Home / Browse projects / Raigarh, Maharashtra / AURA VILLAGE PHASE 1

Completed No litigation declared Residential / Group Housing project

AURA VILLAGE PHASE 1

By VECTOR LIFESPACE LLP

RG-MH-67483 · RERA P52000010261 · Last updated on MahaRERA portal: 28 Mar 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Nov 2020Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

AURA VILLAGE PHASE 1 is a Residential / Group Housing project by VECTOR LIFESPACE LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000010261 on 24 Aug 2017. The registration is recorded completed; possession was promised by 20 Nov 2020.

At a glance

Project

  • NameAURA VILLAGE PHASE 1
  • TypeResidential / Group Housing
  • Location
    • pen
    • Pen (M Cl)
    • Raigarh
    • 402107
  • Pincode402107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000010261
  • ReraGenie IDRG-MH-67483

Builder

  • NameVECTOR LIFESPACE LLP
  • Entity typePartnership
  • PartnersUMESH PRAPHAKAR RAO, VASANT NARAYAN JADHAV

Key dates

this monthRegisteredAug 2017PromisedNov 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Aug 2017
  • Promised completion20 Nov 2020
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Number 3NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

Building Number 3: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 28 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes65%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes15%
Open ParkingYes100%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,598 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6506.0
Proposed, not sanctioned6,506 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1TO3 SHAKTI SHOPPING ARCADECO-OP HOUSING SOCIETY LTD OPP BADWAIK HOSPITAL BHANDUP W

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIKHILMESHRAM
PartnerRole in project
VECTOR LIFESPACE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Mar 2024

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: SAMVAAD ARCHITECTS.pdf28 Mar 2024
Details of encumbrances concerned to FinanceFile: no encumbrances certificate.pdf21 Mar 2024
Details of encumbrances concerned to LegalFile: no encumbrances certificate.pdf21 Mar 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement of sale.pdf21 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1.pdf21 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan0100_comp.pdf21 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan0099_comp.pdf21 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SAMVAAD ARCHITECTS.pdf21 Mar 2024
OtherFile: kp.pdf7 Aug 2018
Certificates of CA (Form 3)File: 1.pdf2 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Scan.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Scan2.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 207.pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 208.pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 370.pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 371.pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 701.pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: 702.pdf28 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf28 Mar 2018
Building plan approvalFile: Layout.pdf27 Mar 2018
Building plan approvalFile: Building No3.pdf27 Mar 2018
Building Plan Approval (IOD)File: Layout.pdf27 Mar 2018
Building Plan Approval (IOD)File: Building No3.pdf27 Mar 2018
Layout approvalFile: Lay Out.pdf3 Aug 2017
Building plan approvalFile: Approved Plan.pdf3 Aug 2017
PAN CardFile: LLP PAN Card.pdf3 Aug 2017
Copy of the legal title reportFile: Title Certificate.pdf3 Aug 2017
Details of encumbrancesFile: Certificate.pdf3 Aug 2017
Copy of Layout Approval (in case of layout)File: Lay Out.pdf3 Aug 2017
Building Plan Approval (IOD)File: Approved Plan.pdf3 Aug 2017
Declaration in FORM BFile: Notry 1.pdf3 Aug 2017
Declaration in FORM BFile: Notry 2.pdf3 Aug 2017
Declaration in FORM BFile: Notry 3.pdf3 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch final certificate.pdf3 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate.pdf3 Aug 2017
Certificates of CA (Form 3)File: SR sir.pdf3 Aug 2017
Proforma of Allotment letterFile: vector Lifespace LLP agreement performa.pdf3 Aug 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AURA VILLAGE PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pen5,900+ in Raigarh

2 kmAURA VILLAGE PHASE 1Completed 51Lapsed / revoked 21Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: VECTOR LIFESPACE LLP

VECTOR LIFESPACE LLP has 1 registration on MahaRERA, including AURA VILLAGE PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if AURA VILLAGE PHASE 1 is delayed beyond 20 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AURA VILLAGE PHASE 1?

The registered promoter entity is VECTOR LIFESPACE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AURA VILLAGE PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AURA VILLAGE PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AURA VILLAGE PHASE 1?

The professionals named in the filing: Architect: NIKHILMESHRAM. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AURA VILLAGE PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AURA VILLAGE PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AURA VILLAGE PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.