Bhagyasthan Phase1

By Tulip Inn Construwell Pvt. Ltd.

RG-MH-08855 · RERA P52100000316 · Last updated on MahaRERA portal: 7 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 49 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
29 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

Bhagyasthan Phase1 is a Others project by Tulip Inn Construwell Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100000316 on 15 Jul 2017. Possession was promised by 8 Jul 2024 and is now 27 months past that date. The completion date has moved by 49 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBhagyasthan Phase1
  • TypeOthers
  • Location
    • Mawal
    • Talegaon Dabhade
    • Talegaon Dabhade (M Cl)
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000316
  • ReraGenie IDRG-MH-08855

Builder

  • NameTulip Inn Construwell Pvt. Ltd.
  • Entity typeCompany
  • CINU45200PN2007PTC130087
  • DirectorsBhushan Vilas Palresha, Vishal Naupatlal Palresha

Key dates

27 months past promisethis monthRegisteredJul 2017First promiseJun 2020Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Jul 2017
  • Promised completion8 Jul 2024
  • Revised completionRevised to 8 Jul 2024 (originally 30 Jun 2020)
  • Buildings3 building records
  • Documents filed125 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building BNA80000
BUILDING CNA80000
Building DNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Building B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes90%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed361

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots361
Closed/Covered36
Open Space325
BuildingClosed/CoveredOpen SpaceTotal
Building B12115127
BUILDING C12105117
Building D12105117

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,182 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityTALEGAON DABHADE NAGAR PARISHAD
Permissible FSI9601.01
Proposed, not sanctioned5,739 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANORI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMinal Firake
ArchitectSubha Architects Milind Saraf
EngineerSS Patne Associates
PartnerRole in project
Tulip Inn Construwell Pvt. Ltd.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002291Jun 2020 → Jun 2021

Reason as filed by the promoterProject delayed due to poor response & poor market conditions since one year

EXT52100016917Jun 2020 → Jun 2024

Reason as filed by the promoterWe state that, the above mentioned project has been completed as on today and the promoter has already received Part Occupation Certificate dated. 04.01.2023 and 25.04.2023 covering 274 units out of 284 units in total and the promoter will be applying for occupation certificate for remaining 10 flats, which flats are unsold yet. We further state that, out of 284 units, only 72 units have been sold and the major portion of units is with us only, being unsold. In view of above, we humbly request you to grant us extension for the project till 31.12.2023. Hon'ble Authority has granted extension to

EXT52100025704Jun 2020 → Jul 2024

Reason as filed by the promoterThe promoter Tulip Inn Construwell Private Limited has registered the project ‘BHAGYASTHAN PHASE 1’ with the Maharashtra Real Estate Regulatory Authority vide no. P52100000316. We state that, the promoter prepared a form 4 (Architect Certificate) on completion of project. The project has been completed and full occupancy certificate thereof has been received and the same are uploaded by the promoter on project webpage in MahaRERA website. The project registration was valid upto 30.06.2024, however the occupancy certificate has been received on 04.01.2023, 25.04.2023 and 08.07.2024, hence we hu

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000106461Anagha Anil DeshpandeM/s. Tulip Inn Construwell Pvt .Ltd28/01/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 May 2025

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: BHAGYASTAN_MAHARERA.pdf7 Jul 2025
Other - TechnicalFile: FORM 4 CL BHAGYASTHAN PHASE 1.pdf12 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC B C D Building04122024.pdf6 May 2025
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN 31032025.pdf7 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Bhagyasthan phase 1 31122024.pdf16 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Bhagyasthan phase 1 31122024.pdf16 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Bhagyasthan phase 1 31122024.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN PHASE 1 31122024.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN PH 1 31122024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN PHASE 1 31122024.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN PH 1 31122024.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN PH 1 31122024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN PHASE 1 31122024.pdf14 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN PHASE 1 31122024.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN PHASE 1 31122024.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN PHASE 1 31122024.pdf13 Jan 2025
Declaration in FORM BFile: FORM B BHAGYASTHAN PHASE 1_rotated.pdf21 Dec 2024
Declaration in FORM BFile: FORM B BHAGYASTHAN PHASE 1_rotated.pdf21 Dec 2024
Declaration in FORM BFile: FORM B BHAGYASTHAN PHASE 1_rotated.pdf21 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 CL BHAGYASTHAN PHASE 1.pdf30 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bhagyasthan phase 1 Form 2.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bhagyasthan phase 1 Form 2.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bhagyasthan phase 1 Form 2.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYSTHAN PHASE 1 30092024.pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYSTHAN PHASE 1 30092024.pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYSTHAN PHASE 1 30092024.pdf19 Oct 2024
Certificates of CA (Form 3)File: Bhagyasthanphase 1 Sign Copy_compressed.pdf17 Oct 2024
Certificates of CA (Form 3)File: Bhagyasthanphase 1 Sign Copy_compressed.pdf17 Oct 2024
Certificates of CA (Form 3)File: Bhagyasthanphase 1 Sign Copy_compressed.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN 30092024.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN 30092024.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN 30092024.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Bhagyasthan Phasel 31-03-2024.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Bhagyasthan Phasel 31-03-2024.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Bhagyasthan Phasel 31-03-2024.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN.pdf22 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BHAGYASTHAN.pdf22 Jul 2024
Certificates of CA (Form 3)File: Form 3 BHAGYASTHAN PHASE 1 30062024.pdf22 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Bhagysthan Phase 1 30062024.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: BHAGYASTHAN 30062024.pdf17 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VTP_Cert_PO_392544_1s7UybSign.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A BHAGYASTHAN 31032024.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: INVENTORY BHAGYASTHAN 31032024.pdf6 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN 31032024.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BHAGYASTHAN 31032024.pdf27 Apr 2024
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN 31032024.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BHAGYASTHAN 30062023.pdf5 Feb 2024
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN 31122023.pdf5 Feb 2024
Disclosure of sold/ booked inventoryFile: INVENTORY BHAGYASTHAN 30092023.pdf25 Jan 2024
Disclosure of sold/ booked inventoryFile: INVENTORY BHAGYASTHAN 31122023.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN 31122023.pdf13 Jan 2024
Certificates of CA (Form 3)File: FORM 3 BHAGYASYHAN 30092023.pdf21 Dec 2023
Certificates of CA (Form 3)File: FORM 3 BHAGYASTHAN 30062023.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 BHAGYASTHAN 2022-23.pdf30 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Bhagyasthan 30092023.pdf14 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BHAGYASTHAN 30062023.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: 1 311221.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 2 310322.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 3 300622.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 4 300922.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 5 311222.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 6 310323.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: 7 300623.pdf17 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A BHAGYASTHAN 31032022.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A BHAGYASTHAN 31032023.pdf8 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tulip Inn_Form 1 Copy_March 23.pdf25 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Tulip Inn_Form 2 Copy_March 23.pdf25 Jul 2023
Certificates of CA (Form 3)File: Form 3 Bhagyasthan Ph 1 31032023 compressed.pdf25 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf23 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bhagyasthan OC 25042023.pdf19 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART_OC_VTP Bhagysthan.pdf28 Mar 2023
Certificates of CA (Form 3)File: FORM 3 310321_compressed_compressed-compressed.pdf20 Feb 2023
Certificates of CA (Form 3)File: FORM 3 310322_compressed-compressed.pdf20 Feb 2023
Certificates of CA (Form 3)File: FORM 3 300622_compressed-compressed.pdf20 Feb 2023
Certificates of CA (Form 3)File: FORM 3 310922_compressed_compressed (1).pdf20 Feb 2023
Certificates of CA (Form 3)File: FORM 3 311222 (1).pdf20 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 20192020.pdf20 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 311220 FORM 1.pdf18 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 310321 FORM 1.pdf18 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 300621 FORM 1.pdf18 Feb 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 49 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhagyasthan Phase1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Talegaon Dabhade13,700+ in Pune

2 kmBhagyasthan Phase1Completed 8Lapsed / revoked 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: Tulip Inn Construwell Pvt. Ltd.

Tulip Inn Construwell Pvt. Ltd. has 1 registration on MahaRERA, including Bhagyasthan Phase1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Bhagyasthan Phase1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Bhagyasthan Phase1 is delayed beyond 8 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhagyasthan Phase1?

The registered promoter entity is Tulip Inn Construwell Pvt. Ltd., a company as per the filing. Its CIN U45200PN2007PTC130087 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhagyasthan Phase1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Bhagyasthan Phase1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Bhagyasthan Phase1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhagyasthan Phase1?

The professionals named in the filing: Architect: Minal Firake; Architect: Subha Architects Milind Saraf; Engineer: SS Patne Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhagyasthan Phase1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhagyasthan Phase1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhagyasthan Phase1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.