Home / Browse projects / BAUG E UMAR
BAUG E UMAR
By MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED
RG-MH-73979 · RERA P51900007117 · Last updated on MahaRERA portal: 11 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BAUG E UMAR is a Residential / Group Housing project by MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED in 400008, registered with MahaRERA as P51900007117 on 17 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 13 of the 72 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameBAUG E UMAR
- TypeResidential / Group Housing
- Location
- BADLU RANGARI STREET
- 400008
- Pincode400008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900007117
- ReraGenie IDRG-MH-73979
Builder
- NameMAHANAGAR CONSTRUCTIONS PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorMOHD AJAZ MOHD ISHAQUE ANSARI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed96 files
Current status
Figures as on 11 Dec 2024, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BAUG E UMAR | NA | 25 | 21 | 68 | 4 | 72 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 81%.
BAUG E UMAR: 41% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 81% |
| Plinth | 100% |
| Stilt Floor | 65% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ABID RIZVI |
| Architect | Syed Ahmed Mehdi |
| Engineer | HANWARE CONSULTANTS |
| Engineer | Ziaur Rehman Khan |
| Chartered Accountant | Akram Khan |
| Chartered Accountant | Esha Bhanushali |
| Partner | Role in project |
|---|---|
| MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project was started in 2017 after obtaining RERA registration dated 17/08/2017 and it was expected to complete within the prescribe time period. But due to unforeseen contingencies such as COVID 2019 - which created havoc all over the world and the work was halted for almost more than 18 months. The undersigned Kindly requests your good-self to allow us 12 months extended time period to complete the project. Thanking you
Reason as filed by the promoterDealy on the Ground of Slow sales and Medical Conditions One of the Directors actively involved in project expired and project was on stand still.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600133 | MOHAMMED SAYEED B SHAIKH | MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED | 08/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 30-09-2024.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 30-06-2024.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 31-12-2021.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q4 31-03-2024.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 31-12-2023.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From 2 Q2 30-09-2023.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 30-06-2023.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q4 31-03-2023.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 31-12-2022.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 30-09-2022.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 30-06-2022.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q4 31-03-2022.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 30-09-2021.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q1 30-06-21.pdf | 11 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3-Jul 22 to Sep 22.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 -Apr 22 to Jun 22.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q2 July 24 to Sep 24.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 Apr 24 to Jun 24.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q4 Jan 24 to Mar 24.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q3 Oct 23 to Dec 23.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q2 Jul 23 to Sep 23.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 Apr 23 to Jun 23.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q4 Jan 23 to Mar 23.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 Q3 Oct 22 to Dec 22.pdf | 7 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 6 Dec 2024 |
| Certificates of CA (Form 3)File: Mahanagar FORM 3- 30-06-2021.pdf | 18 May 2023 |
| Certificates of CA (Form 3)File: Mahanagar FORM 3- 30-09-2021.pdf | 18 May 2023 |
| Certificates of CA (Form 3)File: Mahanagar FORM 3- 31-12-2021.pdf | 18 May 2023 |
| Certificates of CA (Form 3)File: Mahanagar FORM 3- 31-03-2022.pdf | 18 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Mahanagar Form 5.pdf | 18 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Mahanagar construction rera form 5.pdf | 11 May 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.PDF | 2 May 2023 |
| Declaration about Commencement CertificateFile: FORMAT D.PDF | 28 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed 2407.pdf | 27 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2020.pdf | 27 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021.pdf | 27 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 27 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 108-07-2018.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 211-10-2018.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 314-01-2019.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 420-04-2019.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 116-07-2019.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 214-10-2019.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 319-04-2020.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 112-07-2020.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 214-10-2020.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 308-01-2021.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 413-04-2021.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 112-10-2017.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 208-01-2018.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 312-04-2018.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 113-07-2018.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 216-10-2018.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 318-01-2019.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 405-04-2019.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 115-07-2019.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 218-10-2019.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 302-01-2020.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 417-04-2020.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 119-07-2020.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 213-10-2020.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 308-01-2021.pdf | 31 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 414-04-2021.pdf | 31 Jul 2021 |
| Certificates of CA (Form 3)File: 130-09-2017.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 231-12-2017.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 331-03-2018.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 430-06-2018.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 530-09-2018.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 631-12-2018.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 731-03-2019.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 830-06-2019.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 930-09-2019.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1031-12-2019.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1131-03-2020.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1230-06-2020.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1330-09-2020.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1431-12-2020.pdf | 30 Jul 2021 |
| Certificates of CA (Form 3)File: 1531-03-2021.pdf | 30 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 16Form531-03-2018.pdf | 30 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 17Form531-03-2019.pdf | 30 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep BAUG E UMAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near this project
Filed coordinates, straight-line distance. 59 registered projects within 2 km.
FATIMA HEIGHTS
M K ENTERPRISES
Nexsa Sky Vista
D.K. REALTORS & DEVELOPERS LIMITED
Lakadawala Garden
M/s. Lakadawala Developers Pvt. Ltd.
La Mer Residences
EXCELLENT REALTOR DEVELOPERS
Godrej Avenue Eleven - Tower A
GODREJ RESIDENCY PRIVATE LIMITED
FUEGO
HILTON INFRASTRUCTURE
Builder: MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED
MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED has 1 registration on MahaRERA, including BAUG E UMAR. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if BAUG E UMAR is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BAUG E UMAR?
The registered promoter entity is MAHANAGAR CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BAUG E UMAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against BAUG E UMAR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for BAUG E UMAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BAUG E UMAR?
The professionals named in the filing: Architect: ABID RIZVI; Architect: Syed Ahmed Mehdi; Engineer: HANWARE CONSULTANTS; Engineer: Ziaur Rehman Khan; Chartered Accountant: Akram Khan; Chartered Accountant: Esha Bhanushali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BAUG E UMAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback