ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ASHIYANA

Registered No litigation declared Others project

ASHIYANA

By S R KULKARNI REALTORS

RG-MH-21953 · RERA P52100029929 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
8 of 11Construction stages donefurthest along: Internal walls, 96%
34 of 51Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

ASHIYANA is a Others project by S R KULKARNI REALTORS in Pune, Maharashtra, registered with MahaRERA as P52100029929 on 15 Jul 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 17 of the 51 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameASHIYANA
  • TypeOthers
  • Location
    • LAW COLLEGE ROAD
    • SHIVAJINAGAR
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029929
  • ReraGenie IDRG-MH-21953

Builder

  • NameS R KULKARNI REALTORS
  • Entity typePartnership
  • PartnersSANJAY RAMCHANDRA KULKARNI, VINAY RAMCHANDRA KULKARNI, DEVDATTA VIKAS KULKARNI, NACHIKET ARUN CHIDGOPKAR, INDRAJIT VIKAS KULKARNI, YATIN SANJAY KULKARNI

Key dates

this monthRegisteredJul 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jul 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed118 files

Current status

33%17 of 51 units booked
103.5%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASHIYANANA191005151

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 96%.

ASHIYANA: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises96%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.96%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,862 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
S R KULKARNI REALTORSPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI10420.67
Proposed, not sanctioned8,120 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 2/3, Atlanta Building, Ground Floor, Nariman Point, Mumbai 400 021
Estimated costRs 64.46 cr
Cost incurredRs 66.72 cr
Work done103.5%
BuildingWingEstimatedIncurred
ASHIYANANARs 64.46 crRs 66.72 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMUKTA S KULKARNI
ArchitectMukta Kulkarni Architects
EngineerBALKRISHNA SARODE
EngineerYatin Kulkarni
Chartered AccountantKISHOR WAGH
Chartered AccountantCA Jayant Prabhakar Kamat
Chartered AccountantWagh Kulkarni and Associates
Chartered AccountantD. Y. Jayade And Co.
PartnerRole in project
S R KULKARNI REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19122518779Dec 2025 → Dec 2026

Reason as filed by the promoterThe project construction is substantially completed, and Part Occupancy Certificate (Part OC) has already been received for the completed portion. Only a minor balance work related to parking area development is pending, which is in progress and will be completed shortly. The remaining Occupancy Certificate (OC) for the full project is under process with the competent authority and will be obtained upon completion of the parking area work. Additionally, a few units in the project are still unsold, and as per RERA requirements, the registration must remain valid until all statutory approvals ar

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Aashiyana01.pdf20 Jul 2026
Withdrawal Update Form 2File: Form2 200726.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 200726.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate SR kulkarni Realtors mARCH 26.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate SR kulkarni Realtors mARCH 26.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate SR kulkarni Realtors mARCH 26.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf4 May 2026
Withdrawal Update Form 2File: Form2 31326.pdf4 May 2026
Withdrawal Update Form 3File: FORM 3 Dec 25.pdf4 May 2026
Withdrawal Update Form 3File: FORM 3 Dec 25.pdf4 May 2026
Withdrawal Update Form 3File: Form3 31326.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Ashiyana.pdf23 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf23 Mar 2026
Withdrawal Update Form 3File: FORM 3 Dec 25.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 Sep 25 Signed.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 30 06 24 S R Kulkarni Realtors.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 30 06 24 S R Kulkarni Realtors.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 Sep 25 Signed.pdf19 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 - rera Dec 24.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 24 S R Kulkarni Realtors.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 24 S R Kulkarni Realtors.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engg Certificate Dec 24_compressed.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec 24.pdf22 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Dec 24.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Architect Certificate.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 300924.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30924.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold 30924.pdf22 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 30924.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate form 1 (2).pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Engg Certificate June 24.pdf23 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Rera Quality Certificate June 24.pdf23 Jul 2024
Disclosure of sold/ booked inventoryFile: Rera Sold Unsold.pdf23 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 06 24 S R Kulkarni Realtors.pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 24 Rera Certificate Form 1.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng certificate S R Kulkarni Realtors310324.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 03 24 S R K REALTORS.pdf22 Apr 2024
Declaration about Commencement CertificateFile: Format D.pdf27 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf27 Feb 2024
Other - TechnicalFile: Format A.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: Circular 29 (1).pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 30623.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 30923.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 301223.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 23 S R K REALTORS-2.pdf23 Jan 2024
Proforma of Agreement for saleFile: Agreement to sale.pdf23 Jan 2024
PAN CardFile: PAN.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 30062023SRK Realtors Ashiyana.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 30092023SRK Realtors Ashiyana.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5 MArch 2023 S R Kulkarni Realtors.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate (Ashiyana).pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Realtors Sold -Unsold.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -June 22.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sept 22.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 - Dec 22.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- March 23.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - June 22.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Sept 22.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Dec 22.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A March 23.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 RERA 3062022.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 RERA 3092022.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 RERA 31122022.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032023 .pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form No 5 MArch 2022.pdf27 Jul 2023
Details of encumbrancesFile: Bajaj Letter.pdf12 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_Aashiyana.pdf12 Jul 2023
Building plan approvalFile: Sheet 01_compressed.pdf29 Jun 2023
Building plan approvalFile: Sheet 02_compressed.pdf29 Jun 2023
Building plan approvalFile: Sheet 03_compressed.pdf29 Jun 2023
Building plan approvalFile: Sheet 04_compressed.pdf29 Jun 2023
Building plan approvalFile: Sheet 05_compressed.pdf29 Jun 2023

How this compares with Pune

33%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASHIYANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIVAJINAGAR13,700+ in Pune

Builder: S R KULKARNI REALTORS

S R KULKARNI REALTORS has 1 registration on MahaRERA, including ASHIYANA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ASHIYANA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASHIYANA?

The registered promoter entity is S R KULKARNI REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASHIYANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASHIYANA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASHIYANA?

The professionals named in the filing: Architect: MUKTA S KULKARNI; Architect: Mukta Kulkarni Architects; Engineer: BALKRISHNA SARODE; Engineer: Yatin Kulkarni; Chartered Accountant: KISHOR WAGH; Chartered Accountant: CA Jayant Prabhakar Kamat. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASHIYANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHIYANA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHIYANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one