Home / Browse projects / Pune, Maharashtra / AVONVISTAPROJECT4
AVONVISTAPROJECT4
By NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD
RG-MH-21517 · RERA P52100029724 · Last updated on MahaRERA portal: 23 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AVONVISTAPROJECT4 is a Residential / Group Housing project by NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD in Pune, Maharashtra, registered with MahaRERA as P52100029724 on 26 Jun 2021. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameAVONVISTAPROJECT4
- TypeResidential / Group Housing
- Location
- PUNE
- Mahalunge
- Mulshi
- 410501
- Pincode410501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029724
- ReraGenie IDRG-MH-21517
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Jun 2021
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 31 Dec 2024)
- Buildings2 building records
- Documents filed174 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A3 BUILDING | NA | 24 | 0 | 0 | 0 | 0 |
| B3 BUILDING | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 86%.
A3 BUILDING63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 86% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B3 BUILDING70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 75% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed313
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A3 BUILDING | 146 | 3 | 149 |
| B3 BUILDING | 160 | 4 | 164 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GAURI H NAIKNAVARE |
| Engineer | KRUPALI KADAM |
| Chartered Accountant | KK SS AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir/Madam, We, Naiknavare Profile Constructions Pvt. Ltd., the promoters of Avon Vista Project 4 (RERA No. P52100029724), hereby submit this application for an extension under Section 6 of the Real Estate (Regulation and Development) Act, 2016. The project was registered on 6th May 2021 with an original completion date of 31st December 2024. Due to unavoidable challenges beyond our control, we request an extension to complete the project as per the required standards. Challenges Faced: Impact of COVID-19: Workforce shortages due to labor migration during lockdowns. Delays in procuring and
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504567 | NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD | Samadhan Dattu Nikam | 22/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 4 Apr 2025
Documents filed174
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Avon Vista 4 - A3 B3 Sold Booked Inventory.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avon Project 4.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Avon Pro4.pdf | 11 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion B3,A3.pdf | 4 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Avon Vista Pro4.pdf | 2 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avon Vista Pro4.pdf | 1 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 - Oct to Dec 24.pdf | 18 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: AVON PRO 4 2A.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08 01 25 RERA ARCH CERTIFICATE A3 B3.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: avon vista pro 4.pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVON VISTA PRO 4.pdf | 8 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: avon vista pro 4.pdf | 8 Jan 2025 |
| Declaration in FORM BFile: P52100029724_FileName_1.pdf | 2 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Avon Vista P4 - FY 23-24.pdf | 7 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AVON PRO 4.pdf | 24 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 AVON PRO 4.pdf | 24 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: GetUserDocumentFileContent (12).pdf | 22 Oct 2024 |
| Details of encumbrances concerned to LegalFile: GetUserDocumentFileContent (12).pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avon Vista Pro4.pdf | 15 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: AV pro 4.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: AVON VISTA PROJECT 4.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AVON PRO 4-merged.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVON PRO 4.pdf | 6 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: AVON VISTA PROJECT 4.pdf | 6 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24 06 24 AV FORM 1 A3 B3.pdf | 3 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Avon Vista pro 4 A3 B3.pdf | 3 Jul 2024 |
| OtherFile: Final Judgement copy.pdf | 25 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avon P4.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: avon pro 4.pdf | 5 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Avon Vista pro 4.pdf | 5 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: AVON VISTA PRO 4.pdf | 5 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 02 04 24 RERA ARCH CERTIFICATE A3 B3 25 03 24.pdf | 2 Apr 2024 |
| OtherFile: Avon Vista Project 4 Bldg A3 B3.pdf | 2 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Avon 4 Dec 23.pdf | 11 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Avon Vista A3 B3.pdf | 6 Jan 2024 |
| OtherFile: Avon Vista B3 A3.pdf | 6 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: AVON PRO 4 B3.pdf | 5 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: AVON PRO 4.pdf | 5 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVON PRO 4.pdf | 2 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: avon pro4 form 2.pdf | 2 Jan 2024 |
| OtherFile: AV B3 A3.pdf | 16 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avon -4 FORM 3 Sept 23.pdf | 17 Oct 2023 |
| OtherFile: AVON VISTA PRO 3 AREA STATEMENT131023.pdf | 13 Oct 2023 |
| OtherFile: AVON VISTA PRO 4 AREA STATEMENT B3 131023.pdf | 13 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 3-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 4-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 5-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 6-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 7-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 8-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 9-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 10-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 11 -17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 12-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 12-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 13-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 14-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 15-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 16-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 17-17 11 10 23.pdf | 12 Oct 2023 |
| Layout approvalFile: AVON PRO 4 LAYOUT 1-17 11 10 23.pdf | 12 Oct 2023 |
| Building plan approvalFile: AVON PRO 4 2-17 11 10 23.pdf | 12 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: AVON PRO 4 LAYOUT 1-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 2-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 3-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 4-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 5-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 6-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 7-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 8-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 9-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 10-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 11 -17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 12-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 12-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 13-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 14-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 15-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 16-17 11 10 23.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: AVON PRO 4 17-17 11 10 23.pdf | 12 Oct 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| AVON VISTA PROJECT 2P52100017914 | PUNE, Pune | Sep 2018 | Completed | Jun 2022 | Jan 1970 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 174 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep AVONVISTAPROJECT4 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 267 registered projects within 2 km.
DWARKA PROJECT3
NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD
SARA NILAAY
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C3
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C2
JAGRUTSARA STRUCTURES LLP
SARA SWAPNODAY
Jagrutsara Structures LLP
Aapla Ghar Moshi Annex Phase I
Maple Shelters Pvt. Ltd.
Builder: NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD
NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD has 2 registrations on MahaRERA, including AVON VISTA PROJECT 2 and AVONVISTAPROJECT4. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that AVONVISTAPROJECT4 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if AVONVISTAPROJECT4 is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AVONVISTAPROJECT4?
The registered promoter entity is NAIKNAVAREPROFILECONSTRUCTIONSPVTLTD, a company as per the filing. Its CIN U45309PN2017PTC173686 and GSTIN 27AAFCN8704N1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AVONVISTAPROJECT4?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AVONVISTAPROJECT4?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AVONVISTAPROJECT4?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AVONVISTAPROJECT4?
The professionals named in the filing: Architect: GAURI H NAIKNAVARE; Engineer: KRUPALI KADAM; Chartered Accountant: KK SS AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVONVISTAPROJECT4?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback