BALAJI HEIGHT

By BALAJI BUILDCON

RG-MH-25099 · RERA P51700006069 · Last updated on MahaRERA portal: 29 Dec 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 24 months past the filed date
  • Completion date moved by 47 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Oct 2024Possession promised24 months past this date
22 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 85%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

BALAJI HEIGHT is a Others project by BALAJI BUILDCON in Thane, Maharashtra, registered with MahaRERA as P51700006069 on 14 Aug 2017. Possession was promised by 30 Oct 2024 and is now 24 months past that date. The completion date has moved by 47 months from the original filing.

At a glance

Project

  • NameBALAJI HEIGHT
  • TypeOthers
  • Location
    • KALYAN TITWALA ROAD
    • TITWALA
    • Kalyan
    • Thane
    • 421607
  • Pincode421607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700006069
  • ReraGenie IDRG-MH-25099

Builder

  • NameBALAJI BUILDCON
  • Entity typePartnership
  • PartnersVIRENDRA MANOHAR PANDIT, ASHISH VIDYADHAR MISHRA, ANIL TULSIRAM BHOIR, BALRAJ JAYA SHETTY
  • Other registrations10 more →
  • Completed6 of 11
  • No longer live3 lapsed, de-registered or revoked

Key dates

24 months past promisethis monthRegisteredAug 2017First promiseNov 2020Revised toOct 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion30 Oct 2024
  • Revised completionRevised to 30 Oct 2024 (originally 1 Nov 2020)
  • Buildings3 building records
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA80000
WING BNA80000
WING CNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 29 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 85%.

WING A69%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
WING B87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
WING C73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
WING A11
WING B11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,400 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3917.0
Proposed, not sanctioned3,917 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKASTURI PLAZA, DOMBIVLI EAST 421201

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHANASHRI R BHOSALE
EngineerARVIND PATEL
Chartered AccountantDHIREN PATEL
Chartered AccountantDINESH POKAR
PartnerRole in project
BALAJI BUILDCON-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010982Nov 2020 → Oct 2022

Reason as filed by the promoterWe at Balaji Buildcon has completed C wing and obtain OC for the same from the authorise authorities (KDMC) as our two wings A/B are currently under completion and we would would like to extend our Rera Project Completion date. As due to the Second lockdown and Extended Monsoon Season, non availability of material and manpower, we were unable to complete the project which is already completed 90% as per Architect Letter issued so kindly grant us a extension of 12 months to complete and hand over the same to our privilege Registered customers signed below with their Name , flat No mentioned aga

EXT51700012859Nov 2020 → Oct 2024

Reason as filed by the promoterDUE TO INCREASE IN FSI PLAN WAS REVISED RESULTING IN INCREASE IN NUMBER OF UNITS FROM 70 TO 95 UNITS

EXT51700008417Nov 2020 → Oct 2021

Reason as filed by the promoterDELAY IN RECEIPT OF TDR AND NON AVAILABILITY OF WORK FORCE DUE TO PENDAMIC (COVID)

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: correction approval-dv.pdf29 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech 311022.pdf14 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 01102022.pdf14 Dec 2022
Certificates of CA (Form 3)File: FORM 3 - 13122022_compressed-1-6.pdf14 Dec 2022
Certificates of CA (Form 3)File: FORM 3 - 13122022_compressed-7-12.pdf14 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 FY 2017-18.pdf14 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 FY 2021-22.pdf14 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A.pdf13 Dec 2022
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf22 Nov 2022
Disclosure of sold/ booked inventoryFile: sold -un sold - A wing.pdf22 Nov 2022
Disclosure of sold/ booked inventoryFile: sold -un sold - B wing.pdf22 Nov 2022
CERSAI detailsFile: CRESAI DECLARATION.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: SALES LIST.pdf4 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 - Balaji Buildcon 31032018.pdf21 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - Balaji Buildcon 31032019.pdf21 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: BB.pdf27 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: BB2.pdf27 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A 31032020_compressed.pdf21 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 31032020_compressed.pdf21 Dec 2021
Declaration about Commencement CertificateFile: form d dec about commencement cert.pdf20 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH 20.pdf20 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH 31032021.pdf20 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHANTI CONSULTAN 31032020_compressed.pdf20 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHANTI CONSULTANT FORM 2 310321_compressed.pdf20 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHANTI CONSULTANT FORM 2 310321_compressed.pdf20 Dec 2021
Disclosure of sold/ booked inventoryFile: sales data 10102021.pdf20 Dec 2021
Details of Restarting of Construction work post lockdownFile: project restated.pdf20 Dec 2021
Certificates of CA (Form 3)File: 1.pdf29 Jul 2017
Building plan approvalFile: IOD LAYOUT.pdf28 Jul 2017
Layout approvalFile: IOD LAYOUT.pdf28 Jul 2017
PAN CardFile: BB Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: 1.pdf28 Jul 2017
Copy of the legal title reportFile: 2.pdf28 Jul 2017
Details of encumbrancesFile: AFFIDAVIT.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD LAYOUT.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD LAYOUT.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 1.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 2.pdf28 Jul 2017
Declaration in FORM BFile: AFFIDAVIT.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: SALE AGREEMENT - BALAJI HEIGHTS -RERA.pdf28 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf28 Jul 2017
OtherFile: 1.pdf28 Jul 2017
OtherFile: 2.pdf28 Jul 2017
OtherFile: 3.pdf28 Jul 2017
OtherFile: 5.pdf28 Jul 2017
OtherFile: 5.pdf28 Jul 2017
OtherFile: 6.pdf28 Jul 2017
OtherFile: 7.pdf28 Jul 2017
OtherFile: 8.pdf28 Jul 2017
OtherFile: 9.pdf28 Jul 2017
OtherFile: 10.pdf28 Jul 2017
OtherFile: 11.pdf28 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 47 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BALAJI HEIGHT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TITWALA7,600+ in Thane

2 kmBALAJI HEIGHTCompleted 84Lapsed / revoked 72Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 257 registered projects within 2 km.

Builder: BALAJI BUILDCON

BALAJI BUILDCON has 11 registrations on MahaRERA, including ROYAL ORCHID and Balaji Mesmero. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that BALAJI HEIGHT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BALAJI HEIGHT is delayed beyond 30 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BALAJI HEIGHT?

The registered promoter entity is BALAJI BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BALAJI HEIGHT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BALAJI HEIGHT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BALAJI HEIGHT?

The professionals named in the filing: Architect: DHANASHRI R BHOSALE; Engineer: ARVIND PATEL; Chartered Accountant: DHIREN PATEL; Chartered Accountant: DINESH POKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BALAJI HEIGHT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BALAJI HEIGHT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BALAJI HEIGHT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.