ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / ATLANTA EDENWORLD PHASE II

Registered No litigation declared Residential / Group Housing project

ATLANTA EDENWORLD PHASE II

By SAI BALAJI DEVELOPER

RG-MH-25733 · RERA P51700010796 · Last updated on MahaRERA portal: 27 Dec 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 99 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 99 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 39 documents Report an error

ATLANTA EDENWORLD PHASE II is a Residential / Group Housing project by SAI BALAJI DEVELOPER in Thane, Maharashtra, registered with MahaRERA as P51700010796 on 31 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 99 months from the original filing.

At a glance

Project

  • NameATLANTA EDENWORLD PHASE II
  • TypeResidential / Group Housing
  • Location
    • PIPE LINE ROAD
    • BHADWAD GOAN
    • Thane (M Corp.)
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700010796
  • ReraGenie IDRG-MH-25733

Builder

  • NameSAI BALAJI DEVELOPER
  • Entity typePartnership
  • GSTIN27ABUFS4949R1ZR
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersNARESH JAGDISH SHARMA, MANOJ ASHOK HIRANANDANI, KALPESH DAMJI GALA
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredAug 2017First promiseSep 2020Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Sep 2020)
  • Buildings2 building records
  • Documents filed39 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 12CNA250000
BUILDING NO 13CNA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

BUILDING NO 12C27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 13C27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area740 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBhiwandi Nizampur Sheher Mahanagarpalika
Permissible FSI6233.99
Proposed, not sanctioned5,343 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchARJUN TOWER 1ST FLOOR GOKHALE ROAD NAUPADA THANE WEST 400602

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SAI BALAJI DEVELOPER-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025845Sep 2020 → Dec 2028

Reason as filed by the promoterThe project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-12-2028. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera.

Litigation declared4

CaseCourtStatus
577/2014BHIWANDI COURTPENDING
187/2014BHIWANDI COURTPENDING
445/2015BHIWANDI COURTPENDING
716/2015BHIWANDI COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed39

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration About Commencent Certificate.pdf27 Dec 2024
Declaration in FORM BFile: Form B_compressed.pdf25 Dec 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrance.pdf23 Dec 2024
Proforma of Allotment letterFile: Allotment Letter.pdf23 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 20.pdf23 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 21.pdf23 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf23 Dec 2024
CERSAI detailsFile: Declaration of CERSAI - No Mortgage.pdf23 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf23 Dec 2024
Deviation Report with respect to Allotment letterFile: No deviation Allotment letter.pdf23 Dec 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrance.pdf23 Dec 2024
Deviation Report with respect to model copy of AgreementFile: No deviation AFS.pdf23 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 22.pdf23 Dec 2024
Proforma of Agreement for saleFile: AFS.pdf23 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf23 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 23.pdf23 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 24.pdf23 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecured Finance.pdf23 Dec 2024
Certificates of CA (Form 5)File: Form 5 Atlanta Edenworld Phase -II.pdf9 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 Mar 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration for Society.pdf29 Mar 2018
Status of ConveyanceFile: Declaration for Conveyance Deed.pdf29 Mar 2018
Layout approvalFile: IOD.pdf30 Jul 2017
Building plan approvalFile: IOD.pdf30 Jul 2017
PAN CardFile: SAI BALAJI PAN COPY.pdf30 Jul 2017
Copy of the legal title reportFile: T C COPY.pdf30 Jul 2017
Details of encumbrancesFile: EMCUMBACES.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf30 Jul 2017
Declaration in FORM BFile: FORM-B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE FORM -1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE FORM -2.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA CERTFICATE FORM -3.pdf30 Jul 2017
Proforma of Allotment letterFile: AGREEMENT LETTER.pdf30 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf30 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 99 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ATLANTA EDENWORLD PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHADWAD GOAN7,600+ in Thane

2 kmATLANTA EDENWORLD PHASE Completed 15Lapsed / revoked 12Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: SAI BALAJI DEVELOPER

SAI BALAJI DEVELOPER has 3 registrations on MahaRERA, including ATLANTA EDENWORLD PHASE II and ATLANTA EDENWORLD PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ATLANTA EDENWORLD PHASE II is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATLANTA EDENWORLD PHASE II?

The registered promoter entity is SAI BALAJI DEVELOPER, a partnership as per the filing. Its GSTIN 27ABUFS4949R1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATLANTA EDENWORLD PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATLANTA EDENWORLD PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in ATLANTA EDENWORLD PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATLANTA EDENWORLD PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATLANTA EDENWORLD PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.