AVANT PARK WEST

By M/s. Kratee Infracon Pvt. Ltd.

RG-MH-06802 · RERA P51800053738 · Last updated on MahaRERA portal: 29 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 4 months from the original
2 of 11Construction stages donefurthest along: Basement (if any), 70%
67 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

AVANT PARK WEST is a Residential / Group Housing project by M/s. Kratee Infracon Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053738 on 28 Nov 2023. Possession is promised by 30 Oct 2027. The completion date has moved by 4 months from the original filing. 5 of the 72 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameAVANT PARK WEST
  • TypeResidential / Group Housing
  • Location
    • Dadabhai Cross Road No. 3
    • Vile Parle (West)
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400056
  • Pincode400056
  • RERA no.P51800053738
  • ReraGenie IDRG-MH-06802

Builder

  • NameM/s. Kratee Infracon Pvt. Ltd.
  • Entity typeCompany
  • CINU70109MH2019PTC328076
  • DirectorsSharan Piyush Parekh, Sudhir Jayantilal Vajani

Key dates

this monthRegisteredNov 2023First promiseJun 2027Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2023
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2027)
  • Buildings1 building record
  • Documents filed67 files

Current status

7%5 of 72 units booked
41.7%Work done, per cost certificate

Figures as on 29 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Park WestNA11872072

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 70%.

Park West: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises29%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.22%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes30%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed113

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots113
Closed/Covered113

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,475 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Aug 2025
LandownerVillageDistrict
Amit Darshan Co Operative Housing Society Ltd.VileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI6713.23
Proposed, not sanctioned6,685 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch348/352, I and II FLOOR, ZAVERI BUILDING, ABDUL REHMAN STREET, MUMBAI 400003
Estimated costRs 64.36 cr
Cost incurredRs 26.84 cr
Work done41.7%
BuildingWingEstimatedIncurred
Park WestNARs 64.36 crRs 26.84 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkit Dharia
ArchitectPARIN NILESH SHAH
EngineerDivya Home Solutions
EngineerJACOB BASTYAW DSOUZA
EngineerClint Patrick Dos Santos
Chartered AccountantH P Jadeja & Associates
Chartered AccountantNEHALI DOSHI
Chartered AccountantJIMIT SHAH
PartnerRole in project
M/s. Kratee Infracon Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51800053738/WarJun 2027 → Oct 2027

Reason as filed by the promoterNA

Litigation declared1

CaseCourtStatus
6792/2022/2022Dindoshi CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: form 2A (engineer certificate) new format park west_Issue.pdf29 Sep 2026
Withdrawal Update Form 1File: Architect Certificate_Avant Park West_June 2026.pdf7 Aug 2026
Withdrawal Update Form 2File: Engineer Certificate_Avant Park West_June 2026.pdf7 Aug 2026
Withdrawal Update Form 3File: CA Certificate_Avant Park West_June 2026.pdf7 Aug 2026
Withdrawal Update Form 1File: Form 1_Architects Certificate_Avant Park West_March 2026.pdf5 May 2026
Withdrawal Update Form 2File: Engineer Certificate_Avant Park West_March 2026.pdf5 May 2026
Withdrawal Update Form 3File: CA Certificate_Avant Park West_March 2026.pdf5 May 2026
Building plan approvalFile: IOD.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 1-1 highlighted.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 2-2.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 3-3.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 4-4.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 5-6.pdf17 Mar 2026
Layout approvalFile: Approved Drawing 7-end.pdf17 Mar 2026
Commencement certificateFile: 2025-09-10_2493986_FurtherCC_signed- Sept 2025.pdf25 Feb 2026
Withdrawal Update Form 1File: Form 1 architects certificate park west dec 2025 (1).pdf25 Feb 2026
Withdrawal Update Form 1File: Form 1 architects certificate park west dec 2025 (1).pdf25 Feb 2026
Withdrawal Update Form 2File: PARK WEST FORM 2 DEC 25.pdf25 Feb 2026
Withdrawal Update Form 2File: PARK WEST FORM 2 DEC 25.pdf25 Feb 2026
Withdrawal Update Form 3File: Signed CA Certificate-KRATEE INFRA AMIT DARSHAN-dec 25.pdf25 Feb 2026
Withdrawal Update Form 3File: Signed CA Certificate-KRATEE INFRA AMIT DARSHAN-dec 25.pdf25 Feb 2026
Withdrawal Update Form 1File: Form 1 architects certificate Park West September 2025_.pdf8 Nov 2025
Withdrawal Update Form 2File: PARK WEST Engineer FORM 2 sep 25 (1).pdf8 Nov 2025
Withdrawal Update Form 3File: Signed CA Certificate-Park West Project- KRATEE -Sept25.pdf8 Nov 2025
Withdrawal Update Form 1File: form 1.pdf7 Nov 2025
Withdrawal Update Form 2File: form 2.pdf7 Nov 2025
Withdrawal Update Form 3File: form 3.pdf7 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate-KRATEE INFRA AMIT DARSHAN-Mar 25.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf8 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Park West Form 2 Dec .pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf11 Feb 2025
Building plan approvalFile: IOD signed_29th Aug 24.pdf25 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: IOD signed_29th Aug 24.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_ sep 24.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Final Architect Certificate.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf6 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf6 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf6 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf6 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf6 Jun 2024
Copy of the legal title reportFile: Title Certificate Final.pdf18 Nov 2023
Declaration in FORM BFile: affidavit cum Declaration - Promoter FINAL.pdf7 Nov 2023
PAN CardFile: Pan Card Colour.pdf2 Nov 2023
CERSAI detailsFile: CERSAI Undertaking with Report FINAL.pdf2 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3-REVISED FINAL.pdf2 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure in Other Organisation.pdf2 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account DECLARATON FORMAT A 4 2 l d.pdf2 Nov 2023
Layout approvalFile: Drawing.pdf31 Oct 2023
Copy of Layout Approval (in case of layout)File: Drawing.pdf31 Oct 2023
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf12 Oct 2023
Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf12 Oct 2023
Building plan approvalFile: IOD_signed.pdf30 Sep 2023
Details of encumbrances concerned to FinanceFile: declaration Legal.pdf30 Sep 2023
Details of encumbrances concerned to FinanceFile: declaration Finance.pdf30 Sep 2023
Details of encumbrances concerned to LegalFile: declaration Legal.pdf30 Sep 2023
Details of encumbrances concerned to LegalFile: declaration Finance.pdf30 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD_signed.pdf30 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: FirstCC_signed.pdf30 Sep 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (LH).pdf30 Sep 2023
Deviation Report with respect to Allotment letterFile: No_Deviation_Allotment.pdf30 Sep 2023
Deviation Report with respect to model copy of AgreementFile: No_Deviation_AFS.pdf30 Sep 2023

How this compares with Mumbai Suburban

7%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 4 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVANT PARK WEST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle (West)6,700+ in Mumbai Suburban

Builder: M/s. Kratee Infracon Pvt. Ltd.

M/s. Kratee Infracon Pvt. Ltd. has 1 registration on MahaRERA, including AVANT PARK WEST. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AVANT PARK WEST is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVANT PARK WEST?

The registered promoter entity is M/s. Kratee Infracon Pvt. Ltd., a company as per the filing. Its CIN U70109MH2019PTC328076 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVANT PARK WEST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AVANT PARK WEST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVANT PARK WEST?

The professionals named in the filing: Architect: Ankit Dharia; Architect: PARIN NILESH SHAH; Engineer: Divya Home Solutions; Engineer: JACOB BASTYAW DSOUZA; Engineer: Clint Patrick Dos Santos; Chartered Accountant: H P Jadeja & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVANT PARK WEST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVANT PARK WEST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVANT PARK WEST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.