Home / Browse projects / Pune, Maharashtra / ATUL VIHAR

Registration lapsed No litigation declared Residential / Group Housing project

ATUL VIHAR

By JOSHI JAGTAP ASSOCIATES

RG-MH-17040 · RERA P52100028039 · Last updated on MahaRERA portal: 12 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 25 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
7 of 11Construction stages donefurthest along: Basement (if any), 0%
16 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

ATUL VIHAR is a Residential / Group Housing project by JOSHI JAGTAP ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100028039 on 26 Jan 2021. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 25 months from the original filing. 5 of the 21 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameATUL VIHAR
  • TypeResidential / Group Housing
  • Location
    • KOTHRUD
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411038
  • Pincode411038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028039
  • ReraGenie IDRG-MH-17040

Builder

  • NameJOSHI JAGTAP ASSOCIATES
  • Entity typePartnership
  • PartnersBINDA ARVIND JAGTAP, KANCHAN SUNIL PIMPALKHUTE, KUMUD DEVIDAS JOSHI

Key dates

13 months past promisethis monthRegisteredJan 2021First promiseAug 2023Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jan 2021
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 28 Aug 2023)
  • Buildings1 building record
  • Documents filed85 files

Current status

24%5 of 21 units booked

Figures as on 12 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
atul viharNA7721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

atul vihar: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 12 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Fire Protection and Safety RequirementsYes100%

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered70

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area649 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
JOSHI JAGTAP ASSOCIATESPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI713.9
Proposed, not sanctioned714 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOTHRUD

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDD Architects
EngineerSanil Shinde
Chartered AccountantA V IYER and CO
Chartered AccountantSiddhant Biswas and Associates
Chartered AccountantA M Sadawarte and Co
PartnerRole in project
JOSHI JAGTAP ASSOCIATES-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019170Aug 2023 → Jun 2024

Reason as filed by the promoterRespected Sir/Madam, I Mrs. Bind Arvind Jagtap authorized partner of M/s Joshi Jagtap Associates’, the developer responsible for the construction of the "Atul Vihar" project located at Plot No 8, S.no. 26, Dahanukar Colony, CTS No 499, Pune 411038. We would like to bring to your attention the reason for the delay in completing the construction and request an extension of the completion date until 30th June 2024. The project has been already completed 100% and We have filed all the necessary documents with the local authority for the purpose of getting Completion Certificate. The time required

EXT52100024168Aug 2023 → Aug 2024

Reason as filed by the promoterRespected Sir/Madam, I Mrs. Bind Arvind Jagtap authorized partner of M/s Joshi Jagtap Associates’, the developer responsible for the construction of the "Atul Vihar" project located at Plot No 8, S.no. 26, Dahanukar Colony, CTS No 499, Pune 411038. We would like to bring to your attention to the reason for the delay in completing the construction and request an extension of the completion date until 26th August 2024. The project has been already completed 100% and We have filed all the necessary documents with the local authority for the purpose of getting Completion Certificate. The time requ

EXT52100017442Aug 2023 → Feb 2024

Reason as filed by the promoterRespected Sir/Madam, I Mrs. Bind Arvind Jagtap authorized partner of M/s Joshi Jagtap Associates’, the developer responsible for the construction of the "Atul Vihar" project located at Plot No 8, S.no. 26, Dahanukar Colony, CTS No 499, Pune 411038. We would like to bring to your attention the reasons for the delay in completing the construction and request an extension of the completion date until 28th February 2024. The delay in the completion of the project can be attributed to the below mentioned factor, which have severely impacted our construction timeline: Labour problems because of the

EXT52100027464Aug 2023 → Sep 2025

Reason as filed by the promoterRespected Sir/Madam, I Mrs. Bind Arvind Jagtap authorized partner of M/s Joshi Jagtap Associates’, the developer responsible for the construction of the "Atul Vihar" project located at Plot No 8, S.no. 26, Dahanukar Colony, CTS No 499, Pune 411038. We would like to bring to your attention to the reason for the delay in completing the construction and request an extension of the completion date. The construction of the project has been 100% completed and We have received part completion of the building upto 6th floor out of the total 7 floors. Furthermore We have submitted all the necessary doc

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Feb 2025

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 - ARCHITECT CERTIFICATE.pdf12 Dec 2025
Form 2File: FORM 2 - ENGINEER CERTIFICATE.pdf12 Dec 2025
Form 3File: FORM 3 - CA CERTIFICATE.pdf12 Dec 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF BOOKED, SOLD INVENTORY.pdf12 Dec 2025
Form 1File: FORM - 1.pdf4 Aug 2025
Form 2File: FORM - 2.pdf4 Aug 2025
Form 3File: FORM - 3.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf4 Aug 2025
Form 1File: FORM - 1.pdf30 May 2025
Form 2File: FORM - 2.pdf30 May 2025
Form 3File: FORM - 3.pdf30 May 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf30 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1.pdf26 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3.pdf26 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf26 Mar 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF BOOKED AND SOLD.pdf26 Mar 2025
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 - ARCHITECT'S CERTIFICATE.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 - ENGINEERS CERTIFICATE.pdf8 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC-1.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF BOOKED SOLD INVENTORY.pdf8 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2A - ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE.pdf8 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: DISCLORE OF SOLD BOOKED INVENTORY.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_Compressed.pdf28 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf11 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf11 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf11 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest In Other Real Estate Organisation.pdf11 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf27 Feb 2024
Declaration in FORM BFile: AFFIDAVIT - FOR EXTENSION_compressed.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INTVENTORY.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FOR UPLOAD.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FOR UPLOAD.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 LATEST FOR UPLOAD.pdf13 Sep 2023
Disclosure of sold/ booked inventoryFile: ATUL VIHAR SOLD BOOKED INVENTORY SIGNED.pdf4 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A.pdf29 Aug 2023
Declaration in FORM BFile: AFFIDAVIT - FORMAT B.pdf25 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - LATEST.pdf25 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: joshi jagtap format A.pdf14 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: LATEST COMMENCEMENT CERTIFICATE WITH STAMP SIGN-COMPRESSED.pdf8 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf8 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 COMPRESSED.pdf8 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf8 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FOR UPLOADING.pdf8 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 LASTEST SCAN.pdf8 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM -1 JOSHI JAGTAP - 2023_compressed.pdf30 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENG CERT- 2023 compressed.pdf30 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 2023.pdf30 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 2023 LATEST compressed.pdf30 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FROM - 5 RERA - 2023.pdf30 Jun 2023
Details of encumbrancesFile: JOSHI JAGTAP ASSO - ENCUMBRANCE CERTI FICATE.pdf10 May 2023
Proforma of Agreement for saleFile: JOSH JAGTAP - AGREEMENT FOR SALE OF FLAT_compressed.pdf10 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 2022_compressed.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM - 5 - JOSHI JAGTAP 20-21.pdf29 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 2021.pdf22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE- FORM 1.pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JJA.pdf6 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT ON STATEMENT OF ACCOUNTS - JJOSHI JAGTAP ASSO.pdf6 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE BANK AC LETTER.pdf5 Jan 2023
Layout approvalFile: LATEST SANCTION PLAN.pdf4 Jan 2023
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf4 Jan 2023
Details of encumbrances concerned to FinanceFile: TITLE SEARCH REPORT.pdf4 Jan 2023
Details of encumbrances concerned to LegalFile: TITLE SEARCH REPORT.pdf4 Jan 2023
Copy of Layout Approval (in case of layout)File: LATEST SANCTION PLAN.pdf4 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: LATEST COMMENCEMENT CERTIFICATE.pdf4 Jan 2023
Declaration about Commencement CertificateFile: COMMENCEMENT DECLARATION.pdf4 Jan 2023
CERSAI detailsFile: CERSAI UNDERTAKING.pdf4 Jan 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf4 Jan 2023
Proforma of Agreement for saleFile: PROFORMA AGREEMENT FOR SALE.pdf4 Jan 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION ALLOTMENT LETTER.pdf4 Jan 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION AGREEMENT.pdf4 Jan 2023
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf8 Jan 2021
Layout approvalFile: scan00000072.pdf7 Jan 2021
Details of encumbrancesFile: Details of encumbrances.pdf7 Jan 2021
Copy of Layout Approval (in case of layout)File: scan00000072.pdf7 Jan 2021
Declaration in FORM BFile: affidavit1_compressed (1).pdf30 Dec 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf30 Dec 2020

How this compares with Pune

24%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 25 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ATUL VIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KOTHRUD13,700+ in Pune

2 kmATUL VIHARCompleted 92Lapsed / revoked 46Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 290 registered projects within 2 km.

Builder: JOSHI JAGTAP ASSOCIATES

JOSHI JAGTAP ASSOCIATES has 1 registration on MahaRERA, including ATUL VIHAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that ATUL VIHAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ATUL VIHAR is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATUL VIHAR?

The registered promoter entity is JOSHI JAGTAP ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATUL VIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATUL VIHAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATUL VIHAR?

The professionals named in the filing: Architect: DD Architects; Engineer: Sanil Shinde; Chartered Accountant: A V IYER and CO; Chartered Accountant: Siddhant Biswas and Associates; Chartered Accountant: A M Sadawarte and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATUL VIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATUL VIHAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATUL VIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.