12 Mar 2026
Withdrawal Update Form 3File: CA CERT 25-26 2.pdf12 Mar 2026
Withdrawal Update Form 3File: CA CERT 25-26 3.pdf12 Mar 2026
Form 1File: Architect Certificate.pdf23 Feb 2026
Form 2File: Engineer Certficate.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold 31-03-2020.pdf23 Feb 2026
Form 3File: cacert.pdf23 Feb 2026
Form 1File: Architect Certificate.pdf23 Feb 2026
Form 2File: Engineer Certficate.pdf23 Feb 2026
Form 3File: cacert.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold 31-03-2020.pdf23 Feb 2026
Form 1File: Architect Certificate.pdf23 Feb 2026
Form 2File: Engineer Certficate.pdf23 Feb 2026
Form 3File: cacert.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold 31-03-2020.pdf23 Feb 2026
Form 1File: Architect Certificate.pdf23 Feb 2026
Form 2File: Engineer Certficate.pdf23 Feb 2026
Form 3File: cacert.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold 31-03-2020.pdf23 Feb 2026

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 85 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHAKTI AANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VADGAON MAVAL13,700+ in Pune

Builder: NIRMITI DEVELOPERS

NIRMITI DEVELOPERS has 6 registrations on MahaRERA, including NIRMITI ARMAAN and Nirmiti Apartments. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if BHAKTI AANGAN is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHAKTI AANGAN?

The registered promoter entity is NIRMITI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHAKTI AANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHAKTI AANGAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHAKTI AANGAN?

The professionals named in the filing: Architect: M J ASSOCIATES; Engineer: RAVINDRA A KARNAVAT AND ASSOCIATES; Engineer: Sachin G Sonawane; Chartered Accountant: M S KUMBHAR AND ASSOCIATES; Chartered Accountant: N. L. Bhakare and Associates; Chartered Accountant: Ranjeetkaur Harvindersingh Pothiwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAKTI AANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAKTI AANGAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAKTI AANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.