ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP

Registered No litigation declared Others project

AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP

By TRANSCON-SHETH CREATORS PRIVATE LIMITED

RG-MH-29628 · RERA P51800029004 · Last updated on MahaRERA portal: 11 Apr 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP is a Others project by TRANSCON-SHETH CREATORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029004 on 23 Apr 2021. Possession is promised by 30 Apr 2027.

At a glance

Project

  • NameAURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP
  • TypeOthers
  • Location
    • DE MONTE LANE
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029004
  • ReraGenie IDRG-MH-29628

Builder

  • NameTRANSCON-SHETH CREATORS PRIVATE LIMITED
  • Entity typeCompany
  • GSTIN27AAACT0197J1Z6
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsJitendra Natwarlal Sheth, Kirti Kediya
  • Other registrations7 more →
  • Completed2 of 8
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredApr 2021PromisedApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Apr 2021
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOPNA510000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,560 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI24428.17
Proposed, not sanctioned1,008 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNO 6 THE ARCADE WORLD TRADE CENTRE CUFF PARADE MUMBAI 400005

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARUN GURAV
EngineerKISHOR SHETYE
Chartered AccountantPAWANKUMAR RUNGTA
Chartered AccountantNeena Ramgarhia Neena Ramgarhia
PartnerRole in project
TRANSCON-SHETH CREATORS PRIVATE LIMITED-

Litigation declared30

CaseCourtStatus
3849/2004CITY CIVIL COURTPENDING
846/2013CITY CIVIL COURTPENDING
10/2014CITY CIVIL COURTPENDING
545/2007CITY CIVIL COURTPENDING
5074/2013HIGH COURTPENDING
261/2013HIGH POWER COMMITEEPENDING
NIL/2019AGRCPENDING
2847/2011HIGH COURTPENDING
10725/2015HIGH COURTPENDING
1381/2019HIGH COURTPENDING
1346/2019HIGH COURTPENDING
1305/2019HIGH COURTPENDING
2947/2017HIGH COURTPENDING
2948/2017HIGH COURTPENDING
11710/2016HIGH COURTPENDING
8035/2009HIGH COURTPENDING
1456/2020HIGH COURTPENDING
1400/2020HIGH COURTPENDING
433/2020HIGH COURTPENDING
193/2014HIGH COURTPENDING
3773/2017CITY CIVIL COURTPENDING
748/2015CITY CIVIL COURTPENDING
3201/2016CITY CIVIL COURTPENDING
353/2005CITY CIVIL COURTPENDING
2484/2012CITY CIVIL COURTPENDING
2842/2015CITY CIVIL COURTPENDING
3447/2015CITY CIVIL COURTPENDING
8640/1990CITY CIVIL COURTPENDING
2331/2004CITY CIVIL COURTPENDING
1076/2015CITY CIVIL COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: Orlem CC wing B Sale 4.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower-06 C Auris Illaria - Commericial.pdf2 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-05 Tower-06 C - Auris Ilaria - Commercial Mar-22.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower-06 C - Auris Ilaria - Commercial.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Auris Ilaria Tower -C.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower-06 C - Auris Ilaria - Commercial.pdf6 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: doc07591120230105182939.pdf7 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Auris IIaria Tower C 30-Sep-2022.pdf6 Dec 2022
Building plan approvalFile: layout1.pdf14 Apr 2021
PAN CardFile: TRANSCON SHETH CREATORS PAN.PDF14 Apr 2021
Copy of the legal title reportFile: Legal Title Report.pdf14 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: layout1.pdf14 Apr 2021
Declaration in FORM BFile: Declaration in FORM B Tower C Comercial Shop.pdf15 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate Form 1.pdf15 Mar 2021
Layout approvalFile: LAYOUT AURIS ILARIA.pdf12 Mar 2021
Building plan approvalFile: Building Approval Plan_03.pdf12 Mar 2021
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf12 Mar 2021
Details of encumbrancesFile: Encumbrance Certificate.pdf12 Mar 2021
Copy of Layout Approval (in case of layout)File: LAYOUT AURIS ILARIA.pdf12 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Approval Plan_03.pdf12 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC 05-Mar-2021.pdf12 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-C A CERTIFICAT Auris Ilaria Tower C - Commercial.pdf12 Mar 2021
Proforma of Allotment letterFile: Proforma - AURIS TOWER C COMMERCIAL.pdf12 Mar 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

2 kmAURIS ILARIA TOWER C PHACompleted 43Lapsed / revoked 14Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: TRANSCON-SHETH CREATORS PRIVATE LIMITED

TRANSCON-SHETH CREATORS PRIVATE LIMITED has 8 registrations on MahaRERA, including AURIS SERENITY TOWER 1 and AURIS SERENITY TOWER 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP?

The registered promoter entity is TRANSCON-SHETH CREATORS PRIVATE LIMITED, a company as per the filing. Its GSTIN 27AAACT0197J1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP?

The professionals named in the filing: Architect: ARUN GURAV; Engineer: KISHOR SHETYE; Chartered Accountant: PAWANKUMAR RUNGTA; Chartered Accountant: Neena Ramgarhia Neena Ramgarhia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AURIS ILARIA TOWER C PHASE I COMMERCIAL SHOP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.