Balaji Heights
RG-MH-72477 · RERA P51700048885 · Last updated on MahaRERA portal: 20 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Balaji Heights is a Residential / Group Housing project by Faisal Constructions in Thane, Maharashtra, registered with MahaRERA as P51700048885 on 24 Jan 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 6 months from the original filing. 35 of the 71 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameBalaji Heights
- TypeResidential / Group Housing
- Location
- Ambernath (W)
- Ambernath
- Khuntavali
- Ambarnath
- Thane
- 421501
- Pincode421501
- RERA no.P51700048885
- ReraGenie IDRG-MH-72477
Builder
- NameFaisal Constructions
- Entity typePartnership
- PartnersChandrika Shashi Nair, Sajeeda Jameel Shaikh, Faisal Jameel Shaikh, Sayed Masood Ali, Nisha Nitin Nair, Divya Sunil Nair, Iqbal Javed Shaikh
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Jan 2023
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed103 files
Current status
Figures as on 20 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Balaji Heights | NA | 7 | 7 | 60 | 11 | 71 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
Balaji Heights: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Balaji Waghu Jamdare and Others | Khuntavali | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | U R & Associates |
| Engineer | Atul Kudtarkar |
| Chartered Accountant | Ganesh V Kale |
| Chartered Accountant | Fahad Khan & Associates |
| Partner | Role in project |
|---|---|
| Faisal Constructions | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWhile registering we had declared the date of completion of this project as 30/06/2025. We wish to inform you that due to unavailability of PWD NOC for Lift, we are not able to apply for Occupation Certificate and it may take us 45 to 60 days for obtaining the PWD NOC and for Occupation Certificate from Ambernath Municipal Council. Therefore, we humbly request your goodself to allow us to extend the date of completion of the said Project by 6 months and permit us to revise the completion date from the current 30/06/2025 to 31/12/2025. We submit here that we shall take all steps necessary to co
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Dec 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Dec 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.pdf | 20 Jan 2026 |
| Form 2File: Form 2.pdf | 20 Jan 2026 |
| Form 3File: Form 3.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory Bhq2.pdf | 20 Jan 2026 |
| Form 1File: Form 1.pdf | 20 Jan 2026 |
| Form 2File: Form 2.pdf | 20 Jan 2026 |
| Form 3File: Form 3.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory.pdf | 20 Jan 2026 |
| Form 2A (FY 2022-2023)File: FORM 2A.pdf | 8 Aug 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A.pdf | 8 Aug 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A.pdf | 8 Aug 2025 |
| Form 5 (FY 2022-2023)File: FORM 5.pdf | 5 Aug 2025 |
| Form 5 (FY 2023-2024)File: FORM 5.pdf | 5 Aug 2025 |
| Form 1File: FORM 1.pdf | 20 Jul 2025 |
| Form 2File: FORM 2.pdf | 20 Jul 2025 |
| Form 3File: FORM 3.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Unsold-Booked Inventory.pdf | 20 Jul 2025 |
| Form 1File: Form 1 Quarter 4 Mar-25.pdf | 30 Jun 2025 |
| Form 2File: Form 2 Quarter 4 Mar-25.pdf | 30 Jun 2025 |
| Form 3File: Form 3 Quarter 4 Mar-25.pdf | 30 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Booked Inventory.pdf | 30 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 15 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 15 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf | 7 Dec 2024 |
| Other - TechnicalFile: Declaration Cum Undertaking.pdf | 7 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate Organization.pdf | 7 Dec 2024 |
| Other - LegalFile: 1 Other Legal.pdf | 4 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 24 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 19 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 19 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 19 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 21 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 21 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 21 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 24 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 23 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 21 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 18 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 2 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 25 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 25 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 25 Oct 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: FORM 3.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 23 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 23 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 1 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 26 Jul 2023 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 17 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Balaji Heights on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambernath7,600+ in Thane
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
KRUSHNA VIHAR - PHASE I
KRUSHAN DHAM BUILDERS & DEVELOPERS
VISHWAJEET MYSPACE
GULABRAO BABURAO KARANJULE PATIL
KHATRI SPARSH
KHATRI REALTY
Tulsi Galaxy
Manas Associates
WALEKAR HOMES
WALEKAR & SON'S DEVELOPERS
See every Thane project, with the district possession charts
Builder: Faisal Constructions
Faisal Constructions has 2 registrations on MahaRERA, including Balaji Heights and SKY HERITAGE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Balaji Heights shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Balaji Heights is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Balaji Heights?
The registered promoter entity is Faisal Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Balaji Heights?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Balaji Heights?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Balaji Heights?
The professionals named in the filing: Architect: U R & Associates; Engineer: Atul Kudtarkar; Chartered Accountant: Ganesh V Kale; Chartered Accountant: Fahad Khan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Balaji Heights?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback