Registered No litigation declared Residential / Group Housing project

ASHA KIRAN

By ASHAPURA DEVELOPERS

RG-MH-30357 · RERA P51700033042 · Last updated on MahaRERA portal: 8 Jan 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
16 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

ASHA KIRAN is a Residential / Group Housing project by ASHAPURA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700033042 on 3 Feb 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameASHA KIRAN
  • TypeResidential / Group Housing
  • Location
    • DIVA
    • AGASAN
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • RERA no.P51700033042
  • ReraGenie IDRG-MH-30357

Builder

  • NameASHAPURA DEVELOPERS
  • Entity typePartnership
  • PartnersROHAN BABUBHAI DHOLU, LILAVATI BABUBHAI DHOLU, DEEP RAMESH DHOLU, RAMESH NARAN DHOLU
  • Other registrations7 more →
  • Completed1 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2022First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2023)
  • Buildings2 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA30000
Building BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

Building A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 8 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered7
Open Space11

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area800 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
LandownerVillageDistrict
Shantabai Vaman MhatreThane (M Corp.)Thane
Bebibai Vaman MhatreThane (M Corp.)Thane
Shailesh Vaman MhatreThane (M Corp.)Thane
AvinashVaman MhatreThane (M Corp.)Thane
Sitabai Pandurang PatilThane (M Corp.)Thane

Approvals and building plan

Permissible FSI730.08
Proposed, not sanctioned730 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGhatkopar Mumbai

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJoshi Deshware & Associates
EngineerShanti Consltutants
Chartered AccountantH V patel and Associates
PartnerRole in project
ASHAPURA DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019405Dec 2023 → Dec 2024

Reason as filed by the promoteras per attachment

EXT51700027100Dec 2023 → Dec 2026

Reason as filed by the promoterThere are 97% of the completion of the project as on date 31/12/2025. There are very few booking in the project. Due to liquidity issue we are unable to complete the project within time limit as provided by RERA. Hence, we are requesting you for extension for completion of the project up to 31/12/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf8 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01 Asha kiran- Architect Certificates Mar 22.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 02 Asha Kiran Architect Certificates Jun 22.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 03 Asha Kiran Architect Certificates for Sep 22.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 04 Asha Kiran Architect Certificates Dec 22.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05 Architect Certificates Mar 23.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06 Architect Certificates Jun 23.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 07 Architect Certificates for Sep 23.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08 Architect Certificates Dec23.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 09 Architect Certificates Mar 24.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 01 Engineers Certificates Mar 22.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 Engineers Certificates Jun 22.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 03 Engineers Certificates Sep 22.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04 Engineers Certificates Dec 22.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05 Engineers Certificates Mar 23.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 06 Engineers Certificates Jun 23.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 07 Engineers Certificates Sep 23.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 08 Engineers Certificates Dec 23.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 09 Engineers Certificates Mar 24.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificates Form 2A Mar 22.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificates Form 2A Mar 23.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificates Form 2A Mar 24.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 01 C A CARTIFICET for rera Mar 22.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 02 C A CARTIFICET for rera Jun 22.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03 C A CARTIFICET for rera Sep 22.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 04 C A CARTIFICET for rera Dec 22.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 05 C A CARTIFICET for rera Mar 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 06 C A CARTIFICET for rera Jun 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07 C A CARTIFICET for rera Sep 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 08 C A CARTIFICET for rera Dec 23.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 09 C A CARTIFICET for rera Mar 24.pdf13 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Engineers Certificates Form 2A Mar 23.pdf13 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Engineers Certificates Form 2A Mar 24.pdf13 Jun 2024
Declaration in FORM BFile: Affidavit cum Declaration Form B.pdf12 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Asha Kiran Dec 23.pdf26 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Asha Kiran Dec 23.pdf26 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Ashapura Developers.pdf11 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf13 Jan 2022
Details of encumbrancesFile: Combined Encr Certi Co promotor.pdf25 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect ertificate Bld 1.pdf25 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arrchitect Certificate Bld 2.pdf25 Dec 2021
OtherFile: Declaration About SRO Query.pdf25 Dec 2021
OtherFile: BANM Certificate final.pdf4 Dec 2021
Layout approvalFile: Approved Layout plan mail dt140821-compressed.pdf3 Dec 2021
Building plan approvalFile: Approved Layout plan mail dt140821-compressed.pdf3 Dec 2021
Copy of the legal title reportFile: Title report_compressed.pdf3 Dec 2021
Copy of Layout Approval (in case of layout)File: Approved Layout plan mail dt140821-compressed.pdf3 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Approved Layout plan mail dt140821-compressed.pdf3 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: CC_26-10-2021.pdf3 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf3 Dec 2021
Declaration about Commencement CertificateFile: Declaration abt CC_new.pdf2 Nov 2021
Proforma of Allotment letterFile: Draft of Proforma Agreement_compressed.pdf2 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engg Certificate_compressed.pdf1 Sep 2021
PAN CardFile: Pan Card.pdf30 Jul 2021
Details of encumbrancesFile: Encr Certificate _Promotor.pdf30 Jul 2021
Declaration in FORM BFile: Form B_Promotor_compressed.pdf30 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Ashapura Dev_Final.pdf30 Jul 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASHA KIRAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AGASAN7,600+ in Thane

Builder: ASHAPURA DEVELOPERS

ASHAPURA DEVELOPERS has 8 registrations on MahaRERA, including NEELKANTHDHARA and ANANT CORNER. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ASHA KIRAN is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASHA KIRAN?

The registered promoter entity is ASHAPURA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASHA KIRAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASHA KIRAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASHA KIRAN?

The professionals named in the filing: Architect: Joshi Deshware & Associates; Engineer: Shanti Consltutants; Chartered Accountant: H V patel and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASHA KIRAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHA KIRAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHA KIRAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.