Home / Browse projects / Pune, Maharashtra / AYAAN A WING

Registered No litigation declared Residential / Group Housing project

AYAAN A WING

By GANDHI BAFNA ASSOCIATES

RG-MH-14629 · RERA P52100022829 · Last updated on MahaRERA portal: 14 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 53 months
  • 1 extension taken
  • Rs 10.75 crore secured on the land, in favour of Prachay Capital Limited

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 53 months from the original
0 of 11Construction stages donefurthest along: Excavation, 80%
43 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

AYAAN A WING is a Residential / Group Housing project by GANDHI BAFNA ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100022829 on 30 Oct 2019. Possession is promised by 30 Dec 2027. The completion date has moved by 53 months from the original filing. 5 of the 48 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameAYAAN A WING
  • TypeResidential / Group Housing
  • Location
    • Nyati Estate Road
    • Mohamadwadi
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100022829
  • ReraGenie IDRG-MH-14629

Builder

  • NameGANDHI BAFNA ASSOCIATES
  • Entity typePartnership
  • PartnersHARSHA YOGESH BAFNA, REKHA MANOJ GANDHI

Key dates

this monthRegisteredOct 2019First promiseJul 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Oct 2019
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 31 Jul 2023)
  • Buildings1 building record
  • Documents filed76 files

Current status

10%5 of 48 units booked
0.7%Work done, per cost certificate

Figures as on 14 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AYAAN A WINGNA141248048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 80%.

AYAAN A WING: 7% average across the applicable activities

ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed200

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots200
Closed/Covered200

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,854 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPrachay Capital Limited
Secured amountRs 10.75 crore
CERSAI search filedYes
Declared on29 Nov 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI12422.98
Proposed, not sanctioned4,523 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE
Estimated costRs 6.80 cr
Cost incurredRs 5.00 lakh
Work done0.74%
BuildingWingEstimatedIncurred
AYAAN A WINGNARs 6.00 crRs 5.00 lakh
-NARs 80.00 lakh-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshwini B Pol
ArchitectCUBIX Architects Associates
EngineerAKSHAY PANDURANG TUPE
EngineerSANJAY BHAIRAWKAR
Chartered AccountantSCT & Company
Chartered AccountantSHRAMAN SURYAKUMAR PAHADE
Chartered AccountantABHINAV THOLE
PartnerRole in project
GANDHI BAFNA ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024729Jul 2023 → Dec 2027

Reason as filed by the promoterDelayed due to funding issues and miscellaneous disputes

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate 30-09-2025.pdf14 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate 30-09-2025.pdf14 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate 30-09-2025.PDF14 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate 30-06-2025.pdf11 Mar 2026
Withdrawal Update Form 2File: Form 2 Engineer certificate 30-06-2025.pdf11 Mar 2026
Withdrawal Update Form 3File: Form 3 CA Certificate 30-06-2025.PDF11 Mar 2026
Form 1File: Form 1 Architect certificate 31-12-2024.pdf10 Dec 2025
Form 2File: Form 2 engineer certificate 31-12-24.pdf10 Dec 2025
Form 3File: Form 3 CA certificate 31-12-2024.PDF10 Dec 2025
Disclosure of Sold and Booked InventoryFile: Declaration of sold unsold 31-12-2024.pdf10 Dec 2025
Self-declaration of Quarterly ProgressFile: Self declaration 31-12-2024.pdf10 Dec 2025
OthersFile: 4 a Details of encumbrances concerned to Finance 31-12-24.pdf10 Dec 2025
Form 1File: Form 1 Architect Certificate 31-03-2025.pdf10 Dec 2025
Form 2File: Form 2 Engineer certificate 31-03-2025.pdf10 Dec 2025
Form 3File: Form 3 CA Certificate 31-03-2025.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: Declaration of sold unsold 31-03-2025.pdf10 Dec 2025
Self-declaration of Quarterly ProgressFile: Self Declaration 31-03-2025.pdf10 Dec 2025
OthersFile: 4 a Details of encumbrances concerned to Finance 31-03-2025.pdf10 Dec 2025
Form 2A (FY 2024-2025)File: Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).PDF1 Dec 2025
Form 5 (FY 2024-2025)File: Annual Audit Report of CA (Form 5) (FY 2024-25).pdf29 Nov 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf13 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 GBA.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021_compressed.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022_compressed.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-2023_compressed.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf28 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured or Unsecured finance Details.PDF26 Nov 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.PDF21 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1.PDF21 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2.PDF21 Nov 2024
Disclosure of sold/ booked inventoryFile: Promoters Disclosure Q1.PDF21 Nov 2024
Disclosure of sold/ booked inventoryFile: Promoters Disclosure Q2.PDF21 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration of Bank Account.PDF21 Nov 2024
Deviation Report with respect to Allotment letterFile: Deviation report with Allotement Letter.PDF21 Nov 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.PDF21 Nov 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report with Agreement.PDF21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22.PDF21 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest -Real Etate Organization-1.pdf21 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest -Real Etate Organization-2.pdf21 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest -Real Etate Organization-3.pdf21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23.PDF21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 23-24.PDF21 Nov 2024
Details of encumbrances concerned to FinanceFile: No Encumbrances Letter.PDF15 Oct 2024
Declaration in FORM BFile: Form B.PDF15 Oct 2024
CERSAI detailsFile: Letter.PDF15 Oct 2024
Details of encumbrances concerned to LegalFile: No Encumbrances Letter.PDF15 Oct 2024
Proforma of Agreement for saleFile: 2 Proforma of Allotment letter.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1.PDF10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2.PDF10 Oct 2024
Details of encumbrancesFile: Encumbrance Certificate Declaration.PDF5 Jan 2022
Declaration about Commencement CertificateFile: Declaration about commencement certificate.PDF5 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate FY 19-20.PDF5 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate FY 20-21.PDF5 Jan 2022
Disclosure of sold/ booked inventoryFile: Disclosure of soldunsold inventory.PDF5 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 19-20.PDF5 Jan 2022
Layout approvalFile: Layout.pdf17 Oct 2019
Building plan approvalFile: MOHAMADWADI 1-3.pdf17 Oct 2019
Building plan approvalFile: MOHAMADWADI 2-3.pdf17 Oct 2019
Building plan approvalFile: MOHAMADWADI 3-3.pdf17 Oct 2019
PAN CardFile: GBA PAN card.PDF17 Oct 2019
Copy of the legal title reportFile: Search and title report.PDF17 Oct 2019
Copy of the legal title reportFile: Supplimentary search report.PDF17 Oct 2019
Details of encumbrancesFile: No encumburance.PDF17 Oct 2019
Copy of Layout Approval (in case of layout)File: Layout.pdf17 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: MOHAMADWADI 1-3.pdf17 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: MOHAMADWADI 2-3.pdf17 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: MOHAMADWADI 3-3.pdf17 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf17 Oct 2019
Declaration in FORM BFile: New Form B.PDF17 Oct 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf17 Oct 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Eng Cert.PDF17 Oct 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Form 3.pdf17 Oct 2019
Proforma of Allotment letterFile: Ayaan-Allotment Letter draft.pdf17 Oct 2019
Proforma of Allotment letterFile: Flat Agreement - Ayaan mohmadwadi.pdf17 Oct 2019
OtherFile: NA Order.PDF17 Oct 2019
OtherFile: Mohammadwadi satbara.PDF17 Oct 2019

How this compares with Pune

10%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 53 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AYAAN A WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mohamadwadi13,700+ in Pune

2 kmAYAAN A WINGCompleted 82Lapsed / revoked 27Other 76Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: GANDHI BAFNA ASSOCIATES

GANDHI BAFNA ASSOCIATES has 1 registration on MahaRERA, including AYAAN A WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AYAAN A WING is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AYAAN A WING?

The registered promoter entity is GANDHI BAFNA ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AYAAN A WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AYAAN A WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AYAAN A WING?

The professionals named in the filing: Architect: Ashwini B Pol; Architect: CUBIX Architects Associates; Engineer: AKSHAY PANDURANG TUPE; Engineer: SANJAY BHAIRAWKAR; Chartered Accountant: SCT & Company; Chartered Accountant: SHRAMAN SURYAKUMAR PAHADE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AYAAN A WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AYAAN A WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AYAAN A WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.