ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Avishkar Ridhima

Registered No litigation declared Others project

Avishkar Ridhima

By ARUN BABAN MARATHE

RG-MH-83937 · RERA P52100052836 · Last updated on MahaRERA portal: 12 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
124 of 124Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

Avishkar Ridhima is a Others project by ARUN BABAN MARATHE in Pune, Maharashtra, registered with MahaRERA as P52100052836 on 5 Oct 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 0 of the 124 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameAvishkar Ridhima
  • TypeOthers
  • Location
    • Maan
    • Man
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052836
  • ReraGenie IDRG-MH-83937

Builder

  • NameARUN BABAN MARATHE
  • Entity typeIndividual
  • GSTIN27AMWPM7631H1ZF
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2023First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Oct 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed79 files

Current status

0%0 of 124 units booked
46.8%Work done, per cost certificate

Figures as on 12 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CommercialNA1108484
ResidentialNA6640040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Commercial27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Residential27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,196 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Apr 2026
LandownerVillageDistrict
Mrs Vandana Baburao ShindeUmarga (M Cl)Osmanabad
Mr Baburao Bhanudas ShindeUmarga (M Cl)Osmanabad
Mr Bhaskar Raghunath GiteLohsarAhmednagar
Mr Madhur Dhananjay DabhadeDakhanePune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI4861.18
Proposed, not sanctioned4,861 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKothrud Pune
Estimated costRs 11.75 cr
Cost incurredRs 5.50 cr
Work done46.84%
BuildingWingEstimatedIncurred
CommercialNARs 11.75 crRs 5.50 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Shivanand Swami
EngineerMr Ganesh Tonde
EngineerRutuja Jagdale
Chartered AccountantCA Santosh Ghare and Associates Ghare
Chartered AccountantV R Khandelwal & Co
PartnerRole in project
ARUN BABAN MARATHE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100023039Dec 2026 → Dec 2027

Reason as filed by the promoterDue to Revise plan sanction

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Avishkar Ridhima (2).pdf12 May 2026
Withdrawal Update Form 1File: Avishkar Ridhima (1).pdf12 May 2026
Withdrawal Update Form 2File: Form 2 Dec 25 Ridhima.pdf12 May 2026
Withdrawal Update Form 2File: Form 2 Dec 25 Ridhima.pdf12 May 2026
Withdrawal Update Form 3File: Form 3 Ridhima September 25.pdf12 May 2026
Withdrawal Update Form 3File: Form 3 Riddhima Dec-25.pdf12 May 2026
Form 1File: Form-1 Riddhima (1).pdf22 Sep 2025
Form 2File: Form 2-Ridhima.pdf22 Sep 2025
Form 3File: Form 3 Ridhima CA certified March 25 (1).pdf22 Sep 2025
Disclosure of Sold and Booked InventoryFile: AVISHKAR RIDHIMA UNSOL SHOP FLAT LIST (1).pdf22 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Ridhima.pdf7 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- ridhima.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: AVISHKAR RIDHIMA UNSOL SHOP FLAT LIST.pdf7 Apr 2025
Declaration in FORM BFile: Form B-Ridhima.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 03-Jan-2025 6-26 pm (1) (1)_compressed.pdf28 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-23 24.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RIDDHIMA 1 ARCHITECH CERTIFICARE (1).pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ridhima form 3 (1) (2).pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Ridhima.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: AVISHKAR RIDHIMA UNSOL SHOP FLAT LIST.pdf21 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-Ridhima.pdf21 Oct 2024
Declaration in FORM BFile: RIDHIMA RERA AFFIDEVIT (1).pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RIDHIMA ARCH CERTIFICATE SEPT 2023.pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RIDHIMA ARCH CERTIFICATE SEPT 2023 (1).pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RIDHIMA ARCH CERTIFICATE DECE 2023 (1).pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-Oct 2023.pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-Dec 2023.pdf9 Aug 2024
Disclosure of sold/ booked inventoryFile: AVISHKAR RIDHIMA UNSOL SHOP FLAT LIST.pdf9 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A FORM 3 SEPTEMBER 2023.pdf9 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A FORM 3 DEC -2023 (1).pdf9 Aug 2024
Copy of the legal title reportFile: Maan 156 Ridhima 2024 search_0001_compressed-1-15.pdf6 Jun 2024
Copy of the legal title reportFile: Maan 156 Ridhima 2024 search_0001_compressed-16-24.pdf6 Jun 2024
Layout approvalFile: scan0539_.pdf25 May 2024
Building plan approvalFile: scan0540_.pdf25 May 2024
Building plan approvalFile: scan0541_.pdf25 May 2024
Building plan approvalFile: scan0542_.pdf25 May 2024
Building plan approvalFile: scan0543_.pdf25 May 2024
Building plan approvalFile: scan0544_.pdf25 May 2024
Building plan approvalFile: scan0545_.pdf25 May 2024
Building plan approvalFile: scan0546_.pdf25 May 2024
Copy of Layout Approval (in case of layout)File: scan0539_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0540_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0541_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0542_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0543_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0544_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0545_.pdf25 May 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0546_.pdf25 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC (1).PDF25 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RIDDHIMA 1 ARCHITECH CERTIFICARE (1).pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ridhima engineering certificate.pdf24 Apr 2024
Disclosure of sold/ booked inventoryFile: AVISHKAR RIDHIMA UNSOL SHOP FLAT LIST.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ridhima form 3 (1).pdf24 Apr 2024
Layout approvalFile: 01_compressed.pdf12 Jul 2023
Building plan approvalFile: 02_compressed.pdf12 Jul 2023
Building plan approvalFile: 03_compressed.pdf12 Jul 2023
Building plan approvalFile: 04_compressed.pdf12 Jul 2023
Building plan approvalFile: 05_compressed.pdf12 Jul 2023
PAN CardFile: 1 PAN Card (3).pdf12 Jul 2023
Copy of the legal title reportFile: 5 (13) (1)-3-5_merged.pdf12 Jul 2023
Details of encumbrances concerned to FinanceFile: self declarance regarding encomburance.pdf12 Jul 2023
Details of encumbrances concerned to LegalFile: self declarance regarding encomburance.pdf12 Jul 2023
Copy of Layout Approval (in case of layout)File: 01_compressed.pdf12 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 02_compressed.pdf12 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 03_compressed.pdf12 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 04_compressed.pdf12 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: 05_compressed.pdf12 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: CC Maan 156_compressed.pdf12 Jul 2023
Declaration about Commencement CertificateFile: declaration about CC formate D (1).pdf12 Jul 2023
Declaration in FORM BFile: Form B - Promoter.pdf12 Jul 2023
CERSAI detailsFile: declaration regarding cersai.pdf12 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3) (11) (1).pdf12 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloure of Inter.pdf12 Jul 2023
Proforma of Allotment letterFile: Model form of AL- Ridhima.pdf12 Jul 2023
Proforma of Agreement for saleFile: Draft - Rera - Avishkar consultancy and developers-Maan- marathe- Flat -As per RERA Act -A12 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Formate A.pdf12 Jul 2023
Deviation Report with respect to Allotment letterFile: devisition reports allotment letter.pdf12 Jul 2023
Deviation Report with respect to model copy of AgreementFile: divition reports agreements to sell.pdf12 Jul 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Avishkar HortusP52100079971Bhegadewadi, Pune15Apr 2025OngoingMay 2027Not due yet

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Avishkar Ridhima on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Maan13,700+ in Pune

2 kmAvishkar RidhimaCompleted 19Lapsed / revoked 10Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: ARUN BABAN MARATHE

ARUN BABAN MARATHE has 4 registrations on MahaRERA, including Chinchechi Baug and Avishkar Ridhima. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Avishkar Ridhima is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Avishkar Ridhima?

The registered promoter entity is ARUN BABAN MARATHE, an individual as per the filing. Its GSTIN 27AMWPM7631H1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Avishkar Ridhima?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Avishkar Ridhima?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Avishkar Ridhima?

The professionals named in the filing: Architect: Ar Shivanand Swami; Engineer: Mr Ganesh Tonde; Engineer: Rutuja Jagdale; Chartered Accountant: CA Santosh Ghare and Associates Ghare; Chartered Accountant: V R Khandelwal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Avishkar Ridhima?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Avishkar Ridhima. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Avishkar Ridhima to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one