ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / AYESHA GARDEN B WING

Registration lapsed No litigation declared Others project

AYESHA GARDEN B WING

By AZKA BUILDERS AND DEVELOPERS

RG-MH-80641 · RERA P51700033810 · Last updated on MahaRERA portal: 5 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
5 of 11Construction stages donefurthest along: Installation of Lifts, 85%
17 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

AYESHA GARDEN B WING is a Others project by AZKA BUILDERS AND DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700033810 on 8 Mar 2022. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 9 months from the original filing. 32 of the 49 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameAYESHA GARDEN B WING
  • TypeOthers
  • Location
    • CTS 207 / 212
    • KALYAN
    • Kalyan-Dombivali (M Corp.)
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700033810
  • ReraGenie IDRG-MH-80641

Builder

  • NameAZKA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • GSTIN27ABNFA9680L1ZM
  • PartnersONALI ADAMALI KACHWALA, ZOHEB SHANNAWAZ PANWELKAR, AFFAN ASIM JALAL, ASIM ZAHIR AHMED KHOT, HUMA MOHAMMAD AZAM SHAIKH
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

13 months past promisethis monthRegisteredMar 2022First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Mar 2022
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed99 files

Current status

65%32 of 49 units booked

Figures as on 5 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AYESHA GARDEN B WINGNA121204949

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 85%.

AYESHA GARDEN B WING: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 5 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered14
Open Space6

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,643 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Apr 2026
LandownerVillageDistrict
Johar Hasan ZojwallaKalyan-Dombivali (M Corp.)Thane
Moiz Hasan ZojwallaKalyan-Dombivali (M Corp.)Thane
Gulam M Mainuddin FakihKalyan-Dombivali (M Corp.)Thane

Approvals and building plan

Sanctioning authorityKalyanDombivali (M Corp.)
Permissible FSI4350.0
Proposed, not sanctioned4,350 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOLD SUCHAK NIWAS CTSNO 3203 MURBAD ROAD KALYAN WEST 421301

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATISH KANADE
ArchitectARCHITECTS INC
EngineerPRANAV ENTERPRISES
EngineerPRAGATI ENTERPRISES
Chartered AccountantJHS & ASSOCIATES LLP
Chartered AccountantMithil VinayKhatau & Associates
Chartered AccountantThakkar Prakash and company
Chartered AccountantFahad Khan and Associates
PartnerRole in project
AZKA BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700027864Dec 2024 → Sep 2025

Reason as filed by the promoterAs per the attachment

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Architects Certificate.pdf5 Nov 2025
Form 2File: Form 2 A Azka Final.pdf5 Nov 2025
Form 3File: Form 3 Q2 FY 25-26 Final.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold - standard format B Wing.pdf5 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf5 Nov 2025
Form 1File: Form 1.pdf4 Aug 2025
Form 2File: Form 2-.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold .pdf4 Aug 2025
Form 3File: Form 3 Q1 FY 25-26 Final.pdf4 Aug 2025
OthersFile: Form 2A.pdf4 Aug 2025
Form 1File: Form 1 31-03-2025.pdf2 Jul 2025
Form 2File: form 2 31-03-2025.pdf2 Jul 2025
Form 3File: Form 3 Q4 24-25 Scaned .pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold 31-03-2025 Scaned.pdf2 Jul 2025
Declaration in FORM BFile: Form B b wing extension 2025 30-09.pdf11 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf11 Mar 2025
Disclosure of sold/ booked inventoryFile: B wing - Disclosure -June 24.pdf8 Mar 2025
Disclosure of sold/ booked inventoryFile: B 30-09-24 Sold Unsold.pdf8 Mar 2025
Disclosure of sold/ booked inventoryFile: B 31-12-24 sold unsold.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Quarterly Form 1 30-09-2024.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Quarterly Form 1 31-12-2024.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Comporess B wng Q2.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: compress B wing Q2 .pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Quarterly Form 2 30-09-2024.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Quarterly Form 2 31-12-2024.pdf27 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA Quarterly Form 2A 30-09-2024.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2024-25 Q1_organized_compressed (2).pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3FY202425Q1.pdf29 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2024-25 Q1 FINAL.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3FY202425Q1.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3FY202425Q1.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1ArchF130062022.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2ArchF130-09-2022.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3ArchF131-12-2022.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4Arch F 1 30-06-2023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5Arch F 1 30-09-2023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6Arch F 1 31-12-2023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7Arch F 1 30-06-2024.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1Pragati F 2 30-06-2022.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2Pragati F 2 30-09-2022.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3Pragati F 2 31-12-2022.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4Pragati F 2 30-06-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5Pragati F 2 30-09-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6Pragati F 2 31-12-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7Pragati F 2 30-06-2024.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 B WING A 2023.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2022-23 Q1.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2022-23 Q2.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2022-23 Q3-signed.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2023-24 Q1.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2023-24 Q2.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2023-24 Q3.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AZKA Wing B Form 3 FY 2024-25 Q1.pdf13 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE- 2023.pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate B Wing.pdf5 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate B wing Form 2.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A B wing.pdf5 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 B wing_compressed.pdf5 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 B wing 2023-24.pdf5 Jul 2024
OtherFile: Notarized Declaration B Wing.pdf5 Jul 2024
OtherFile: declaration B wing.pdf5 Jul 2024
Disclosure of sold/ booked inventoryFile: Azka B sold unsold 31-03-2024.pdf11 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Azka B rera bank details.pdf11 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: JHS_Letter_Head_B_Wing-Form_5_Annual_Report_Rera_March_2023_AZKA.pdf2 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: JHS Letter Head_B Wing-Form 5 Annual_Report_Rera_March_2023 AZKA_11zon.pdf23 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Cert - B wing - 31-03-2022.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Cert - B wing - 31-03-2023.pdf3 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert - B wing - 31-03-2023.pdf3 Aug 2023
Disclosure of sold/ booked inventoryFile: Azka Builder - B wing-Sold and unsold-March 2023.pdf3 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Azka Builder - Form 3 B wing-compressed.pdf3 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: B Wing -Axis Bank - Collection Account.pdf3 Aug 2023
OtherFile: Power of Attorney-1-35.pdf21 Feb 2022
OtherFile: Power of Attorney-36-70-compressed.pdf21 Feb 2022
OtherFile: Power of Attorney-71-105-compressed.pdf21 Feb 2022
OtherFile: Power of Attorney-106-122.pdf21 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report_200230304339_For_Asset_Based_Search_16_02_2022_00_24_48_230.pdf18 Feb 2022
Status of ConveyanceFile: Conveyance Deed-1-35-compressed.pdf18 Feb 2022
Status of ConveyanceFile: Conveyance Deed-36-70-compressed.pdf18 Feb 2022
Status of ConveyanceFile: Conveyance Deed-71-105-compressed.pdf18 Feb 2022
Status of ConveyanceFile: Conveyance Deed-106-125.pdf18 Feb 2022

How this compares with Thane

65%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 9 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AYESHA GARDEN B WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

2 kmAYESHA GARDEN B WINGCompleted 51Lapsed / revoked 31Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 160 registered projects within 2 km.

Builder: AZKA BUILDERS AND DEVELOPERS

AZKA BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including AYESHA GARDEN B WING and AYESHA GARDEN A WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that AYESHA GARDEN B WING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AYESHA GARDEN B WING is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AYESHA GARDEN B WING?

The registered promoter entity is AZKA BUILDERS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27ABNFA9680L1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AYESHA GARDEN B WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AYESHA GARDEN B WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AYESHA GARDEN B WING?

The professionals named in the filing: Architect: SATISH KANADE; Architect: ARCHITECTS INC; Engineer: PRANAV ENTERPRISES; Engineer: PRAGATI ENTERPRISES; Chartered Accountant: JHS & ASSOCIATES LLP; Chartered Accountant: Mithil VinayKhatau & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AYESHA GARDEN B WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AYESHA GARDEN B WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AYESHA GARDEN B WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.