Home / Browse projects / Pune, Maharashtra / DWARKA PROJECT3

Registration lapsed No litigation declared Residential / Group Housing project

DWARKA PROJECT3

By NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD

RG-MH-08118 · RERA P52100000163 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 8 complaints at MahaRERA
  • Completion date moved by 78 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
29 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
292 of 480Units unsoldnot recorded sold or booked
8Complaints at MahaRERAon this registration
Jump to the 241 documents Report an error

DWARKA PROJECT3 is a Residential / Group Housing project by NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD in Pune, Maharashtra, registered with MahaRERA as P52100000163 on 7 Jul 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 78 months from the original filing. 188 of the 480 units on this registration are recorded sold or booked, and 29 of 55 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NameDWARKA PROJECT3
  • TypeResidential / Group Housing
  • Location
    • CHAKAN
    • Mahalunge
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000163
  • ReraGenie IDRG-MH-08118

Builder

  • NameNAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD
  • Entity typeCompany
  • Managing DirectorHEMANT DATTAJI NAIKNAVARE
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

4 months past promisethis monthRegisteredJul 2017First promiseDec 2019Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Jul 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2019)
  • Buildings5 building records
  • Documents filed241 files

Current status

39%188 of 480 units booked
41.2%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C41NA131396096
C42NA13096096
F1NA1301440144
F2NA1301440144
CLUB HOUSENA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

C4191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C4282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
F20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
CLUB HOUSE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed189

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots189
Closed/Covered109
Open Space80
BuildingClosed/CoveredOpen SpaceTotal
C41144054
C42144054
F140040
F241041

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,960 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI19100.0
Proposed, not sanctioned17,099 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE 4
Estimated costRs 44.71 cr
Cost incurredRs 18.43 cr
Work done41.23%
BuildingWingEstimatedIncurred
-NARs 9.70 crRs 2.42 cr
F1NARs 9.17 cr-
F2NARs 9.17 cr-
C42NARs 8.10 crRs 8.10 cr
C41NARs 7.91 crRs 7.91 cr
CLUB HOUSENARs 66.00 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGAURI NAIKNAVARE
EngineerKRUPALI KADAM
EngineerPramod Ghume
EngineerRavindra Ukhade
Chartered AccountantAkshay Shrishrimal
Chartered AccountantKKSS AND ASSOCIATES
PartnerRole in project
NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013412Dec 2019 → Dec 2024

Reason as filed by the promoterTo MahaRERA MUMBAI Subject : Application for the extension of “Dwarka” Project - 3 with reason P52100000163 in RERA. Dear Sir, We have registered our “Dwarka” Project -3 P52100000163 under RERA. The completion date for the said project was 30th Dec 2022. We have already applied for RERA Extension on date 29th Dec 2022. We submits that the said project consist of Bldg. C41:- Completed & Occupancy Certificate received, Bldg .C42 & Development:- Under Construction Phase , Bldg F1 & F2 :- Buildings Cancelled & No booking taken. We state that, in Building C41 consist of 96 Flats and sold out and po

EXT52100010174Dec 2019 → Jun 2022

Reason as filed by the promoterWe have registered our Project DWARKA PROJECT 3 - P52100000163 under RERA. The completion date for the project is 30 TH JUNE 2021. But considering the COVID-19 situation, we are unable to complete our Project due to various reasons mentioned as under. As you are aware, due to lockdown announced by the Government of Maharashtra, the labours moved from site to their native places. Mostly the labours are from other States like UP, Bihar Orissa, Assam, Rajasthan etc. The labour strength on site reduced drastically. At the same time there is shortage of material. As some factories production reduce

EXT52100005322Dec 2019 → Dec 2020

Reason as filed by the promoter1. It is experienced by the Promoter that there are number of challenges such as availing finance, slowdown in market in implementing and completing the Real Estate Projects. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. We have been trying our level best to complete our projects on time. 2. The Promoter had availed project finance from Diwan Housing Finance Corporation Ltd (DHFL). However, the Promoter could not avail finance facility in smooth manner from the said DHFL. Subsequently, DHFL

EXT52100025554Dec 2019 → Dec 2025

Reason as filed by the promoterDear Sir/Madam, We, Naiknavare Housing Development Pvt. Ltd., respectfully submit this application for an extension of our project, Dwarka Project 3 (MahaRERA Registration No. P52100000163), under the provisions of the Real Estate (Regulation and Development) Act, 2016. The Dwarka Project 3 comprises four buildings: C41, C42, F1, F2 & Club House. Out of these, Building C41 has been successfully completed and handed over to the allottees. The Occupancy Certificate (OC) for Building C41 has already been uploaded to the MahaRERA portal. Building C42 is currently under construction and has achieve

EA26032620385Dec 2019 → Jun 2026

Reason as filed by the promoterRespected Sir/Madam, We, Naiknavare Housing Development Pvt. Ltd., being the Promoter of the project “Dwarka Project 3” bearing MahaRERA Registration No. P52100000163, respectfully submit that at the time of project registration, the Promoter had proposed development of multiple buildings namely Building C41, C42, F1, F2 and Clubhouse, which were included in the RERA registration; however, post the COVID-19 pandemic, due to unfavorable market conditions and project feasibility considerations, the Promoter decided to drop the development of Buildings F1 and F2, and accordingly the said building

Litigation declared3

CaseCourtStatus
137/2013DISTRICT COURT PUNEPENDING FOR ORDER
R DARKHAST NO 611/2012CJJD PUNEPENDING FOR ORDER
3165/2016HIGH COURT BOMBAYPRE ADMISSION

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC005000000000344Suvarna Sanjay Gitya and Shantanu Sanjay GityayNaiknavare Developers Pvt Ltd and other directors28/09/2017
CC005000000023396SUNIL S DHOTRENAIKNAVARE HOUSING DEVELOPMENT PVT.LTD.06/09/2019
CC005000000054195Chinmay KoradNaiknavare Housing Developments Pvt Lts17/07/2020
CC005000000054198Meghna Aashiesh AdvallNaiknavare Housing Development Private Limited16/07/2020
CC005000000054197Archit Padmanabh MandaNaiknavare Housing Development Private Limited19/04/2020
CC005000000096148NEHA ATISHNAIKNAVARE HOUSING DEVELOPMENT PVT LTD18/10/2021
CC005000000117058Sudhir Vasant PatilNaiknavare Housing Development Pvt. Ltd.07/05/2022
CC005000000279832Samruddhee Jeevan JoshiNaiknavare Housing Developments Pct. Ltd.21/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Oct 2022

Documents filed241

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 241 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Dwarka 3 form 1.pdf17 Jul 2026
Withdrawal Update Form 2File: Dwarka 3 form 2.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 3 Dwarka P 3 June 26_11zon.pdf17 Jul 2026
Withdrawal Update Form 1File: DWR frm 1.pdf20 May 2026
Withdrawal Update Form 2File: DWR frm 2.pdf20 May 2026
Withdrawal Update Form 3File: Dwarka 3 FORM 3.pdf20 May 2026
Form 2A (FY 2017-2018)File: Form 2A Dwarka pro 3 (9).pdf9 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Dwarka pro 3 (1).pdf9 Apr 2026
Form 2A (FY 2019-2020)File: Form 2A Dwarka pro 3 (7).pdf9 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A Dwarka pro 3 (2).pdf9 Apr 2026
Form 2A (FY 2023-2024)File: Form 2A Dwarka pro 3 (3).pdf9 Apr 2026
Form 2A (FY 2022-2023)File: Form 2A Dwarka pro 3 (4).pdf9 Apr 2026
Form 2A (FY 2021-2022)File: Form 2A Dwarka pro 3 (5).pdf9 Apr 2026
Form 2A (FY 2020-2021)File: Form 2A Dwarka pro 3 (6).pdf9 Apr 2026
Form 2A (FY 2018-2019)File: Form 2A Dwarka pro 3 (8).pdf9 Apr 2026
Form 5 (FY 2018-2019)File: FORM 5 18-19.pdf26 Mar 2026
Form 5 (FY 2019-2020)File: FORM 5 19-20.pdf26 Mar 2026
Form 5 (FY 2020-2021)File: FORM 5 2021.pdf26 Mar 2026
Form 5 (FY 2022-2023)File: FORM 5 22-23.pdf26 Mar 2026
Form 5 (FY 2023-2024)File: 23-24.pdf26 Mar 2026
Withdrawal Update Form 1File: DWARKAPRO3 FORM 1.pdf20 Jan 2026
Withdrawal Update Form 2File: DWARKA PRO 3 FORM 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Dwarka 3 FORM 3.pdf20 Jan 2026
Form 1File: Dwarka Pro3 - Uploaded.pdf10 Dec 2025
Form 2File: Dwarka Pro3 - Uploaded.pdf10 Dec 2025
Form 3File: Dwaraka 3 - Uploaded.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: Dwarka Project 3 - Sold_Booked Inventory_compressed.pdf10 Dec 2025
Form 1File: Dwarka Pro3 - Uploaded.pdf10 Dec 2025
Form 2File: Dwarka Pro3.pdf10 Dec 2025
Form 3File: DWARKA PRO 3 FORM 3 SEPT 24.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SEPT 24.pdf10 Dec 2025
Form 1File: FORM 1 DEC 24.pdf10 Dec 2025
Form 2File: FORM 2 DEC 24.pdf10 Dec 2025
Form 3File: DWARKA PRO 3 FORM 3 DEC 24.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DEC 24.pdf10 Dec 2025
Form 1File: FORM 1 JUN 24.pdf10 Dec 2025
Form 2File: FORM 2 JUNE 24.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD JUNE 24.pdf10 Dec 2025
Form 3File: DWARKA PRO 3 FORM 3 JUN 24.pdf10 Dec 2025
Form 1File: FORM 1 MAR 24.pdf10 Dec 2025
Form 2File: FORM 2 MAR 24.pdf10 Dec 2025
Form 3File: DWARKA PRO 3 FORM 3 MAR 24.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD MAR 24.pdf10 Dec 2025
Form 1File: form 1 dec 23.pdf10 Dec 2025
Form 2File: FORM 2 DEC 23.pdf10 Dec 2025
Form 3File: FORM 3 DEC 23.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DEC 23.pdf10 Dec 2025
Form 1File: FORM 1 OCT 23.pdf10 Dec 2025
Form 2File: FORM 2 OCRT 23.pdf10 Dec 2025
Form 3File: FORM 3 OCT 23.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD OCT 23 (2).pdf10 Dec 2025
Withdrawal Update Form 1File: DWARKA PRO 3 FORM 1.pdf10 Dec 2025
Withdrawal Update Form 2File: DWARKA PRO 3 FORM 2.pdf10 Dec 2025
Withdrawal Update Form 3File: DWARKA PROJECT 3 FORM 3.pdf10 Dec 2025
Form 5 (FY 2024-2025)File: Certificate_Dwarka 3.pdf10 Dec 2025
Form 1File: DWARKA PRO 3 FORM 1.pdf18 Oct 2025
Form 2File: DWARKA PRO 3 FORM 2.pdf18 Oct 2025
Form 3File: DWARKA PROJECT 3 FORM 3.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: DWARKA PRO 3 SOLD UNSOLD_compressed.pdf18 Oct 2025
Form 1File: DWARKA PRO 3 FORM 1.pdf19 Jul 2025
Form 2File: DWARKA PRO 3 FORM 2.pdf19 Jul 2025
Form 3File: Dwaraka 3 Form 3.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Dwarka pro 3 sold unsold.pdf19 Jul 2025
Self-declaration of Quarterly ProgressFile: DWARKA PRO 3 SELF DECLARATION.pdf19 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dwarka Pro3.pdf18 Apr 2025
Certificates of CA (Form 3)File: Dwaraka 3.pdf18 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Dwarka Pro3.pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dwarka Pro3.pdf9 Apr 2025
Certificates of CA (Form 3)File: Form3-Corrected 480 flats Dwarka-3.pdf10 Mar 2025
Certificates of CA (Form 3)File: DWARKA PRO3 FINAL FORM3 WITH F1 AND F2.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: DWARKA PRO SALES SOLD UNSOLD DATA 2025.pdf4 Mar 2025
Certificates of CA (Form 3)File: DWARKA PROJECT-3 RERA FORM 3 (FINAL).PDF13 Feb 2025
Certificates of CA (Form 3)File: DWARKA 3 FORM 3.pdf7 Feb 2025
Certificates of CA (Form 5)File: form5 project3.pdf6 Feb 2025
Certificates of CA (Form 5)File: form5 project3_merged-pages-deleted.pdf6 Feb 2025
Disclosure of sold/ booked inventoryFile: sold unsold dwark pro 3 dec 2024 (1).pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5 project3.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5 project3_merged-pages-deleted.pdf6 Feb 2025
Layout approvalFile: BLDG C 43 Sanction Plan No 16_11zon.pdf4 Feb 2025
Layout approvalFile: Sanction Lay Out Plan no 1_11zon.pdf4 Feb 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
DWARKA SEC 1BVILLAGE MHALUNGE TAL KHED DIST PUNE384CompletedMar 2015Late, Oct 2015
DWARKA D3 D4VILLAGE MHALUNGE TAL KHED DIST PUNE64CompletedMar 2015Late, Sep 2015

How this compares with Pune

39%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 78 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DWARKA PROJECT3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHAKAN13,700+ in Pune

2 kmDWARKA PROJECT3Completed 6Lapsed / revoked 4Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD

NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD has 3 registrations on MahaRERA, including DWARKA PROJECT 1 and DWARKA PROJECT2. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DWARKA PROJECT3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DWARKA PROJECT3 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DWARKA PROJECT3?

The registered promoter entity is NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DWARKA PROJECT3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DWARKA PROJECT3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DWARKA PROJECT3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DWARKA PROJECT3?

The professionals named in the filing: Architect: GAURI NAIKNAVARE; Engineer: KRUPALI KADAM; Engineer: Pramod Ghume; Engineer: Ravindra Ukhade; Chartered Accountant: Akshay Shrishrimal; Chartered Accountant: KKSS AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DWARKA PROJECT3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DWARKA PROJECT3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DWARKA PROJECT3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.