Avant Heera Complex
By Avant Jakhar Natural Resources LLP
RG-MH-04527 · RERA P51800022151 · Last updated on MahaRERA portal: 12 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Avant Heera Complex is a Residential / Group Housing project by Avant Jakhar Natural Resources LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800022151 on 4 Sep 2019. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameAvant Heera Complex
- TypeResidential / Group Housing
- Location
- R R Thakur Road
- Majas Village
- Andheri
- Mumbai Suburban
- 400060
- Pincode400060
- RERA no.P51800022151
- ReraGenie IDRG-MH-04527
Builder
- NameAvant Jakhar Natural Resources LLP
- Entity typeOthers
- Named personsudeep saha
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Sep 2019
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings1 building record
- Documents filed21 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Avant Heera Complex Building No 2 Extension | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.
Avant Heera Complex Building No 2 Extension: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 65% |
Progress on shared amenities15
As on 12 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 25% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ashutosh Kane |
| Engineer | Mohd Suhil Shaikh |
| Engineer | Brixwell Engineering |
| Chartered Accountant | Ankita Nikhil Shah |
| Chartered Accountant | Sen and Ray |
| Partner | Role in project |
|---|---|
| Avant Jakhar Natural Resources LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196251 | Sanjay Narayan Das | sudeep kumar saha | 04/03/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Dec 2024
Documents filed21
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Other.pdf | 12 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 17 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 17 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 18 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Avant Heera Complex.pdf | 18 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: cc revalidation.pdf | 23 Aug 2019 |
| Layout approvalFile: layout.pdf | 22 Aug 2019 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 22 Aug 2019 |
| Declaration in FORM BFile: FORM B.pdf | 22 Aug 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 22 Aug 2019 |
| Proforma of Allotment letterFile: Agreement for Sale and Allotment letter.pdf | 22 Aug 2019 |
| Building plan approvalFile: IOA.pdf | 3 Aug 2019 |
| PAN CardFile: Avant Jakhar Natural Resources LLP_ pan card.pdf | 3 Aug 2019 |
| Copy of the legal title reportFile: title certificate.pdf | 3 Aug 2019 |
| Details of encumbrancesFile: encumbrances.pdf | 3 Aug 2019 |
| Building Plan Approval (IOD)File: IOA.pdf | 3 Aug 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf | 3 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf | 3 Aug 2019 |
| Certificates of CA (Form 3)File: CA Certificate (form 3).pdf | 3 Aug 2019 |
| OtherFile: oc cum amended plan.pdf | 3 Aug 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 21 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Avant Heera Complex on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Majas Village6,700+ in Mumbai Suburban
RATAN HERITAGE
NEXUS BUILDERS & DEVELOPERS
JP Parkway
Srushti Raj Developers LLP
Gyan Gold Crest
Gyan S. P. Developers LLP
PREM BUILDERS
PREM BUILDERS
Edenrose
Hillview Venture
AIM Garden
AIM Developers
See every Mumbai Suburban project, with the district possession charts
Builder: Avant Jakhar Natural Resources LLP
Avant Jakhar Natural Resources LLP has 1 registration on MahaRERA, including Avant Heera Complex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Avant Heera Complex shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Avant Heera Complex is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Avant Heera Complex?
The registered promoter entity is Avant Jakhar Natural Resources LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Avant Heera Complex?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Avant Heera Complex?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Avant Heera Complex?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Avant Heera Complex?
The professionals named in the filing: Architect: Ashutosh Kane; Engineer: Mohd Suhil Shaikh; Engineer: Brixwell Engineering; Chartered Accountant: Ankita Nikhil Shah; Chartered Accountant: Sen and Ray. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Avant Heera Complex?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.