ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / AVIGHNA COMPLEX PHASE I

Registration lapsed Litigation declared Residential / Group Housing project

AVIGHNA COMPLEX PHASE I

By AVIGHNAA INFRA BUILDCON LLP

RG-MH-28877 · RERA P51700027284 · Last updated on MahaRERA portal: 15 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 6 cases
  • 1 complaint at MahaRERA

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
6 of 142Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

AVIGHNA COMPLEX PHASE I is a Residential / Group Housing project by AVIGHNAA INFRA BUILDCON LLP in Thane, Maharashtra, registered with MahaRERA as P51700027284 on 1 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 136 of the 142 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAVIGHNA COMPLEX PHASE I
  • TypeResidential / Group Housing
  • Location
    • MIRA GAON
    • MIRA ROAD EAST
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700027284
  • ReraGenie IDRG-MH-28877

Builder

  • NameAVIGHNAA INFRA BUILDCON LLP
  • Entity typePartnership
  • GSTIN27ABQFA1109D1ZS
  • PartnersPRASHANT VINOD VAGHASIYA, NIRMALA VINOD VAGHASIYA
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredDec 2020PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Dec 2020
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed55 files

Current status

96%136 of 142 units booked
88.6%Work done, per cost certificate

Figures as on 15 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AVIGHNA COMPLEX PHASE INA1401420142

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

AVIGHNA COMPLEX PHASE I: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 15 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,880 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Declared on4 Oct 2024
LandownerVillageDistrict
KUMAR PANDURANG MEREMira-Bhayandar (M Corp.)Thane

Approvals and building plan

Sanctioning authorityMIRA BHAYANDER MUNICIPAL CORPORATION
Permissible FSI20851.0
Proposed, not sanctioned6,134 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM V PLAZA MANVEL PADA ROAD NEAR RAILWAY STATION VIRAR EAST
Estimated costRs 31.27 cr
Cost incurredRs 27.71 cr
Work done88.62%
BuildingWingEstimatedIncurred
AVIGHNA COMPLEX PHASE INARs 26.95 crRs 24.26 cr
-NARs 4.31 crRs 3.45 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGNER HOUSE ENGINEER
ArchitectARCHITECTURAL PLANET
EngineerMIRAV CONSULTANCY
EngineerPAWAN ASSOCIATE
Chartered AccountantB M SHETTY
Chartered AccountantPRADEEP MAHABALA KUNDER
Chartered AccountantR K PANDE AND ASSOCIATES
PartnerRole in project
AVIGHNAA INFRA BUILDCON LLP-

Litigation declared6

CaseCourtStatus
15/2020SUB DIVISIONAL OFFICEROngoing
66/2022MAHARASHTRA REVENUE TRIBUNALOngoing
12754/2016Bombay High CourtOngoing
7616/2017Bombay High CourtOngoing
5626/2023Bombay High CourtOngoing
RTS REVISION NO 2715/PRA. KRA/361/J-4/2015Revenue MInisterOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000397247RAJKUMAR NARAYANDAS GUPTA1. M/s. Vighnaharta Construction Builder and developers. 2. M/s. Avighna Infra LLP.02/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase I Engineer Certificate.pdf15 Jun 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Ph I bank form B.pdf9 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Ph I bank form B.pdf9 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis closure ph 1.pdf7 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Ph 1.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis Ph 1 .pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: PH I Disclosure .pdf7 Oct 2024
Deviation Report with respect to Allotment letterFile: PH II dev allotment .pdf7 Oct 2024
Proforma of Agreement for saleFile: Proforma of afs .pdf7 Oct 2024
Deviation Report with respect to model copy of AgreementFile: PH I dev of afs.pdf7 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Ph 1.pdf7 Oct 2024
Deviation Report with respect to Allotment letterFile: PH II dev allotment .pdf7 Oct 2024
Deviation Report with respect to model copy of AgreementFile: PH I dev of afs.pdf7 Oct 2024
Proforma of Agreement for saleFile: Proforma of afs .pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis closure ph 1.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis Ph 1 .pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: PH I Disclosure .pdf7 Oct 2024
Details of encumbrances concerned to LegalFile: Details of encumbrance concerned to finance.pdf6 Oct 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrance concerned to finance.pdf6 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3 Rera Certificate.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE form 1 .pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf6 Oct 2024
CERSAI detailsFile: CERSAI_Search_Report_ phase 1.pdf6 Oct 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrance concerned to finance.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE form 1 .pdf6 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3 Rera Certificate.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf6 Oct 2024
CERSAI detailsFile: CERSAI_Search_Report_ phase 1.pdf6 Oct 2024
Details of encumbrances concerned to LegalFile: Details of encumbrance concerned to finance.pdf6 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph 1 CA Form 3 (1).pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration Ph 1 (1).pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Disclosure on Form 3 Phase 1.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf2 Mar 2023
Building plan approvalFile: Avighna Approved plan .pdf4 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Avighna Approved plan .pdf4 May 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Feb 2022
Declaration about Commencement CertificateFile: AVIGHNAA.pdf27 Feb 2022
Declaration in FORM BFile: FORM B KUMAR MERE (1).pdf27 Nov 2020
OtherFile: POWER DEVELOPMENT.pdf23 Nov 2020
OtherFile: Development.pdf21 Nov 2020
Layout approvalFile: layout plan.pdf13 Nov 2020
Building plan approvalFile: Building Plan Avighna.pdf13 Nov 2020
Building plan approvalFile: N A Cerificate.pdf13 Nov 2020
PAN CardFile: Avighnaa Pan Card.pdf13 Nov 2020
Copy of the legal title reportFile: Title Certificate.pdf13 Nov 2020
Details of encumbrancesFile: Encumarance Certificate.pdf13 Nov 2020
Copy of Layout Approval (in case of layout)File: layout plan.pdf13 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Avighna.pdf13 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: N A Cerificate.pdf13 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Certificate.pdf13 Nov 2020
Declaration in FORM BFile: Form B (2).pdf13 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Artitect Certificatre 1 (1).pdf13 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf13 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate (6).pdf13 Nov 2020
Proforma of Allotment letterFile: draft agreement.pdf13 Nov 2020

How this compares with Thane

96%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVIGHNA COMPLEX PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIRA ROAD EAST7,600+ in Thane

2 kmAVIGHNA COMPLEX PHASE ICompleted 87Lapsed / revoked 66Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 235 registered projects within 2 km.

Builder: AVIGHNAA INFRA BUILDCON LLP

AVIGHNAA INFRA BUILDCON LLP has 2 registrations on MahaRERA, including AVIGHNA COMPLEX PHASE I and AVIGHNA COMPLEX PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that AVIGHNA COMPLEX PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AVIGHNA COMPLEX PHASE I is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVIGHNA COMPLEX PHASE I?

The registered promoter entity is AVIGHNAA INFRA BUILDCON LLP, a partnership as per the filing. Its GSTIN 27ABQFA1109D1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVIGHNA COMPLEX PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AVIGHNA COMPLEX PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AVIGHNA COMPLEX PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVIGHNA COMPLEX PHASE I?

The professionals named in the filing: Architect: DESIGNER HOUSE ENGINEER; Architect: ARCHITECTURAL PLANET; Engineer: MIRAV CONSULTANCY; Engineer: PAWAN ASSOCIATE; Chartered Accountant: B M SHETTY; Chartered Accountant: PRADEEP MAHABALA KUNDER. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVIGHNA COMPLEX PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVIGHNA COMPLEX PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVIGHNA COMPLEX PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.