Home / Browse projects / Udupi, Karnataka / Balakrishna Towers
Balakrishna Towers
RG-KA-18678 · RERA PRM/KA/RERA/1273/318/PR/190809/002765 · Last updated on RERA Karnataka portal: Not stated
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Balakrishna Towers is a Residential/Group Housing project by Y.S.Balakrishna Rao in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/190809/002765 on 9 Aug 2019. Possession is promised by 30 Sep 2020. The completion date has moved by 6 months from the original filing. 0 of the 14 units on this registration are recorded sold or booked, and 0 of 15 construction stages are filed complete.
At a glance
Project
- NameBalakrishna Towers
- TypeResidential/Group Housing
- Location
- Udupi
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1273/318/PR/190809/002765
- ReraGenie IDRG-KA-18678
Builder
- NameY.S.Balakrishna Rao
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on9 Aug 2019
- Promised completion30 Sep 2020
- Revised completionRevised to 30 Sep 2020 (originally 31 Mar 2020)
- Buildings1 building record
- Documents filed20 files
Current status
Figures as on Not stated, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BALAKRISHNA TOWERS | - | - | - | 14 | 0 | 14 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on Not stated, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 15 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
As on Not stated, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | c shridhar acharya |
| Engineer | Raveendra Acharya |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed20
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/190809/002765 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| combinepdf_Compressed | - |
| 5Approved Building Plan | - |
| single plan | - |
| DRAFT Sale DEED | - |
| 6Kalsanka flat deed | - |
| 7saledeed and rtc | - |
| 5Approved Building Plan | - |
| 8Allotment Letter | - |
| 9Brochure-min | - |
| project specification-compressed | - |
| 2Ec | - |
| Affidavith | - |
| 13khata | - |
| 14CONVERSIOM_compressed (1) | - |
| 5Approved Building Plan | - |
| Form B | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1273_318_PR_190809_002765.xlsx | - |
| Occupancy CertificateFile: IMG_0001.jpg | - |
| Completion certificateFile: IMG_0001.jpg | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep Balakrishna Towers on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
Filed coordinates, straight-line distance. 53 registered projects within 2 km.
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: Y.S.Balakrishna Rao
Y.S.Balakrishna Rao has 1 registration on RERA Karnataka, including Balakrishna Towers. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if Balakrishna Towers is delayed beyond 30 Sep 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Balakrishna Towers?
The registered promoter entity is Y.S.Balakrishna Rao. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Balakrishna Towers?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Balakrishna Towers?
The professionals named in the filing: Architect: c shridhar acharya; Engineer: Raveendra Acharya. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Balakrishna Towers?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback