Home / Browse projects / Pune, Maharashtra / Ashiana Malhar Phase 4

Registered No litigation declared Residential / Group Housing project

Ashiana Malhar Phase 4

By Ashiana Housing Limited

RG-MH-94635 · RERA PR1260002501981 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
86 of 110Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 11 documents Report an error

Ashiana Malhar Phase 4 is a Residential / Group Housing project by Ashiana Housing Limited in Pune, Maharashtra, registered with MahaRERA as PR1260002501981 on 1 Jan 2026. Possession is promised by 30 Sep 2029. 24 of the 110 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameAshiana Malhar Phase 4
  • TypeResidential / Group Housing
  • Location
    • MARUNJI ROAD
    • Pune
    • Marunji
    • Mulshi
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1260002501981
  • ReraGenie IDRG-MH-94635

Builder

  • NameAshiana Housing Limited
  • Entity typeCompany
  • CINL70109WB1986PLC040864
  • GSTIN27AADCA9093P1ZX
  • Managing DirectorVishal Gupta
  • DirectorsAnkur Gupta, Varun Gupta, Abhishek Dalmia, Sonal Mattoo, Piyul Mukherjee, Narayan NA Anand
  • Other registrations7 more →
  • Declared earlier projects32 →

Key dates

this monthRegisteredJan 2026PromisedSep 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Jan 2026
  • Promised completion30 Sep 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed11 files

Current status

22%24 of 110 units booked
7.7%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA15141100110

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Tower 1: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo75%
Sewerage (Chamber, Lines, Septic Tank , STP)No75%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNo100%
Treatment And Disposal Of Sewage And Sullage WaterNo100%
Solid Waste Management And DisposalNo100%
Water conservation /Rain water harvestingNo11%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNo0%

Parking filed257

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots257
Open Space188
Stilt / Ground69

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area93,990 sq m
Land owned byNot the promoter
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Nov 2025
LandownerVillageDistrict
MADAN SHANTILAL JAIN-Pune
PURUSHOTTAM MUKUNDDAS LOHIA-Pune
VIJAYKUMAR SANTOSHCHAND JAINMumbai CityMumbai City
MS HINDUMAL BALMUKUND INVESTMENT CO PVT LTD-Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI9666.26
Proposed, not sanctioned9,666 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKP HOUSING SOCIETYGEN. THIMAYA RAODEAST STREET CAMPPUNEMAHARASHTRA411001
Estimated costRs 28.97 cr
Cost incurredRs 2.22 cr
Work done7.66%
BuildingWingEstimatedIncurred
Tower 1NARs 23.59 crRs 95.96 lakh
-NARs 5.38 crRs 1.26 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjeev Mehta
ArchitectMangesh Gotal
EngineerMS JW consultant LLP
EngineerRamshankar Sharma
EngineerSagar Kale
Chartered AccountantSAC & Co LLP
Chartered AccountantB.Chhawchharia & Co.
PartnerRole in project
Ashiana Housing Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Nov 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2029

Documents filed11

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 M4.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 - M4.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 M4_compressed.pdf24 Apr 2026
Layout approvalFile: 2-14.pdf19 Dec 2025
Declaration and undertaking (Annexure A)File: Order 50 Annexure A - print.pdf18 Dec 2025
Layout approvalFile: 1-14 Lay Out_compressed.pdf18 Dec 2025
Layout approvalFile: Malhar Plan shaded.pdf18 Dec 2025
Layout approvalFile: 220503 Ashiana Malhar Phasing Plan F-Model (1).pdf26 Nov 2025
Building plan approvalFile: 7-14 Section AA & Elevation_compressed.pdf26 Nov 2025
Building plan approvalFile: 5-14 T1,4,6,7_compressed.pdf20 Nov 2025
Building plan approvalFile: 3-14 Parking Layout_compressed.pdf20 Nov 2025

Promoter's earlier projects33

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

31 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Anmol Phase III and Plaza Phase IIrevenue estate of Village-Dhulena Sector 33 Tehsil-Sohna Distt Gurgaon Haryana300OngoingDec 2028Dec 2028
Ashiana MalharMarunji Taluka Mulshi District Pune Maharashtra220OngoingOct 2026Oct 2026
Ashiana Tarang Phase IVBRevenue Village of Milakpur Gurjar Tehsil Tijara Bhiwadi Distt Alwar Rajasthan48OngoingJun 2026Jun 2026
Ashiana Shubham Phase IVBSengundram Village Govindapuram Hamlet Maraimalai Nagar Municipal Limit Chengalpet Tamil Nadu140OngoingDec 2025Dec 2025
Ashiana Tarang Phase IVARevenue Village of Milakpur Gurjar Tehsil Tijara Bhiwadi Distt. Alwar Rajasthan26OngoingNov 2025Nov 2024
Ashiana Amantran Phase IIIvillage Keshopura Tehsil Sanganer Jaipur224OngoingAug 2025Aug 2025
Ashiana Amantran Phase-IIJaipur56OngoingJun 2025Jun 2025
AshianaAmantran Phase-IJaipur224OngoingDec 2024Dec 2024
Ashiana Nirmay Phase IVBhiwadi151OngoingDec 2024Dec 2024
Ashiana Dwarka Phase IVJodhpur96OngoingOct 2024Oct 2024
Ashiana Daksh Phase-IIJaipur192OngoingOct 2024Oct 2024
Ashiana Tarang-IIIBhiwadi96CompletedJul 2024Jul 2024
Ashiana Daksh, Phase-IJaipur341CompletedJul 2024Jul 2024
Ashiana Daksh Phase IIIVillage Srikishanpura Tehsil Sanganer Distt Jaipur Rajasthan96CompletedJul 2024Jul 2024
Ashiana Shubham Phase IVASengundram Village Govindapuram Hamlet Maraimalai Nagar Municipal Limit Chengalpet Taluk Kancheepuram District Tamil Nadu220CompletedMar 2024Mar 2024
Ashiana Aditya Phase-IIJamshedpur200CompletedJan 2024Jan 2024
Ashiana Aditya Phase-IJamshedpur250CompletedJun 2023Jun 2021
Ashiana Dwarka Phase IIIJodhpur96CompletedMay 2023May 2023
Ashiana Dwarka Phase IIJodhpur96CompletedMay 2023May 2023
Ashiana SeharJamshedpur239CompletedJan 2023Jan 2023
AshianaNirmay Phase IIIBhiwadi192CompletedDec 2022Dec 2022
Ashiana Shubham Phase IIISengundram Village Govindapuram Hamlet Maraimalai Nagar Municipal Limit Chengalpet Taluk Kancheepuram Chennai Tamil Nadu172CompletedOct 2022Oct 2022
Ashiana Tarang-IIBhiwadi48CompletedMay 2022May 2022
Ashiana Umang Phase IVJaipur192CompletedOct 2021Oct 2021
Ashiana Umang Ph-V and Umang PlazaJaipur304OngoingOct 2021Late, Oct 2024
AshianaNirmay Phase IIBhiwadi96CompletedMay 2021May 2021
Ashiana Shubham Phase IISengundram Village Govindapuram Hamlet Maraimalai Nagar Municipal Limit Chengalpet Taluk Kancheepuram District Tamil Nadu144CompletedMar 2021Mar 2021
Ashiana SeharJamshedpur239CompletedJan 2021Jan 2021
Anmol Phase Irevenue estate of Village-Dhunela Sector 33 Tehsil- Sohna Distt Gurugram Haryana300CompletedOct 2020Oct 2020
Anmol Phase IIrevenue estate of Village-Dhunela Sector 33 Tehsil- Sohna Distt Gurugram Haryana280CompletedApr 2020Apr 2020
Ashiana Dwarka EWS/LIGJodhpur102CompletedMay 2019May 2019
AshianaTarang Phase IABhiwadi104CompletedApr 2019Late, Apr 2021
Ashiana Shubham Phase ISengundram Village Govindapuram Hamlet Maraimalai Nagar Municipal Limit Chengalpet Taluk Kancheepuram District Tamil Nadu144CompletedJun 2017Jun 2017

How this compares with Pune

22%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ashiana Malhar Phase 4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

2 kmAshiana Malhar Phase 4Completed 11Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: Ashiana Housing Limited

Ashiana Housing Limited has 8 registrations on MahaRERA, including Ashiana Malhar Phase I and Commercial Block and Ashiana Amodh Phase I. Its filings disclose 32 earlier MahaRERA projects: declares 30 of 32 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ashiana Malhar Phase 4 is delayed beyond 30 Sep 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ashiana Malhar Phase 4?

The registered promoter entity is Ashiana Housing Limited, a company as per the filing. Its CIN L70109WB1986PLC040864 and GSTIN 27AADCA9093P1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ashiana Malhar Phase 4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ashiana Malhar Phase 4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ashiana Malhar Phase 4?

The professionals named in the filing: Architect: Sanjeev Mehta; Architect: Mangesh Gotal; Engineer: MS JW consultant LLP; Engineer: Ramshankar Sharma; Engineer: Sagar Kale; Chartered Accountant: SAC & Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ashiana Malhar Phase 4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ashiana Malhar Phase 4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ashiana Malhar Phase 4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.