Home / Browse projects / Mumbai Suburban, Maharashtra / Aveza Phase 1

Registration lapsed No litigation declared Residential / Group Housing project

Aveza Phase 1

By Tata Housing Development Company Limited

RG-MH-25382 · RERA P51900007527 · Last updated on MahaRERA portal: 15 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
15 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 83%
3Complaints at MahaRERAon this registration
Jump to the 145 documents Report an error

Aveza Phase 1 is a Residential / Group Housing project by Tata Housing Development Company Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900007527 on 17 Aug 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameAveza Phase 1
  • TypeResidential / Group Housing
  • Location
    • Navghar Road
    • Mulund East
    • Opp Navghar Police Station
    • MHADA Colony
    • Mulund East
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007527
  • ReraGenie IDRG-MH-25382

Builder

  • NameTata Housing Development Company Limited
  • Entity typeCompany
  • CINU45300MH1942PLC003573
  • GSTIN27AAACT0191Q1ZY
  • Managing DirectorSanjay Bhupender Dutt
  • ChairpersonBanmali Surendra Kumar Agrawala
  • DirectorsSandhya Shailesh Kudtarkar, Kamlesh Mansukhlal Parekh, Ankur Dalwani, Sudip Mullick
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects25 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed145 files

Current status

27.9%Work done, per cost certificate

Figures as on 15 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA490000
Tower BNA410000
Tower CNA480000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 15 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 83%.

Tower A53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises12%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks27%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower B60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower C53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure44%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks27%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 15 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes4%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Sky BridgeYes0%
Swimming pool at Podium 5 levelYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area35,122 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024
LandownerVillageDistrict
Richa RealtorsMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI77060.5
Proposed, not sanctioned44,822 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNariman Point
Estimated costRs 439.29 cr
Cost incurredRs 122.68 cr
Work done27.93%
BuildingWingEstimatedIncurred
Tower ANARs 142.61 crRs 38.94 cr
Tower CNARs 129.17 crRs 45.05 cr
Tower BNARs 90.57 crRs 35.49 cr
-NARs 76.94 crRs 3.20 cr

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapadia Associates
EngineerGokani Consultants
PartnerRole in project
Tata Housing Development Company Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018436Dec 2023 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B.

Litigation declared2

CaseCourtStatus
2051/2015Bombay High CourtAd interim granted by High Court on Third April Two thousand Seventeen not to take any co coerciv
Thane Compliant ULP No 235 of 2016/2016Industrial Labour CourtKept for appearance of the Parties and Next date is Twenty Six April Two Thousand Eighteen

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000057247Ratul LahiriTATA Housing Development Company Limited13/12/2018
CC006000000057308Shikha SinghTATA Housing Development Company Limited14/12/2018
CC006000000251361Uddhavsingh RajputTata Housing Development Company Ltd.05/06/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed145

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: AVEZA Phase 1_11zon.pdf15 May 2025
Certificates of CA (Form 3)File: Certificate of CA Form 3.pdf20 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf8 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 29 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf8 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf8 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Ph 1 Q3 2 1 2025.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3 CA Certificate Ph 1 Q3 16 1 2025.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer certificate Ph 1 Q3 3 1 2025.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Circular 29 Sept 2024.pdf2 Dec 2024
Declaration in FORM BFile: Form B.pdf28 Nov 2024
Certificates of CA (Form 3)File: Signed Form 3 - Aveza Phase 1 Sept 2024-compressed.pdf28 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of Interest in Other Real Estate Organisation.pdf28 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Form 1 - Aveza Phase I.pdf27 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Form Ph 1 Sept 24.pdf20 Oct 2024
Certificates of CA (Form 3)File: Aveza Form 3 Mulund Phase 1 Sep-24.pdf20 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza PH1 Q2 Sept 24.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- Aveza Phase 1.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240Arc Certificate.pdf19 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Q1_Eng Cert_Phase 1.pdf19 Jul 2024
Certificates of CA (Form 3)File: Form 3_Q1_CA Certificate_Phase 1.pdf19 Jul 2024
Declaration about Commencement CertificateFile: Format D.pdf15 May 2024
Declaration in FORM BFile: Mulund Aveza Affidavit RERA Ph 1 Extension.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Arch certificate.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 8 Form 2A.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23 Tata.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf15 May 2024
CERSAI detailsFile: Cersai report.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: Circular no 29_Sold unsold Inventory_compressed.pdf15 May 2024
Certificates of CA (Form 3)File: Form 3 CA certificate_compressed.pdf15 May 2024
Certificates of CA (Form 5)File: RERA Audit Form 5 2017 - 18.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2 Certificates of CA (Form 5).pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Audit Form 5 2019 - 2020.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Audit Form 5 2020 - 21.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Audit Form 5 2022 - 23.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit Form 5 2021 - 22.pdf15 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A TATA.pdf15 May 2024
Certificates of CA (Form 3)File: Q4_Form 3_Phase 1_CA certificate_Jan to March 2024.pdf18 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ph 1- Mar 24.pdf15 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 eng cert Phase 1- Mar 24.pdf15 Apr 2024
Form 2AFile: form 2A Quality Mar 24 - Phase 1.pdf15 Apr 2024
Certificates of CA (Form 3)File: Q3_CA Certificate_Phase I.pdf16 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_Arch Certificate_Phase I.pdf11 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3_Engg Certificate_Phase I.pdf11 Jan 2024
Certificates of CA (Form 3)File: Q2_CA Certificate_Phase I.pdf23 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q2_Engineer Certificate_Phase I.pdf11 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2_Arch Certificate_Phase I.pdf9 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Phase-1 RERA Certifiacte_1_11zon.pdf30 Sep 2023
Certificates of CA (Form 3)File: 2023_Q1_Form 3_Phase I_CA certificate.pdf17 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2023_Q1_Form 2_Phase I_Eng certificate.pdf10 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023_Q1_Form 1_Phase I_Architect Certificate.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3 - CA certificate - Aveza Phase 1_Mar-23.pdf23 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Arch Certificate - Aveza Phase 1.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Eng Certificate - Aveza Phase 1.pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3 Form 1 arch cert-Ph 1-Dec 22.pdf15 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 Eng Cert Dec 22- Aveza Phase 1.pdf15 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Aveza Quality Certificate Mar 22 - Phase 1.pdf15 Feb 2023
Certificates of CA (Form 5)File: Q3 FORM 3_Aveza_Phase I_ Dec 22.pdf15 Feb 2023
Certificates of CA (Form 3)File: Q2 FORM 3_Aveza_Phase I_ Sept 22.pdf1 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 Form 1 arch cert-Ph 1-Sept 22.pdf20 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sept 22- Aveza Phase 1.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-Aveza Phase I FY 21-22.pdf6 Oct 2022
Certificates of CA (Form 3)File: Q1 FORM 3_Aveza_Phase I_ June 22.pdf6 Sep 2022
Certificates of CA (Form 3)File: Q4 Form 3_Mulund_Phase 1 - Mar-22.pdf19 Aug 2022
Disclosure of sold/ booked inventoryFile: Q1 Aveza Phase 1.pdf19 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220711110553.pdf12 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza ph1 Q3 2021-22.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph1 Q4 2021-22.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza ph1 Q3 2021-22.pdf6 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph1 Q4 2021-22.pdf6 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: THDC RERA Aveza Phase I 2020-21.PDF18 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert Q2 Aveza phase 1.pdf1 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engg Cert Serein Q2 2021-22.pdf1 Nov 2021
Disclosure of sold/ booked inventoryFile: Q2 Aveza Phase 1.pdf29 Oct 2021
Certificates of CA (Form 3)File: Q2 FORM 3_Mulund_Phase I_Sep-21 .pdf29 Oct 2021
Form 2AFile: Aveza Quality Certificate Sept 21 - Phase I.pdf9 Oct 2021
Certificates of CA (Form 3)File: FORM 3_Aveza_Phase I_ Q1 June 21.pdf7 Sep 2021
Certificates of CA (Form 3)File: Q4 Form 3 Aveza Ph1 March 21.pdf1 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza ph1 Q1 2021-22.pdf31 Jul 2021
Disclosure of sold/ booked inventoryFile: Aveza Phase 1.pdf30 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form A Aveza Ph1 Q1 2021-22.pdf16 Jul 2021

Promoter's earlier projects17

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise16 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Amantra PH 1 Tower A A3Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 42130292CompletedDec 2015Late, Mar 2016
Amantra PH 1 Tower L B12Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302197CompletedNov 2015Late, Mar 2016
Amantra PH 1 Tower D A4Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302127CompletedNov 2015Late, Mar 2016
Amantra PH 1 Tower C A5Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302114CompletedNov 2015Late, Mar 2016
Amantra PH 1 Tower E B6Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302168CompletedSep 2015Late, Mar 2016
Amantra PH 1 Tower B A2Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302120CompletedSep 2015Late, Mar 2016
Inora Park PH II - 3 BHKLand Survey No 27by2Pand 27by9P Undri Tal Haveli Pune104CompletedOct 2014Jul 2014
Eden Court, PH III -Centraus MallPlot No II G 7 8 Action Area II ew Town Rajarhat Kolkata 700 15638CompletedMar 2014Late, May 2014
Eden Court, PH II - T-D,EPlot No II G 7 8 Action Area II ew Town Rajarhat Kolkata 700 156171CompletedJun 2013Late, Sep 2013
Prive Phase II - 25 VillasPrive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 40125CompletedMar 2013Late, Aug 2014
Prive Phase II - 13 VillasPrive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 40113CompletedMar 2013Late, Apr 2015
Inora Park PH I - 2,2 1/2 BHKLand Survey No 27by2Pand 27by9P Undri Tal Haveli Pune141CompletedJan 2013Late, Aug 2013
Prive Phase I - 35 VillasPrive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 40135CompletedMar 2012Late, Jun 2013
Eden Court, PH I - T-A,B,CPlot NoII G7 8 Action Area II New Town Rajarhat Kolkata 700 156348CompletedMar 2012Late, Jun 2012
New Haven Boisar 1 and Row HouseChillar Road Betegaon Boisar East Maharashtra 4015011,438CompletedDec 2011Late, Mar 2015
Aquila HeightsSy No 27 HMT HMT Factory Main Road Near HMT School Peenya Plantation Yelahanka Hobli Bengaluru North Taluk Bengaluru 560053108CompletedDec 2011Late, Oct 2012
Shubh Griha Boisar IChillar Road Betegaon Boisar East Maharashtra 4015011,578CompletedJun 2011Late, Dec 2013

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aveza Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East,6,700+ in Mumbai Suburban

2 kmAveza Phase 1Completed 51Lapsed / revoked 52Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: Tata Housing Development Company Limited

TATA HOUSING DEVELOPMENT COMPANY LIMITED has 3 registrations on MahaRERA, including Amantra Phase 2 and Aveza Phase 1. Its filings disclose 25 earlier MahaRERA projects: declares 2 of 25 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Aveza Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Aveza Phase 1 is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aveza Phase 1?

The registered promoter entity is Tata Housing Development Company Limited, a company as per the filing. Its CIN U45300MH1942PLC003573 and GSTIN 27AAACT0191Q1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aveza Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Aveza Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Aveza Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aveza Phase 1?

The professionals named in the filing: Architect: Kapadia Associates; Engineer: Gokani Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aveza Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aveza Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aveza Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.