Home / Browse projects / Mumbai Suburban, Maharashtra / Asmita Sand Dunes

Completed No litigation declared Others project

Asmita Sand Dunes

By Sun Developers

RG-MH-77038 · RERA P51800005600 · Last updated on MahaRERA portal: 6 Dec 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 54 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

Asmita Sand Dunes is a Others project by Sun Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005600 on 11 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NameAsmita Sand Dunes
  • TypeOthers
  • Location
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005600
  • ReraGenie IDRG-MH-77038

Builder

  • NameSun Developers
  • Entity typePartnership
  • PartnersNilesh Shantilal Tank, Kiran Shantilal Tank

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Asmita Sand DunesNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Asmita Sand Dunes: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Closed/Covered1
Open Space28

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,494 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8663.31
Proposed, not sanctioned8,474 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchshop no 12 to 17 Asmita Ascon Acres I Asmita Township Mira Road East Dist Thane 401107

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA A Architects
EngineerHiren M Tanna
PartnerRole in project
Sun Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001871Jun 2019 → Jun 2020

Reason as filed by the promoterDue to late BMC compliance OC of the building has been obtained up to 16th Floor instead of 20th Floor. We are in the process to get balance OC from 17th to 20th Floor ASAP.

EXT51800009518Jun 2019 → Jun 2021

Reason as filed by the promoterProject “Asmita Sand Dunes” having C.C. of basement+ground (Pt)+Stilt (Pt)+Podium+1st to 19th & 20th (Pt) upper flr as per approved amended plan dtd 10.06.2016(proposed for 20th full flr). Actual construction also completed till 97.5% (as per Architect certificate) i.e. 20th(Pt) upper floor at time of RERA registration & initiated O.C. process till 20th(Pt) upper flr from 6/10/2017 through our Arch. Pranav Shah. Part O.C. till 16th Flr issued on 29/05/2019 with condition mentioned therein which required to be complied by concern Corporation including but not limited to demolition of illegal st

EXT51800011248Jun 2019 → Dec 2023

Reason as filed by the promoterWe are writing to formally request an extension of the RERA (Real Estate Regulatory Authority) registration for our project, "Asmita Sand Dunes till 31.12.2023. It is pertinent to note that out of 101 Units, 66 units holder are in Possession With Occupation Certificate received prior to 31.12.2022. Balance 9 Unit Holder are been provided with the Possession with Occupation certificate in July 2023. And Balance 26 units are Unsold and the FORM 4 has been submitted. It is pertinent to note that from the 9 Unit Holder, we have obtained the consent of the 8 unit holder. As per MahaRera intimation,

Litigation declared3

CaseCourtStatus
1407/2012Bombay High Courtpending
1776/2011Dindoshi City Civil CourtNOM Hearing
576/2012Dindoshi City Civil Courtmatter is for filing of Reply to Chamber Summons filed by Plaintiff

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Jul 2023

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A for Financial Year 2019-20.pdf6 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A for Financial Year 2020-21.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 18 19 Sun Developers.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 19 20.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20 21.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21 22.pdf6 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final OC 13-7-2023.pdf22 Jul 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: REGISTRATION.pdf22 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Malad.pdf2 Sep 2022
CERSAI detailsFile: Cersai.pdf26 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf13 May 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf13 May 2021
Certificates of CA (Form 5)File: RERA Form 5 UDIN-1.pdf21 Jun 2019
Certificates of CA (Form 5)File: RERA Form 5 Certificate.pdf21 Jun 2019
OtherFile: Architech Certificate.pdf21 Jun 2019
OtherFile: Asmita Sand Dunes part OC 1.pdf30 May 2019
OtherFile: Asmita Sanddunes Part OC.pdf22 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf31 Jul 2017
Building plan approvalFile: IOD.pdf30 Jul 2017
Layout approvalFile: scan0213.pdf30 Jul 2017
Layout approvalFile: scan0216.pdf30 Jul 2017
Layout approvalFile: scan0215.pdf30 Jul 2017
PAN CardFile: Sun_Developers_PAN_CARD.pdf30 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf30 Jul 2017
Details of encumbrancesFile: Asmita Sand dunes non encumbrance.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0213.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0215.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0216.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Asmita Sand Dunes CC.pdf30 Jul 2017
Declaration in FORM BFile: Deccl form B.pdf30 Jul 2017
Proforma of Allotment letterFile: decl agrement.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Asmita Sand Dunes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmAsmita Sand DunesCompleted 203Lapsed / revoked 119Other 166Dot size: filed unitsN

Filed coordinates, straight-line distance. 488 registered projects within 2 km.

Builder: Sun Developers

Sun Developers has 1 registration on MahaRERA, including Asmita Sand Dunes. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Asmita Sand Dunes is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Asmita Sand Dunes?

The registered promoter entity is Sun Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Asmita Sand Dunes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Asmita Sand Dunes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Asmita Sand Dunes?

The professionals named in the filing: Architect: A A Architects; Engineer: Hiren M Tanna. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Asmita Sand Dunes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Asmita Sand Dunes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Asmita Sand Dunes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.