Registered No litigation declared Residential / Group Housing project

ASMITA GRAND MAISON

By ASMITA INDIA LIMITED

RG-MH-42520 · RERA P51700033489 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 85%
40 of 434Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

ASMITA GRAND MAISON is a Residential / Group Housing project by ASMITA INDIA LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700033489 on 22 Feb 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 394 of the 434 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameASMITA GRAND MAISON
  • TypeResidential / Group Housing
  • Location
    • NAYA NAGAR
    • MIRA ROAD EAST
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700033489
  • ReraGenie IDRG-MH-42520

Builder

  • NameASMITA INDIA LIMITED
  • Entity typeCompany
  • DirectorsDHARMESH HARENDRA UPADHYAYA, JAYANT SUNDERDAS FATNANI, RUKHSAR SYED MUZAFFAR SYED HUSSAIN, SAYED NOORJAHAN BEGUM NAZAR HUSIEN, SYED MAZHAR MUZAFFAR HUSSAIN

Key dates

this monthRegisteredFeb 2022First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed106 files

Current status

91%394 of 434 units booked
56.4%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASMITA GRAND MAISON TOWER 1NA403321214226
ASMITA GRAND MAISON TOWER 2NA40332080208

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.

ASMITA GRAND MAISON TOWER 173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
ASMITA GRAND MAISON TOWER 274%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed441

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots441
Closed/Covered365
Open Space76
BuildingClosed/CoveredOpen SpaceTotal
ASMITA GRAND MAISON TOWER 118338221
ASMITA GRAND MAISON TOWER 218238220

Land and ownership11

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,537 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jun 2026
LandownerVillageDistrict
SYED NAZAR HUSSAINMira-Bhayandar (M Corp.)Thane
Madhukant Chandulal ShahMira-Bhayandar (M Corp.)Thane
Mayurdwaj Chandulal ShahMira-Bhayandar (M Corp.)Thane
Kiran Chandulal ShahMira-Bhayandar (M Corp.)Thane
Haren Chandulal ShahMira-Bhayandar (M Corp.)Thane
Chandrakant Bhaidas ShahMira-Bhayandar (M Corp.)Thane
Vipinchandra Bhaidas ShahMira-Bhayandar (M Corp.)Thane
Pramilabai Narottamdas ShahMira-Bhayandar (M Corp.)Thane
Nikunj Dinesh ShahMira-Bhayandar (M Corp.)Thane
Birju Dinesh ShahMira-Bhayandar (M Corp.)Thane
Hansaben Dinesh ShahMira-Bhayandar (M Corp.)Thane

Approvals and building plan

Permissible FSI32392.58
Proposed, not sanctioned32,393 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA ROAD EAST, THANE
Estimated costRs 436.39 cr
Cost incurredRs 246.23 cr
Work done56.42%
BuildingWingEstimatedIncurred
ASMITA GRAND MAISON TOWER 1NARs 210.69 crRs 123.12 cr
ASMITA GRAND MAISON TOWER 2NARs 210.69 crRs 123.12 cr
-NARs 15.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEJS CONSULTANTS Basavraj Gadekar
EngineerADARSH CONSULTANT
Chartered AccountantANIL A MASAND
Chartered AccountantD R VAGADIA & CO
PartnerRole in project
ASMITA INDIA LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700016581Dec 2026 → Dec 2027

Reason as filed by the promoter(A) We had received Part Commencement Certificate (CC) issued by Mira- Bhayandar Municipal Corporation vide MNP/NR/3135/2021-2022 dated 30/12/2021 for Tower T-1 Part Ground Floor + First Floor admeasuring proposed Area 763.87 Sq Mtrs and for Tower T-2 Part Ground Floor + 6 Part Podium + 7 to 29 Floors admeasuring proposed construction Area 13540.77 Sq. Mtrs totally admeasuring 14304.64 Sq. Mtrs. (B) After getting Part CC We had applied to State Environment Impact Assessment Authority (SEIAA), Maharashtra vide proposal No. SIA/MH/MIS/70380/2021 dated 28/06/2022. We received Environment Clearanc

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 mar.pdf14 May 2026
Withdrawal Update Form 2File: Form-2 mar.pdf14 May 2026
Withdrawal Update Form 3File: form 3 march 26 final (1).pdf14 May 2026
Withdrawal Update Form 1File: FORM1.pdf12 May 2026
Withdrawal Update Form 1File: Form 1.pdf12 May 2026
Withdrawal Update Form 2File: FORM2.pdf12 May 2026
Withdrawal Update Form 2File: Annexure B Form 2.pdf12 May 2026
Withdrawal Update Form 3File: form3.pdf12 May 2026
Withdrawal Update Form 3File: form 3 dec 25 final.pdf12 May 2026
Withdrawal Update Form 1File: architect form 1 july 25.pdf16 Jan 2026
Withdrawal Update Form 2File: form2.pdf16 Jan 2026
Withdrawal Update Form 3File: form 3.pdf16 Jan 2026
Form 5 (FY 2024-2025)File: form.pdf20 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F FORM 5.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annexure F FORM 5.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F FORM 5.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annexure F FORM 5.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf13 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf8 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3N.pdf8 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Engineer's Certificate.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adarsh Consultant Engineer's Certificate.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 1 Engineer's Certificate.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Form 3.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form3.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2.pdf7 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf7 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Annual Report-CA Cert.pdf5 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf22 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf22 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf22 Jul 2023
Building plan approvalFile: 3.pdf3 Jun 2023
Building plan approvalFile: 4.pdf3 Jun 2023
Building plan approvalFile: 5.pdf3 Jun 2023
Building plan approvalFile: 6.pdf3 Jun 2023
PAN CardFile: PAN.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf3 Jun 2023
Declaration about Commencement CertificateFile: AIL - Format D.pdf3 Jun 2023
Declaration in FORM BFile: Affidavit cum Declaration.pdf3 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architect Cert.pdf3 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Cert.pdf3 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Site Supervisor.pdf3 Jun 2023
Disclosure of sold/ booked inventoryFile: AIL - Disclosure of Solid-Booked Inventory.pdf3 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CA Certificate.pdf3 Jun 2023
Layout approvalFile: CC Plan 1-6.pdf15 May 2023
Layout approvalFile: CC Plan 1-6.pdf15 May 2023
Building plan approvalFile: 2.pdf15 May 2023
Building plan approvalFile: 2.pdf15 May 2023
Building plan approvalFile: 2.pdf15 May 2023
Copy of Layout Approval (in case of layout)File: CC Plan 1-6.pdf15 May 2023
Copy of Layout Approval (in case of layout)File: CC Plan 1-6.pdf15 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf15 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf15 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf15 May 2023
Proforma of Agreement for saleFile: Asmita Grand Maison Agreement Final.pdf26 Apr 2023
Proforma of Allotment letterFile: Allottment Letter.pdf26 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: AIL - New Revised Approved CC.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Adobe Scan 03-Feb-2023.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf2 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adarsh Consultant Form 2 Engineer Certificate.pdf2 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate FORM 3.pdf2 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf25 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 May 2022

How this compares with Thane

91%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASMITA GRAND MAISON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIRA ROAD EAST7,600+ in Thane

2 kmASMITA GRAND MAISONCompleted 17Lapsed / revoked 11Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 67 registered projects within 2 km.

Builder: ASMITA INDIA LIMITED

ASMITA INDIA LIMITED has 1 registration on MahaRERA, including ASMITA GRAND MAISON. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ASMITA GRAND MAISON is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASMITA GRAND MAISON?

The registered promoter entity is ASMITA INDIA LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASMITA GRAND MAISON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASMITA GRAND MAISON?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASMITA GRAND MAISON?

The professionals named in the filing: Architect: TEJS CONSULTANTS Basavraj Gadekar; Engineer: ADARSH CONSULTANT; Chartered Accountant: ANIL A MASAND; Chartered Accountant: D R VAGADIA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASMITA GRAND MAISON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASMITA GRAND MAISON. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASMITA GRAND MAISON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.