Home / Browse projects / Thane, Maharashtra / BALAJI SERENITY
BALAJI SERENITY
RG-MH-86980 · RERA PR1330002500556 · Last updated on MahaRERA portal: 27 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BALAJI SERENITY is a Residential / Group Housing project by Arihant Associates in Thane, Maharashtra, registered with MahaRERA as PR1330002500556 on 12 Aug 2025. Possession is promised by 31 Dec 2030. 1 of the 86 units on this registration are recorded sold or booked, and 1 of 10 construction stages are filed complete.
At a glance
Project
- NameBALAJI SERENITY
- TypeResidential / Group Housing
- Location
- Mira Bhayandar
- Mira-Bhayandar (M Corp.)
- Thane
- 401107
- Pincode401107
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1330002500556
- ReraGenie IDRG-MH-86980
Builder
- NameArihant Associates
- Entity typePartnership
- PartnersSUMIT MUTHA, VIREN MUTHA, SURESH KHANDELWAL, RAVI VYAS, PRANIT AGARWAL, NIDHI BOKADIA
- Other registrations3 more →
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on12 Aug 2025
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings1 building record
- Documents filed13 files
Current status
Figures as on 27 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Balaji Serenity A Building | NA | 14 | 11 | 86 | 0 | 86 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 10 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Balaji Serenity A Building: 10% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 100% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | 0% |
Parking filed266
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Bharatkumar Patel | BHAYANDAR | Thane |
| Rajkumar Patel | BHAYANDAR | Thane |
| Bhavesh Patel | BHAYANDAR | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Balaji Serenity A Building | NA | Rs 21.76 cr | Rs 1.95 cr |
| - | NA | Rs 9.33 cr | Rs 83.61 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Bharatkumar Patel |
| Engineer | Neel Dholia |
| Chartered Accountant | Rd lukad and Company |
| Chartered Accountant | JASMITA MODI |
| Chartered Accountant | RAMESH DHONDIRAM LUKAD |
| Partner | Role in project |
|---|---|
| Arihant Associates | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportNot on the file
A lawyer's report on who owns the land and what is registered against it.
- Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jul 2025 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed13
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form1-July-Sep.pdf | 27 Jun 2026 |
| Withdrawal Update Form 1File: Form1 Oct-Dec.pdf | 27 Jun 2026 |
| Withdrawal Update Form 1File: Form1-Jan-March.pdf | 27 Jun 2026 |
| Withdrawal Update Form 2File: Form2-July-Sep.pdf | 27 Jun 2026 |
| Withdrawal Update Form 2File: Form2 -Oct-Dec.pdf | 27 Jun 2026 |
| Withdrawal Update Form 2File: Form2 jan to march.pdf | 27 Jun 2026 |
| Withdrawal Update Form 3File: BALAJI SERENITY jult to sep (1).pdf | 27 Jun 2026 |
| Withdrawal Update Form 3File: BALAJI SERENITY oct to dec (1).pdf | 27 Jun 2026 |
| Withdrawal Update Form 3File: BALAJI SERENITY JAN to MAR (1).pdf | 27 Jun 2026 |
| Declaration and undertaking (Annexure A)File: ANNEXURE A DECLARATION CUM UNDERTAKING SUMIT MUTHA_page-0001.pdf | 22 Jul 2025 |
| Layout approvalFile: layout.pdf | 11 Jul 2025 |
| Building plan approvalFile: Building Plan.pdf | 11 Jul 2025 |
| Building plan approvalFile: 10th floor plan.pdf | 11 Jul 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 13 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BALAJI SERENITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane
Filed coordinates, straight-line distance. 240 registered projects within 2 km.
Codename StarLife
JP Infra Realty Private Limited
Prestige Garden Trails
PRESTIGE ESTATES PROJECTS LIMITED
TIARA HILLS PHASE I BLDG NO 3, 5 AND 2
PNK SPACE DEVELOPMENT PVT LTD
The Palace Tower B
JP Infra Realty Private Limited
Sector 2A - Wings JKL
Eversmile Properties Private Limited
CRESCENT WTC - WESTERN TRADE CENTER - PHASE -
CRESCENT SHELTERS
See every Thane project, with the district possession charts
Builder: Arihant Associates
ARIHANT ASSOCIATES has 4 registrations on MahaRERA, including ANAND TOWER and SamarthNagar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if BALAJI SERENITY is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BALAJI SERENITY?
The registered promoter entity is Arihant Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BALAJI SERENITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BALAJI SERENITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BALAJI SERENITY?
The professionals named in the filing: Architect: Bharatkumar Patel; Engineer: Neel Dholia; Chartered Accountant: Rd lukad and Company; Chartered Accountant: JASMITA MODI; Chartered Accountant: RAMESH DHONDIRAM LUKAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BALAJI SERENITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback