ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / ATLANTA RESIDENCY PHASE I

Completed No litigation declared Residential / Group Housing project

ATLANTA RESIDENCY PHASE I

By SRI BALAJI DEVELOPER

RG-MH-85366 · RERA P51700007107 · Last updated on MahaRERA portal: 7 Nov 2020

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2019Possession promisedregistration recorded completed
15 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 97%
0Complaints at MahaRERAon this registration
Jump to the 20 documents Report an error

ATLANTA RESIDENCY PHASE I is a Residential / Group Housing project by SRI BALAJI DEVELOPER in Thane, Maharashtra, registered with MahaRERA as P51700007107 on 17 Aug 2017. The registration is recorded completed; possession was promised by 31 Mar 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameATLANTA RESIDENCY PHASE I
  • TypeResidential / Group Housing
  • Location
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700007107
  • ReraGenie IDRG-MH-85366

Builder

  • NameSRI BALAJI DEVELOPER
  • Entity typePartnership
  • GSTIN27ABTFS4394P1ZX
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerDAYANAND MOTIRAM CHORGE
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredAug 2017First promiseMar 2018Revised toMar 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion31 Mar 2019
  • Revised completionRevised to 31 Mar 2019 (originally 31 Mar 2018)
  • Buildings3 building records
  • Documents filed20 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 2 TYPE 05 - WING - GNA250000
BUILDING NO 3 TYPE - 05 - WING - HNA250000
BUILDING NO 4 TYPE - 05 - WING - INA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Nov 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 97%.

BUILDING NO 2 TYPE 05 - WING - G89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
BUILDING NO 3 TYPE - 05 - WING - H89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
BUILDING NO 4 TYPE - 05 - WING - I89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 7 Nov 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes97%
Storm Water DrainsYes97%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes97%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes75%
Open ParkingNoNot applicable

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered36
BuildingClosed/CoveredTotal
BUILDING NO 2 TYPE 05 - WING - G1212
BUILDING NO 3 TYPE - 05 - WING - H1212
BUILDING NO 4 TYPE - 05 - WING - I1212

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,041 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9462.15
Proposed, not sanctioned9,462 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLOOR NIRMAL DEEP OPP TALAO PALI DR MOOSE ROAD THANE WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAVRACHANA
EngineerEPICON CONSULTANT PVT LTD
EngineerR R CONSULTTING
PartnerRole in project
SRI BALAJI DEVELOPER-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001289Mar 2018 → Mar 2019

Reason as filed by the promoterThe Construction of the Project is completed fully @ 100 % . We shall be applying for Occupancy Certificate by 31st January , 2019 and expecting Occupancy Certificate on or before 31st March 2019. On account of slow down in Real Estate Sector owing to Demonetization and GST impact , fund flow is affected which has resulted in delay for application for Completion Certificate. Kindly grant us extension till 31st March , 2019.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Sep 2019

Documents filed20

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Phase I.pdf7 Nov 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf14 Sep 2019
OtherFile: Other.pdf14 Sep 2019
Certificates of CA (Form 5)File: Form 5 Atlanta Res Ph 1.pdf10 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf30 Mar 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: DECLARATION FOR SOCIETY PH I.pdf30 Mar 2018
Status of ConveyanceFile: DECLARATION FOR CONVEYANCE PH I.pdf30 Mar 2018
Building plan approvalFile: Layout.pdf30 Jul 2017
Layout approvalFile: Layout.pdf30 Jul 2017
PAN CardFile: PAN CARD.pdf30 Jul 2017
Copy of the legal title reportFile: TITLE REPORT-ilovepdf-compressed.pdf30 Jul 2017
Details of encumbrancesFile: Emcumbrances Phase 1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf30 Jul 2017
Building Plan Approval (IOD)File: Layout.pdf30 Jul 2017
Declaration in FORM BFile: Form B Phase 1.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase 1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase 1 FINAL.pdf30 Jul 2017
Certificates of CA (Form 3)File: Form 3 phase 1.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement Letter Phase 1.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Phase 1.pdf30 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ATLANTA RESIDENCY PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhiwandi (M Corp.)7,600+ in Thane

2 kmATLANTA RESIDENCY PHASE Completed 28Lapsed / revoked 23Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 85 registered projects within 2 km.

Builder: SRI BALAJI DEVELOPER

SRI BALAJI DEVELOPER has 3 registrations on MahaRERA, including ATLANTA RESIDENCY PHASE I and ATLANTA RESIDENCY PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ATLANTA RESIDENCY PHASE I is delayed beyond 31 Mar 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATLANTA RESIDENCY PHASE I?

The registered promoter entity is SRI BALAJI DEVELOPER, a partnership as per the filing. Its GSTIN 27ABTFS4394P1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATLANTA RESIDENCY PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATLANTA RESIDENCY PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATLANTA RESIDENCY PHASE I?

The professionals named in the filing: Architect: NAVRACHANA; Engineer: EPICON CONSULTANT PVT LTD; Engineer: R R CONSULTTING. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATLANTA RESIDENCY PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATLANTA RESIDENCY PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATLANTA RESIDENCY PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.