Home / Browse projects / Mumbai Suburban, Maharashtra / ATMARAM CHSL

Completed No litigation declared Others project

ATMARAM CHSL

By NAMOREALTY AND INFRA LLP

RG-MH-27111 · RERA P51800011731 · Last updated on MahaRERA portal: 8 Aug 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 35 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2022Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Excavation, 90%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

ATMARAM CHSL is a Others project by NAMOREALTY AND INFRA LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011731 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2022. The completion date has moved by 35 months from the original filing.

At a glance

Project

  • NameATMARAM CHSL
  • TypeOthers
  • Location
    • jai pali hill
    • borivali west
    • Borivali
    • Mumbai Suburban
    • 400103
  • Pincode400103
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011731
  • ReraGenie IDRG-MH-27111

Builder

  • NameNAMOREALTY AND INFRA LLP
  • Entity typePartnership
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseOct 2019Revised toSep 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Oct 2019)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ATMARAM CHSLNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 90%.

ATMARAM CHSL: 80% average across the applicable activities

ActivityProgress
Excavation90%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 8 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered41

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area911 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3175.0
Proposed, not sanctioned2,705 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMDAS SUTRALE ROAD BORIVALI WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDREAMS INFRASTRUCTURE
EngineerRAJE CONSULTANTS
Chartered AccountantVAYEDA AND ASSOCIATES
PartnerRole in project
NAMOREALTY AND INFRA LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009814Oct 2019 → Mar 2022

Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects.

EXT51800002549Oct 2019 → Oct 2020

Reason as filed by the promoterApprovals pending from MCGM .

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jul 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Aug 2022

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT FORM 4(1).pdf8 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf4 Aug 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: REGISTRATION CERTIFICATE.pdf4 Aug 2022
Status of ConveyanceFile: Deemed Conveyance_1-13.pdf4 Aug 2022
Status of ConveyanceFile: Deemed Conveyance_14-26.pdf4 Aug 2022
Status of ConveyanceFile: Deemed Conveyance_27-end.pdf4 Aug 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT CC-compressed.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - 2020-compressed.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTIFICATE - FORM 2A.pdf21 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - FY 19-20.pdf18 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - FY 20 -21.pdf18 Jun 2021
Disclosure of sold/ booked inventoryFile: BOOKED-SOLD INVENTORY.pdf21 May 2021
Building plan approvalFile: Drawing.pdf13 Jul 2020
Building Plan Approval (IOD)File: Drawing.pdf13 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: 2250441_FurtherCC_signed.pdf12 Jul 2020
Building plan approvalFile: 2245486Amendletter_signed.pdf2 Jul 2020
Building Plan Approval (IOD)File: 2245486Amendletter_signed.pdf2 Jul 2020
Building plan approvalFile: AM PLAN .pdf15 Feb 2020
Building plan approvalFile: APPROVAL LETTER.pdf15 Feb 2020
Building Plan Approval (IOD)File: AM PLAN .pdf15 Feb 2020
Building Plan Approval (IOD)File: APPROVAL LETTER.pdf15 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: 6 TH - PART 11th.pdf15 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 F Y 18-19.pdf9 Nov 2019
Building plan approvalFile: Amended Issue Letter.pdf21 May 2019
Building Plan Approval (IOD)File: Amended Issue Letter.pdf21 May 2019
Commencement Certificates / NA Order for plotted developmentFile: 10th part 04-01-2019.pdf21 May 2019
Certificates of CA (Form 5)File: Form 5.pdf30 Sep 2018
Building plan approvalFile: NEW IOD 09-03-2018.pdf6 Jun 2018
Building plan approvalFile: 12-05-2018 iod.pdf6 Jun 2018
Building Plan Approval (IOD)File: 12-05-2018 iod.pdf6 Jun 2018
Building Plan Approval (IOD)File: NEW IOD 09-03-2018.pdf6 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: 8TH FLOOR 29-05-2018.pdf6 Jun 2018
Building plan approvalFile: ATMARAM IOD PLAN.pdf29 Jul 2017
Building plan approvalFile: ATMARAM IOD PLAN.pdf29 Jul 2017
Layout approvalFile: ATMARAM IOD PLAN.pdf29 Jul 2017
PAN CardFile: LLP PANCARD.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE REPORT PMM.pdf29 Jul 2017
Details of encumbrancesFile: PROMOTER LETTER.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: ATMARAM IOD PLAN.pdf29 Jul 2017
Building Plan Approval (IOD)File: ATMARAM IOD PLAN.pdf29 Jul 2017
Building Plan Approval (IOD)File: ATMARAM IOD PLAN.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: ATMARAM CC 1 ST.pdf29 Jul 2017
Declaration in FORM BFile: form b final.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE NRI.pdf29 Jul 2017
Proforma of Allotment letterFile: RERA Agreement.pdf29 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHANTI DHAM CHSLEKSAR ROAD BORIVALI WEST21CompletedJul 2015Jul 2015
SHANTI DHAMEKSAR ROAD BORIVALI WEST21CompletedJul 2015Jul 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 35 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ATMARAM CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near borivali west6,700+ in Mumbai Suburban

2 kmATMARAM CHSLCompleted 101Lapsed / revoked 67Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 305 registered projects within 2 km.

Builder: NAMOREALTY AND INFRA LLP

NAMOREALTY AND INFRA LLP has 2 registrations on MahaRERA, including ATMARAM CHSL and SHANTINIKETAN. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ATMARAM CHSL is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATMARAM CHSL?

The registered promoter entity is NAMOREALTY AND INFRA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATMARAM CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATMARAM CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATMARAM CHSL?

The professionals named in the filing: Architect: DREAMS INFRASTRUCTURE; Engineer: RAJE CONSULTANTS; Chartered Accountant: VAYEDA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATMARAM CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATMARAM CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATMARAM CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.