Audumbar Parvati by Gaurav Developers
RG-MH-87378 · RERA P52100048688 · Last updated on MahaRERA portal: 7 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 15 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 20 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Audumbar Parvati by Gaurav Developers is a Residential / Group Housing project by GAURAV DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100048688 on 12 Jan 2023. Possession was promised by 30 Jul 2025 and is now 15 months past that date. The completion date has moved by 20 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameAudumbar Parvati by Gaurav Developers
- TypeResidential / Group Housing
- Location
- Near Akshara International School
- Pimpri Chinchwad
- Tathwade
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100048688
- ReraGenie IDRG-MH-87378
Builder
- NameGAURAV DEVELOPERS
- Entity typePartnership
- PartnersRahul Kawashte, Kiran Dewadiga, Nitin Khatpe
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Jan 2023
- Promised completion30 Jul 2025
- Revised completionRevised to 30 Jul 2025 (originally 4 Nov 2023)
- Buildings1 building record
- Documents filed115 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Audumbar Parvati | NA | 7 | 6 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
Audumbar Parvati: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 7 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed44
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Parubai Lingayya Bhandari | Tathwade | Pune |
| Umesh Lingayya Bhandari | Tathwade | Pune |
| Ramesh Lingayya Bhandari | Tathwade | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | Rutuja Narsingh & Associates |
| Partner | Role in project |
|---|---|
| GAURAV DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602179 | Jyoti Parshuram Lashkare | GAURAV DEVELOPERS | 13/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Jan 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Aug 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed115
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: 3 Declaration in FORM B.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: dec 24 f3.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: jun 24 f3.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sep 24 f3.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20250121141607.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 fy 2223.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 4.pdf | 7 Feb 2025 |
| Declaration in FORM BFile: Affidavit Audumber Parvati.pdf | 31 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 As on 31st December 24 Audumber Parvati.pdf | 31 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A Certificate Audumber Parvati.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumber Parvati as on 31-12-2024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on 31-12-2024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on Dec 2024.pdf | 18 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Audumber Parvati - FY 2023-24.pdf | 3 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sept 2024.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: March 24.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 23.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sept 23.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 2024.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 23.pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: March 2023.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 2023.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: June 2023.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: September 23.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: December 23.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 2024.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 June 24.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Sept 24.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: September 24.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: September 24.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 2024.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 24.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: December 23.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: September 23.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 2023.pdf | 2 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 23.pdf | 2 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumber Parvati as on 31-12-2023.pdf | 28 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumber Parvati as on 31-03-2024.pdf | 28 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on June 2024.pdf | 28 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on Sep 2024.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumber Parvati as on December 2023.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumber Parvati as on March 2024.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on June 2024.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on Sep 2024.pdf | 28 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumber Parvati as on 31-12-2023.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumber Parvati as on 31-03-2024.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on Sep 2024.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumber Parvati as on December 2023.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumber Parvati as on March 2024.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on Sep 2024.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 As on june 2024 Audumber Parvati.pdf | 24 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 As on Sept 2024 Audumber Parvati.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on June 2024 Revised.pdf | 24 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on Sep 2024 Revised.pdf | 24 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on June 2024 Revised.pdf | 24 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on Sep 2024 Revised.pdf | 24 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on June 2024.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on June 2024.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Audumbar Parvati as on Sep 2024.pdf | 23 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on Sep 2024.pdf | 23 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on June 2024.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate March 2023 Audumber (1).pdf | 14 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Audumbar Parvati as on 31-03-2023.pdf | 14 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Audumbar Parvati as on 31-03-2023.pdf | 14 Dec 2024 |
| Layout approvalFile: Plan - Audumbar Parvati.pdf | 6 Aug 2024 |
| Building plan approvalFile: Plan - Audumbar Parvati.pdf | 6 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Plan - Audumbar Parvati.pdf | 6 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan - Audumbar Parvati.pdf | 6 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - Audumbar Parvati.pdf | 6 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on Dec 2023.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on March 2024.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on June 2024.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 CA Certificate on Project Cost Fund withdrawal (Form 3) (2).pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: f.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on March 2023.pdf | 9 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Audumbar Parvati as on June 2023.pdf | 9 Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 115 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Audumbar Parvati by Gaurav Developers on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimpri Chinchwad13,700+ in Pune
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: GAURAV DEVELOPERS
Gaurav Developers has 2 registrations on MahaRERA, including Gaurav Shripad and Audumbar Parvati by Gaurav Developers. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Audumbar Parvati by Gaurav Developers shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Audumbar Parvati by Gaurav Developers is delayed beyond 30 Jul 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Audumbar Parvati by Gaurav Developers?
The registered promoter entity is GAURAV DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Audumbar Parvati by Gaurav Developers?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Audumbar Parvati by Gaurav Developers?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Audumbar Parvati by Gaurav Developers?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Audumbar Parvati by Gaurav Developers?
The professionals named in the filing: Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Audumbar Parvati by Gaurav Developers?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback