Home / Browse projects / Thane, Maharashtra / AURUM
AURUM
RG-MH-14372 · RERA P51700022870 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AURUM is a Residential / Group Housing project by Shree GHP Housing in Thane, Maharashtra, registered with MahaRERA as P51700022870 on 1 Nov 2019. Possession was promised by 15 Sep 2026 and is now 1 months past that date. The completion date has moved by 36 months from the original filing. 18 of the 63 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameAURUM
- TypeResidential / Group Housing
- Location
- Kharkarli Road
- Thane
- Thane (M Corp.)
- 400601
- Pincode400601
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700022870
- ReraGenie IDRG-MH-14372
Builder
- NameShree GHP Housing
- Entity typePartnership
- PartnersHimanshu Prashant Sharma, Pravin Raghunath Jadhav, Ashish Mehender Dhanani, Yugank Dikshant Sharma, Narendra Arjan Dhanani
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Nov 2019
- Promised completion15 Sep 2026
- Revised completionRevised to 15 Sep 2026 (originally 15 Sep 2023)
- Buildings1 building record
- Documents filed118 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AURUM | NA | 17 | 0 | 61 | 2 | 63 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
AURUM: 62% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed142
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Milind Prabhakar Bhagwat | Thane (M Corp.) | Thane |
| Pathik Milind Bhagwat | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| AURUM | NA | Rs 22.00 cr | Rs 14.75 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TEN FOLDS ARCHITECTS AND CONSULTANTS Jagwani |
| Engineer | Archetype Consultants I Pvt Ltd |
| Engineer | MILIND THAKUR |
| Chartered Accountant | Bhupendra P Shah |
| Chartered Accountant | S Nagwekar And Co |
| Partner | Role in project |
|---|---|
| Shree GHP Housing | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe construction was delayed due to DP road from 9 mtrs to 12 mtrs. was not sanctioned, so we are not getting permission of construction above 10 floors. Now DP road sanctioned from TMC and we have received CC upto 16th floors of the project as on date 15.01.2024
Reason as filed by the promoterwe got the CC, but due to delay period the Labour contractor was not willing to work as per the old rate, therefore we had to search for other Labour contractors.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Sep 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form1 June26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: SGH Form 2 June26 .pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form3 Aurum June26.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A-Mar26.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form1 Mar26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Mar26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: GHP Aurum Mar26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Form1 Archi Dec25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: Form2 Dec25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: Form3 CA Dec25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: Form1 Arch Sept25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form2 Sept25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form3 ca Sept25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: Form1 Archi certi.pdf | 4 Sep 2025 |
| Withdrawal Update Form 2File: Form2 June Engg.pdf | 4 Sep 2025 |
| Withdrawal Update Form 3File: Form3 AURUM.pdf | 4 Sep 2025 |
| Withdrawal Update Form 1File: Form1 Archi certi.pdf | 7 Aug 2025 |
| Withdrawal Update Form 2File: Form2 June Engg.pdf | 7 Aug 2025 |
| Withdrawal Update Form 3File: Form3 AURUM.pdf | 7 Aug 2025 |
| Form 2A (FY 2024-2025)File: Form2A.pdf | 7 Aug 2025 |
| Form 5 (FY 2024-2025)File: Form5 GHP Mar25.pdf | 15 Jul 2025 |
| Form 1File: Form1 Mar 2025.pdf | 12 Jun 2025 |
| Form 2File: Form2 Mar25.pdf | 12 Jun 2025 |
| Form 3File: Form3 GHP Mar25.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold-unsold mar25.pdf | 12 Jun 2025 |
| Form 1File: Form1 Architect DEC24.pdf | 26 May 2025 |
| Form 1File: Arch Form1 Sept24.pdf | 26 May 2025 |
| Form 2File: Form2 SEPT24.pdf | 26 May 2025 |
| Form 3File: Form3 sept24.pdf | 26 May 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold sept24 GHP.pdf | 26 May 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report.pdf | 25 Apr 2025 |
| Proforma of Agreement for saleFile: RERA - Revised Ag of Sale AURUM.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Mar25-AURUM.pdf | 4 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 GHP Dec24.pdf | 27 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 GHP Dec24.pdf | 27 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold sept24 GHP.pdf | 27 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold Dec24 GHP.pdf | 27 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect DEC24.pdf | 15 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GHP Form3 sept24.pdf | 29 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 GHP SEPT24.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Form1 Sept24.pdf | 24 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA June24.pdf | 24 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 JUNE24.pdf | 24 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold June 24.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AURUM Form1 Arch certi June24.pdf | 10 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site supervisor March24.pdf | 2 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold March24.pdf | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 ENGG Mar24.pdf | 29 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA certifi Mar2024.pdf | 29 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 GHP March24.pdf | 29 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Arch certi Mar 24.pdf | 13 Apr 2024 |
| Layout approvalFile: Layout plan.pdf | 31 Jan 2024 |
| Building plan approvalFile: First and Gr flr.pdf | 31 Jan 2024 |
| Building plan approvalFile: 2 to 10 flr.pdf | 31 Jan 2024 |
| Building plan approvalFile: 11 to 16 flr.pdf | 31 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: Layout plan.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: First and Gr flr.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 to 10 flr.pdf | 31 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 11 to 16 flr.pdf | 31 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Thane 16th flr.pdf | 31 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration cc.pdf | 31 Jan 2024 |
| Declaration in FORM BFile: Form B developer.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certi form1.pdf | 31 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certi form2.pdf | 31 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf | 31 Jan 2024 |
| CERSAI detailsFile: CERSAI REPORT 24124.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certi form3.pdf | 31 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Mar23 sold unsold ghp.pdf | 27 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: sept23 sold unsold ghp.pdf | 27 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sept-2023 ghp housing.pdf | 27 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect sept23.pdf | 9 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 ghp.pdf | 17 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5 ghp.pdf | 17 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FY22-23 form2A AURUM.pdf | 3 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Form1 Mar 23.pdf | 19 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold sept 22.pdf | 21 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AURUM ca certi sept 22.pdf | 21 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Arch Mar 20.pdf | 19 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Arch sept 20.pdf | 19 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 arch Mar 21.pdf | 19 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AURUM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Thane7,600+ in Thane
Filed coordinates, straight-line distance. 91 registered projects within 2 km.
ASHAR PULSE
Ms ASHAR VENTURES
SHETH ZURI
Sheth Developers Private Limited
Jagdale Edge
JAGDALE INFRASTRUCTURE PVT. LTD.
Bliss
Kapstone Constructions Private Limited
RUSTOMJEE LA VIE Wing D
Kapstone Constructions Private Limited
Thane Project
LODHA DEVELOPERS LIMITED
See every Thane project, with the district possession charts
Builder: Shree GHP Housing
Shree GHP Housing has 1 registration on MahaRERA, including AURUM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if AURUM is delayed beyond 15 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AURUM?
The registered promoter entity is Shree GHP Housing, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AURUM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AURUM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AURUM?
The professionals named in the filing: Architect: TEN FOLDS ARCHITECTS AND CONSULTANTS Jagwani; Engineer: Archetype Consultants I Pvt Ltd; Engineer: MILIND THAKUR; Chartered Accountant: Bhupendra P Shah; Chartered Accountant: S Nagwekar And Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AURUM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback