ReraGenieLog inGet a buyer report

Home / Browse projects / Atlas Royal - A

Registration lapsed No litigation declared Residential / Group Housing project

Atlas Royal - A

By Atlas Infratech Pvt.Ltd

RG-MH-77391 · RERA P51900013134 · Last updated on MahaRERA portal: 19 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 84 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

Atlas Royal - A is a Residential / Group Housing project by Atlas Infratech Pvt.Ltd in 400004, registered with MahaRERA as P51900013134 on 14 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 84 months from the original filing.

At a glance

Project

  • NameAtlas Royal - A
  • TypeResidential / Group Housing
  • Location
    • MUGHBHATCROSS LANE
    • 400004
  • Pincode400004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900013134
  • ReraGenie IDRG-MH-77391

Builder

  • NameAtlas Infratech Pvt.Ltd
  • Entity typeCompany
  • CINU70102MH2009PTC192732
  • GSTIN27AAICA0003E1ZF
  • Managing DirectorsNaresh Raichand Jain, Mahendra Kiritkumar Shah
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseDec 2018Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Sep 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed79 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Atlas RoyalNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Atlas Royal: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 19 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Tower Parking MechanismYes65%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,080 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Sep 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI7410.44
Proposed, not sanctioned7,410 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch7 Sun Chember Dhobi Talao Opp Liberty Cinema Mumbai 400 020

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Atlas Infratech Pvt.Ltd-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900012116Dec 2018 → Mar 2023

Reason as filed by the promoterThe project has been completed in all aspects except parking tower for which we have already made payment to contractor, however the contractor has not done any work yet and we in process of getting the work completed through another contractor. We have also received MHADA NOC for OC

EXT51900001256Dec 2018 → Mar 2021

Reason as filed by the promoterWe have received MHADA NOC for Occupancy Certificate. The car lift work is pending from Vendor Side and accordingly OC is pending. Rest all work is done & possession to tenants already given on basis of MHADA NOC for Occupancy Certificate

EXT51900005912Dec 2018 → Mar 2021

Reason as filed by the promoterThe project is complete in all aspects. Further we have already obtained MHADA NOC for obtaining Occupancy Certificate. Obtaining OC is only a technical formality left and we are in process of the same.

EXT51900015325Dec 2018 → Dec 2025

Reason as filed by the promoterCar Parking Work has to be complete due first vendor M/s Sophus Elevetors Pvt.Ltd who was appointed and we have done the payment of Rs.42 lakhs has been gone into NCLT and now we are in process with other Car Parking M/s.Accord Elevevators for that Reason O.C. is Pending and we required time to complete the work of Car Parking

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Atlas A wing 10-10-2024.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Oct 2024
Certificates of CA (Form 3)File: FORM 3 A WING - converted.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory (1).pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Atlas A wing 10-10-2024.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Oct 2024
Certificates of CA (Form 3)File: FORM 3 A WING - converted.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory (1).pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Atlas A wing 10-10-2024.pdf19 Oct 2024
Certificates of CA (Form 3)File: FORM 3 A WING - converted.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory (1).pdf19 Oct 2024
Declaration in FORM BFile: FORM B A wing -.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A- 23-24 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A- 22-23 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A- 21-22 A wing.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 FY 24 A Wing.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 31st March 2024_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 30th June 2024_0001.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-april 24.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Declaration in FORM BFile: FORM B A wing -.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A- 23-24 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A- 22-23 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A- 21-22 A wing.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 FY 24 A Wing.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 31st March 2024_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 30th June 2024_0001.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-april 24.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Declaration in FORM BFile: FORM B A wing -.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 31st March 2024_0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: Atlas Royal A Wing 30th June 2024_0001.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd July 2024_0001_0001.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-april 24.pdf6 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera Architect Certificate - A Wing 3rd April 2024__0001.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A- 21-22 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A- 22-23 A wing.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A- 23-24 A wing.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 FY 24 A Wing.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Atlas Royal B Wing March 2023.pdf24 Feb 2024
CERSAI detailsFile: cersai declaration for Atlas Royal A.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 A wing FY 23.pdf18 Oct 2023
Details of encumbrances concerned to FinanceFile: 1B Details Of Encumbrance.pdf21 Apr 2023
Details of encumbrances concerned to LegalFile: 1B Details Of Encumbrance.pdf21 Apr 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate for Atlas Royal A.pdf21 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-1.pdf21 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Declaration Atlas Royal A.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arcitect Buldging Completion Certicate A wing.pdf6 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: A Wing - Mar 20 Form 5.pdf7 Dec 2021
Certificates of CA (Form 3)File: Form 3 - A - 15 Jun 2021.pdf15 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf25 Jun 2019
Certificates of CA (Form 5)File: Atlas Royal A Form 5.pdf25 Mar 2019
Layout approvalFile: layout Plan 01.pdf10 Aug 2017
Building plan approvalFile: IOD.pdf10 Aug 2017
PAN CardFile: Atlas - Pan Card.pdf10 Aug 2017
Copy of the legal title reportFile: Title Certificate - 330.pdf10 Aug 2017
Copy of the legal title reportFile: Title Certificate - 331.pdf10 Aug 2017
Copy of the legal title reportFile: Title Certificate - 323.pdf10 Aug 2017
Details of encumbrancesFile: Title Certificate - 323.pdf10 Aug 2017
Copy of Layout Approval (in case of layout)File: layout Plan 01.pdf10 Aug 2017
Building Plan Approval (IOD)File: IOD.pdf10 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: CC FOR RERA.pdf10 Aug 2017
Declaration in FORM BFile: Form B.pdf10 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf10 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineer.pdf10 Aug 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf10 Aug 2017
Proforma of Allotment letterFile: Draft Sale Agreement for RERA.pdf10 Aug 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Atlas RoyalSita Niwas Co-Operative Hsg.Ltd Mugbhat Cross Lane Girgaon Mumbai 400 0041CompletedDec 2017Jul 2017

Keep Atlas Royal - A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmAtlas Royal - ACompleted 13Lapsed / revoked 23Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: Atlas Infratech Pvt.Ltd

Atlas Infratech Pvt.Ltd has 3 registrations on MahaRERA, including Atlas Royal - A and Atlas Royal B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.

Frequently asked questions

What does it mean that Atlas Royal - A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Atlas Royal - A is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Atlas Royal - A?

The registered promoter entity is Atlas Infratech Pvt.Ltd, a company as per the filing. Its CIN U70102MH2009PTC192732 and GSTIN 27AAICA0003E1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Atlas Royal - A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Atlas Royal - A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Atlas Royal - A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Atlas Royal - A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Atlas Royal - A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.